Permit Information
Permit NumberBLD08-02184
StatusFinaled
Name PARADIGM CONSTRUCTION COMPANY LLC
Site Address 8878 W EVENING STAR LN
Project NamePinetree Village
Customer Number 
ePlanReviewNo
Description
(Unit 3 Building 8) This permit is for the construction of a new townhouse with four attached units. This is unit 3 that has a total of 1278 square feet with an attached garage of 474 square feet. The main level is 689 square feet with one bathroom and a kitchen. The second story is a total of 589 square feet with three bedrooms and two bathrooms. Epoxy anchors are being used on the interior walls and these will require a special inspector's sign off that will be provided to the City of Boise inspector on site. SEE COMMENTS FOR ANCHOR INFO. The furnace has been placed in the attic space and will require a walkway in the attic and a working platform, see attached plan review report for details. The separation wall is built to WP 4136 as noted and detailed on the approved plans. This two hour wall may not have any penetrations, the columns in the garage must be placed inside the separation wall. R-2D zoning district, building setbacks, CUP07-00150, CUP08-00058, and DRH08-00043 per Planning and Zoning. Built per all approved plans, red lining, engineering and plan review report. (BSP)
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final10/20/200910/20/200910/20/2009PPASS
DetailsMike Jordan
jim Phone #: ###-####
DOC - Permit Finaled10/20/200910/20/200910/20/2009PPASS
DetailsMike Jordan
Letter of occ. was issued.
Zoning Approval8/3/20098/3/20098/3/2009 DONE
DetailsMatthew A Halitsky
BLD-Other4/23/20094/23/20094/23/2009PPASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 4/23/2009 at 10:29:09 AM. Verified installation of exterior weather barrier.
BLD-Energy code compliance4/10/20094/13/20094/13/2009APASS
DetailsMike Jordan
Jim Phone #: ###-####
BLD-Framing/Rough-in4/9/20094/9/20094/9/2009PPASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 4/9/2009 at 7:57:53 AM.
BLD-Framing/Rough-in3/23/20093/23/20093/23/2009PNR
DetailsMike Jordan
Jim Phone #: ###-####
BLD-Framing/Rough-in3/20/20093/20/20093/20/2009PPASS
DetailsMike Jordan
Jim Phone #: ###-####. Nailing on both layers of 5/8 type x rock for 2hr. firewall from ceiling to under side of roof deck.
BLD-Framing/Rough-in3/19/20093/19/20093/19/2009PNR
DetailsMike Jordan
Scheduled by a contractor via Hello! on 3/19/2009 at 7:04:09 AM. Contact: ###-####.
BLD-Framing/Rough-in3/18/20093/18/20093/18/2009PPASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 3/18/2009 at 6:24:54 AM. Contact: ###-####. Nailing for both layers of 5/8 type x rock for 2hr. wall at overbuild areas. Also verified fire rated plywood for laydown parapets at overbuild areas.
BLD-Framing/Rough-in3/12/20093/13/20093/13/2009ANR
DetailsMike Jordan
Scheduled by a contractor via Hello! on 3/12/2009 at 8:40:19 PM. Contact: ###-####.
BLD-Framing/Rough-in3/11/20093/11/20093/11/2009PNR
DetailsMike Jordan
Scheduled by a contractor via Hello! on 3/11/2009 at 7:20:49 AM. Contact: ###-####.
BLD-Framing/Rough-in3/10/20093/10/20093/10/2009PPASS
DetailsMike Jordan
Jim Phone #: ###-####. 2nd. floor, 2nd layer of 5/8 type x rock both sides ok.
BLD-Footing3/9/20093/9/20093/9/2009PCANC
DetailsMike Jordan
Scheduled by a contractor via Hello! on 3/9/2009 at 6:55:39 AM. Contact: ###-####.
BLD-Framing/Rough-in3/6/20093/9/20093/9/2009ANR
DetailsMike Jordan
Jim Phone #: ###-####
BLD-Framing/Rough-in3/6/20093/6/20093/6/2009PPASS
DetailsMike Jordan
Jim Phone #: ###-####. 2nd. floor, 2nd. layer of 5/8 type x rock, both sides for 2hr. fire wall.
BLD-Framing/Rough-in3/5/20093/5/20093/5/2009PNR
DetailsMike Jordan
jim Phone #: ###-####
BLD-Framing/Rough-in3/4/20093/4/20093/4/2009PPASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 3/4/2009 at 7:07:57 AM. Contact: ###-####. 2nd. floor, 1st. layer of 5/8 type x rock, both sides for 2hr. fire wall.
BLD-Framing/Rough-in3/3/20093/3/20093/3/2009PNR
DetailsMike Jordan
Scheduled by a contractor via Hello! on 3/3/2009 at 7:32:51 AM. Contact: ###-####.
BLD-Framing/Rough-in3/2/20093/2/20093/2/2009PPASS
DetailsMike Jordan
jim Phone #: ###-####. 1st. floor, 2nd. layer of 5/8 type x rock both sides for 2hr. fire wall.
BLD-Framing/Rough-in2/27/20092/27/20092/27/2009PPASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 2/27/2009 at 9:19:05 AM. 1st.layer, 1st. floor of 5/8 type x rock, remaining side for 2hr fire wall.
BLD-Framing/Rough-in2/26/20092/26/20092/26/2009PPART
DetailsMike Jordan
Jim Phone #: ###-####. 1st. floor, 1st. layer of 5/8 type x rock, one side only for 2hr. fire wall.
BLD-Framing/Rough-in2/24/20092/25/20092/26/2009PCANC
DetailsMike Jordan
Jim Phone #: ###-####
BLD-Framing/Rough-in2/23/20092/24/20092/24/2009PNR
DetailsMike Jordan
Jim This inspection is for the fire wall Phone #: ###-####
BLD-Framing/Rough-in2/23/20092/23/20092/23/2009PNR
DetailsMike Jordan
jim Phone #: ###-####
BLD-Footing2/16/20092/17/20092/17/2009APASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 2/16/2009 at 3:10:40 PM. Contact: ###-####. Interior footings ok.
BLD-Energy code compliance2/11/20092/12/20092/12/2009APASS
DetailsMike Jordan
Jim Please call before going out Phone #: ###-####. Rigid foam insul. at interior side of stemwall.
BLD-Foundation2/4/20092/5/20092/5/2009PPASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 2/4/2009 at 8:23:24 AM. Contact: ###-####.
BLD-Footing2/4/20092/4/20092/4/2009PPASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 2/4/2009 at 8:23:05 AM. Contact: ###-####.
Plan assigned to (BSP)12/12/200812/12/20081/20/2009 PASS
DetailsCarl D Madsen
1/20/2009 10:03:09 CDM - activity updated through activity BLDA022 from case BLD08-02184.
Routing - PLAN CHECK12/24/2008 1/20/2009 PASS
DetailsBen S. Pavelka
PLANS/APPL TAKEN TO FRONT DESK  1/20/2009  
Routing - PLANNING Land Div1/20/2009 1/20/2009 PASS
DetailsTodd Tucker
Inspection Record Card- Bld  1/20/2009 DONE
DetailsBarbara Stitt
Permit Ready to Issue  1/20/2009 DONE
DetailsBarbara Stitt
Issue PAID IN FULL permit  1/20/2009 DONE
DetailsBarbara Stitt
Route to Impact Fee Review10/13/200810/16/20081/15/2009 PASS
DetailsCindy M. Gould
Case Summary (BLD)  1/15/2009 DONE
Routing - PUBLIC WORKS12/23/2008 12/24/2008 PASS
DetailsLouise Waldorf
Routing - PLANNING12/19/2008 12/23/2008 PASS
DetailsMatthew A Halitsky
Routing - PLANNING12/19/2008 12/19/2008 PASS
DetailsLucinda Grames
See site plan attached to construction plans. Routed to Matt H.
Plan resubmittals received  12/9/2008 DONE
DetailsAlexandra L. DeYoung
Routing - PLANNING Land Div10/14/2008 10/14/2008 FAIL
DetailsCody Riddle
Final plat has not been approved for associated subdivision. Contacted applicant on 10/14/2008. CER
Routing - Addressing10/13/2008 10/13/2008 PASS
DetailsChris Pichardo
Application received 10/13/2008