To construct a +/- 25' X 25' Trellis shade structure. Work to include 14" diameter concrete footings, 6X6 pressure treated wood columns, 2X6 wood trusses, 6X6X12 wood beams, and wood braces in the long direction per approved plans, all engineering, and the attached plan review report. DRH08-00334, CZC08-00154 per Planning and Zoning.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice BLD1/29/20091/29/20092/9/2009 DONE
DetailsCathy Brown
Second Notice has not been responded to.
Second Notice BLD1/16/20091/16/20091/29/2009 DONE
DetailsCathy Brown
First Notice has not been responded to.
First Notice12/31/200812/31/20081/16/2009 DONE
DetailsTony Young
BLD-Final12/30/200812/31/200812/31/2008APASS
DetailsTony Young
Phone #: ###-#### Internet Inspection Request from: Jessica Noland
DOC - Permit Finaled12/31/200812/31/200812/31/2008PPASS
DetailsTony Young
BLD-Final12/17/200812/18/200812/18/2008ANR
DetailsMike Jordan
Phone #: ###-#### Internet Inspection Request from: Jessica Noland. Needs elec. final.
BLD-Foundation12/9/200812/10/200812/11/2008PPART
DetailsTony Young
Phone #: ###-#### Internet Inspection Request from: Jessica Noland
columns appear ok,, poured
Telephone call  10/17/2008 DONE
Details
t/c w david mckinnon at ###-#### - permit ready and fees given
Permit Ready to Issue  10/17/2008 DONE
Details
Issue PAID IN FULL permit  10/17/2008 DONE
DetailsTisha Gallop
Routing - Erosion and Sediment10/16/2008 10/16/2008 PASS
DetailsSteven Webb
ESC plan approved with attached conditions. ESC08-00906
Routing - PLAN CHECK10/16/2008 10/16/2008 PASS
DetailsSam Zahorka
SAM Z.
PLANS/APPL TAKEN TO FRONT DESK  10/16/2008 DONE
DetailsSam Zahorka
Inspection Record Card- Bld  10/16/2008 DONE
Plan assigned to (SRZ)10/3/200810/3/200810/15/2008 PASS
DetailsSam Zahorka
10/15/2008 13:46:52 SRZ - activity updated through activity BLDA022 from case BLD08-02132.
Plan Reviewer's activity  10/15/2008 DONE
DetailsSam Zahorka
Due to structure being a Temporary shade Trellis, a minimum of 5'-0" fire separation will be maintained from edge of projections to zero lot line per George Slain the Boise City Building Official. (SRZ)
Routing - PLAN CHECK10/13/2008 10/15/2008 PASS
DetailsSam Zahorka
PLANS/APPL TAKEN TO FRONT DESK  10/15/2008 DONE
DetailsSam Zahorka
Case Summary (BLD)  10/15/2008 DONE
Inspection Record Card- Bld  10/15/2008 DONE
Plan resubmittals received  10/13/2008 DONE
DetailsSam Zahorka
Recieved Engineering as requested.
Routing - PLAN CHECK10/13/2008 10/13/2008 FAIL
DetailsSam Zahorka
New site plan required showing Trellis with a Min. Fire seperation distance of 5'-0". Possible floodplain. Routed to Jim Wyllie with Public Works.
Case Summary (BLD)  10/13/2008 DONE
DetailsSam Zahorka
Routing - PUBLIC WORKS10/13/2008 10/13/2008 PASS
DetailsJim Wyllie
Temporary structure, OK per Jim Wyllie with Public works. SRZ
Plan resubmittals received  10/13/2008  
DetailsSam Zahorka
rec'd "2" 8 1/2 X 11 Site plan and 2 copies of sheet SP1.1; taken to Sam Z
1st review completed  10/7/2008 DONE
DetailsSam Zahorka
Routing - PLAN CHECK10/6/2008 10/7/2008 FAIL
DetailsSam Zahorka
Requires Engineering. Spoke with Dave Mckinnon and requested Engineering in order to complete plan review.
Routing - PLANNING10/6/2008 10/6/2008 PASS
DetailsSarah Schafer
Approved per DRH08-00334 and CZC08-00154.
Plans ACCEPTED BY PLAN TECH  10/3/2008 DONE
Ok per Sam Z to take in just 2 copies of plans and ok per Steve W. using the ESC plan from the original plans that were turned in (BLD08-00066) ///dld Had to wait for fee to be paid. was paid on 10-6-08
Application received 10/3/2008