BLD-Final | 7/6/2009 | 7/6/2009 | 7/6/2009 | P | PASS |
Tony Young
|
|
|
ruston Phone #: ###-####
|
DOC - Permit Finaled | 7/6/2009 | 7/6/2009 | 7/6/2009 | P | PASS |
Tony Young
|
|
|
c of o faxed
|
BLD-Final | 7/2/2009 | 7/2/2009 | 7/6/2009 | P | PART |
Tony Young
|
|
|
ruston Phone #: ###-#### need trades
|
BLD-Energy code compliance | 6/2/2009 | 6/2/2009 | 6/2/2009 | P | PASS |
Jim Sly
|
|
|
Rustin Phone #: ###-####
|
BLD-Framing/Rough-in | 5/29/2009 | 6/1/2009 | 6/1/2009 | A | PASS |
Jim Sly
|
|
|
Ruston Phone #: ###-####
|
BLD-Framing/Rough-in | 5/29/2009 | 5/29/2009 | 5/29/2009 | P | PART |
Tony Young
|
|
|
as late as possible please--Russ Phone #: ###-####,, c/n posted
|
BLD-Footing | 5/11/2009 | 5/11/2009 | 5/11/2009 | P | PASS |
Tony Young
|
|
|
Rustin Phone #: ###-####
|
BLD-Footing | 5/8/2009 | 5/11/2009 | 5/11/2009 | A | NR |
Tony Young
|
|
|
Rustin Phone #: ###-#### cutting a tree down,, fell inside ftg area
|
Route to Impact Fee Review | 9/29/2008 | 10/2/2008 | 5/4/2009 | | PASS |
Cindy M. Gould
|
|
|
No impact fees, existing house on lot will be demolished withing 30 days of completion of new structure.
|
Case Summary (BLD) | | | 5/4/2009 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/4/2009 | | DONE |
|
|
|
|
Telephone call | | | 5/4/2009 | | DONE |
|
|
|
stan here to pick it up
|
Permit Ready to Issue | | | 5/4/2009 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 5/4/2009 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (BSP) | 4/30/2009 | 4/30/2009 | 5/1/2009 | | PASS |
Ben S. Pavelka
|
|
|
5/1/2009 16:12:11 BSP - activity updated through activity BLDA022 from case BLD08-02100.
|
Routing - PLAN CHECK | 4/29/2009 | | 5/1/2009 | | PASS |
Ben S. Pavelka
|
|
|
|
Case Summary (BLD) | | | 5/1/2009 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/1/2009 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 4/30/2009 | | |
Ben S. Pavelka
|
|
|
|
1st review completed | | | 4/30/2009 | | |
Ben S. Pavelka
|
|
|
Need a new res check, new floor joists specs, and a window size provided. 4-30-09 BSP
|
Routing - PLANNING | 4/29/2009 | | 4/29/2009 | | PASS |
Lucinda Grames
|
|
|
New site plans obtained with front yard setback at 40 feet.
|
Routing - PUBLIC WORKS | 4/29/2009 | | 4/29/2009 | | PASS |
Louise Waldorf
|
|
|
|
Routing - PLANNING Land Div | 4/24/2009 | | 4/24/2009 | | PASS |
Todd Tucker
|
|
|
Schinnerer Subdivision has been recorded. Property is legal lot.
|
CHANGE STATUS TO (REV) | | | 4/23/2009 | | DONE |
Ben S. Pavelka
|
|
|
Applicant sent in a letter requesting extension on 4-22-09 BSP
|
Meeting | | | 9/30/2008 | | PART |
Bob Archibald
|
|
|
Spoke with Stan Stetson, he requested a delayed demolition of the existing dwelling until completion of new dwelling. I informed Stan that a bond for $3500 be posted and that the existing structure was to be removed within 30 days of new structures completion.
|
Routing - Addressing | 9/29/2008 | | 9/29/2008 | | PASS |
Chris Pichardo
|
|
|
|
Application received | | 9/29/2008 | | | |
Marsha Smylie
|
|
|
|
Routing - PLANNING | 9/29/2008 | | | | FAIL |
Lucinda Grames
|
|
|
Wait for legal lot verification..
|
Routing - PLANNING | 4/24/2009 | | | | FAIL |
|
|
|
Per setback quidelines for Sycamore Overlay house must be built with a front setback of 40 feet. Spoke with Shelly Strate and Stan Ray of Stetson homes on 4-28-09 and let them know of this requirement.
|