Zoning Approval | 8/3/2009 | 8/3/2009 | 8/3/2009 | | FAIL |
Matthew A Halitsky
|
|
|
Fencing, landscaping not complete.
|
BLD-Final | 6/17/2009 | 6/17/2009 | 6/17/2009 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 6/17/2009 at 9:23:14 AM.
|
DOC - Permit Finaled | 6/17/2009 | 6/17/2009 | 6/17/2009 | P | PASS |
Mike Jordan
|
|
|
Cert of occ issued.
|
BLD-Other | 4/14/2009 | 4/14/2009 | 4/14/2009 | P | PASS |
Mike Jordan
|
|
|
Jim- ###-####- building wrap. Verified installation exterior weather barrier.
|
BLD-Other | 4/10/2009 | 4/10/2009 | 4/10/2009 | P | NR |
Mike Jordan
|
|
|
Jim- house wrap Phone #: ###-####
|
BLD-Energy code compliance | 3/31/2009 | 3/31/2009 | 3/31/2009 | P | PASS |
Mike Jordan
|
|
|
Jim Phone #: ###-####. ok to rock.
|
BLD-Energy code compliance | 3/30/2009 | 3/30/2009 | 3/30/2009 | P | NR |
Mike Jordan
|
|
|
jim Phone #: ###-####
|
BLD-Framing/Rough-in | 3/27/2009 | 3/27/2009 | 3/27/2009 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 3/27/2009 at 8:14:23 AM. Contact: ###-####. ok to insul.
|
BLD-Other | 3/25/2009 | 3/25/2009 | 3/25/2009 | P | PASS |
Mike Jordan
|
|
|
Verified double layer5/8 type x rock at soffits ok.
|
BLD-Framing/Rough-in | 3/6/2009 | 3/9/2009 | 3/9/2009 | A | PASS |
Mike Jordan
|
|
|
Jim Phone #: ###-####. Verified nailing, both layers of 5/8 type x rock from 2nd. floor ceiling to underside of roof deck, both sides. Also verfied installation of fire rated plywood for laydown parapets at overbuild a areas.
|
BLD-Framing/Rough-in | 3/6/2009 | 3/6/2009 | 3/6/2009 | P | NR |
Mike Jordan
|
|
|
Jim Phone #: ###-####
|
BLD-Framing/Rough-in | 3/5/2009 | 3/5/2009 | 3/5/2009 | P | PASS |
Mike Jordan
|
|
|
jim Phone #: ###-####. 2nd. floor, 2nd. layer, remaining side of 5/8 type x rock for 2hr. fire wall. ok.
|
BLD-Framing/Rough-in | 3/3/2009 | 3/3/2009 | 3/3/2009 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 3/3/2009 at 7:29:57 AM. Contact: ###-####. 2nd. floor, 1st layer remaining side of 5/8 type x for 2hr. fire wall.
|
BLD-Framing/Rough-in | 3/2/2009 | 3/2/2009 | 3/2/2009 | P | PART |
Mike Jordan
|
|
|
jim Phone #: ###-####. 2nd floor, 1st. layer 5/8 typex, one side only for 2hr. fire wall.
|
BLD-Framing/Rough-in | 2/27/2009 | 2/27/2009 | 2/27/2009 | P | NR |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 2/27/2009 at 8:24:41 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 2/24/2009 | 2/25/2009 | 2/26/2009 | P | CANC |
Mike Jordan
|
|
|
Jim Phone #: ###-####
|
BLD-Framing/Rough-in | 2/23/2009 | 2/24/2009 | 2/24/2009 | A | CANC |
Mike Jordan
|
|
|
Jim This inspection is for the fire wall Phone #: ###-####
|
BLD-Framing/Rough-in | 2/23/2009 | 2/23/2009 | 2/23/2009 | P | PASS |
Mike Jordan
|
|
|
jim Phone #: ###-####. 1st. floor, 2nd layer, both sides, 5/8 type x rock for 2hr. wall ok.
|
BLD-Framing/Rough-in | 2/23/2009 | 2/23/2009 | 2/23/2009 | A | PASS |
Mike Jordan
|
|
|
jim Phone #: ###-####. 1st. floor 2nd layer, type x rock, one side only.
|
BLD-Framing/Rough-in | 2/20/2009 | 2/20/2009 | 2/20/2009 | P | PART |
Mike Jordan
|
|
|
1st. floor, 1st. layer, one side only, type x rock for 2hr. wall.
|
BLD-Framing/Rough-in | 2/19/2009 | 2/20/2009 | 2/20/2009 | A | CANC |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 2/19/2009 at 9:52:40 PM. Contact: ###-####.
|
BLD-Footing | 2/13/2009 | 2/13/2009 | 2/17/2009 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 2/13/2009 at 8:25:45 AM. Contact: ###-####. Interior foortings.
|
BLD-Energy code compliance | 1/29/2009 | 1/29/2009 | 1/29/2009 | P | PASS |
Mike Jordan
|
|
|
Jim Phone #: ###-####. Rigid foam insul at interior side of stemwall. ok.
|
BLD-Foundation | 1/27/2009 | 1/27/2009 | 1/27/2009 | P | PASS |
Mike Jordan
|
|
|
bill Phone #: ###-####
|
BLD-Footing | 1/23/2009 | 1/23/2009 | 1/23/2009 | P | PASS |
Mike Jordan
|
|
|
bill Phone #: ###-####. Perimeter footings.
|
Plan assigned to (BSP) | 12/26/2008 | 12/26/2008 | 1/20/2009 | | PASS |
Ben S. Pavelka
|
|
|
1/20/2009 10:08:34 CDM - activity updated through activity BLDA022 from case BLD08-02189.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/20/2009 | | |
|
|
|
|
Routing - PLANNING Land Div | 1/20/2009 | | 1/20/2009 | | PASS |
Todd Tucker
|
|
|
|
Permit Ready to Issue | | | 1/20/2009 | | DONE |
Barbara Stitt
|
|
|
|
Inspection Record Card- Bld | | | 1/20/2009 | | DONE |
Barbara Stitt
|
|
|
|
Issue PAID IN FULL permit | | | 1/20/2009 | | |
Barbara Stitt
|
|
|
|
CHANGE STATUS TO (REV) | | | 1/9/2009 | | |
|
|
|
|
Route to Impact Fee Review | 10/13/2008 | 10/16/2008 | 1/8/2009 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PLAN CHECK | 12/23/2008 | | 1/8/2009 | | PASS |
Ben S. Pavelka
|
|
|
Plan review complete, waiting for subdivision to be recorded before permits can be issued. (BSP) 1-9-09
|
Case Summary (BLD) | | | 1/7/2009 | | DONE |
|
|
|
|
Telephone call | | | 12/29/2008 | | |
|
|
|
Called Jim Larkin at ###-#### to notify him of resubmittals required for separation wall, res check and water closet clearances. Faxed resubmital request to ###-####. 12-29-08 BSP
|
Plans ACCEPTED BY PLAN CHECK | | | 12/26/2008 | | |
Ben S. Pavelka
|
|
|
|
Routing - PLANNING | 12/19/2008 | | 12/23/2008 | | PASS |
Matthew A Halitsky
|
|
|
|
Routing - PLANNING | | | 12/19/2008 | | PASS |
Lucinda Grames
|
|
|
See site plan attached to construction plans. Routed to Matt H.
|
Plan resubmittals received | | | 12/9/2008 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Routing - PLANNING Land Div | 10/14/2008 | | 10/14/2008 | | FAIL |
Cody Riddle
|
|
|
Final plat has not been approved for associated subdivision. Contacted applicant on 10/14/2008. CER
|
Routing - PUBLIC WORKS | 10/14/2008 | | 10/14/2008 | | PASS |
Louise Waldorf
|
|
|
|
Routing - Addressing | 10/13/2008 | | 10/14/2008 | | PASS |
Chris Pichardo
|
|
|
|
Application received | | 10/13/2008 | | | |
|
|
|
|