Permit Information
Permit NumberBLD08-02193
StatusFinaled
Name PARADIGM CONSTRUCTION COMPANY LLC
Site Address 8848 W EVENING STAR LN
Project NamePinetree Village
Customer Number 
ePlanReviewNo
Description
(UNIT 4 BUILDING 9)This permit is for the construction of a new townhouse. This unit is required to be accessible and the builder in complying by submitting this as a type B unit. Per the governing code only one bathroom in a type B unit is required to be accessible, in this case that bathroom is located in the master bath. The counter tops also are required to be accessible as noted on the plans. This is a one level unit of 1051 square feet with two bedrooms and two bathrooms as well as an attached garage of 282 square feet. There is also a covered front porch of 36 square feet. The side setback for this unit is five feet, therefore the roof overhangs will encroach into the fire separation distance and are required to be rated to one hour on the underneath side per the detail on the approved plans. The separation wall is built to the gypsum detail WP 4136. See comments for anchors. R-2D zoning district, building setbacks, CUP07-00150, CUP08-00058, and DRH08-00043 per Planning and Zoning. Built per all approved plans, engineering, red lining, and plan review report. (BSP)
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final11/2/200911/2/200911/2/2009PPASS
DetailsJim Storey
Jim Phone #: ###-####.
DOC - Permit Finaled11/2/200911/2/200911/2/2009PPASS
DetailsJim Storey
Zoning Approval8/3/20098/3/20098/3/2009 DONE
DetailsMatthew A Halitsky
BLD-Energy code compliance4/20/20094/20/20094/20/2009APASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 4/20/2009 at 6:54:04 AM.
BLD-Other4/17/20094/17/20094/17/2009PPASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 4/17/2009 at 6:56:58 AM. Verified installation of exterior weather barrier.
BLD-Framing/Rough-in4/16/20094/16/20094/16/2009PPASS
DetailsMike Jordan
Jim Phone #: ###-####
BLD-Framing/Rough-in4/2/20094/2/20094/2/2009PCANC
DetailsMike Jordan
Scheduled by a contractor via Hello! on 4/2/2009 at 6:02:30 AM.
BLD-Other4/2/20094/2/20094/2/2009APASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 4/2/2009 at 6:02:06 AM. Verified installation of 5/8 type x rock at soffitts.
BLD-Framing/Rough-in3/26/20093/26/20093/27/2009PPASS
DetailsMike Jordan
firewall construction Phone #: ###-####. Nailing on both layers of 5/8 type x rock from ceiling to underside of roof deck and fire rated plywood for laydown parapets at overbuilds ok.
BLD-Framing/Rough-in3/25/20093/25/20093/25/2009PNR
DetailsMike Jordan
jim Phone #: ###-####
BLD-Framing/Rough-in3/23/20093/23/20093/23/2009PNR
DetailsMike Jordan
Jim Phone #: ###-####
BLD-Framing/Rough-in3/20/20093/20/20093/20/2009PNR
DetailsMike Jordan
Jim Phone #: ###-####
BLD-Framing/Rough-in3/19/20093/19/20093/19/2009PPASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 3/19/2009 at 7:01:49 AM. Contact: ###-####. 2nd. floor, 2nd. layer of 5/8 type x rock, both sides for 2hr. fire wall.
BLD-Framing/Rough-in3/18/20093/18/20093/18/2009PNR
DetailsMike Jordan
Scheduled by a contractor via Hello! on 3/18/2009 at 6:28:28 AM. Contact: ###-####.
BLD-Framing/Rough-in3/17/20093/17/20093/17/2009PPASS
DetailsMike Jordan
Jim Phone #: ###-####. 2nd. floor, 1st. layer, reamaing side, for 2hr. firewall.
BLD-Framing/Rough-in3/16/20093/16/20093/16/2009PPART
DetailsMike Jordan
Scheduled by a contractor via Hello! on 3/16/2009 at 11:16:11 AM. Contact: ###-####. 2nd. floor, 1st. layer, one side only of 5/8 type x rock for 2hr.fire wall.
BLD-Framing/Rough-in3/12/20093/13/20093/13/2009ANR
DetailsMike Jordan
Scheduled by a contractor via Hello! on 3/12/2009 at 8:43:32 PM. Contact: ###-####.
BLD-Framing/Rough-in3/11/20093/11/20093/11/2009PNR
DetailsMike Jordan
Scheduled by a contractor via Hello! on 3/11/2009 at 7:26:52 AM. Contact: ###-####.
BLD-Framing/Rough-in3/10/20093/10/20093/10/2009PNR
DetailsMike Jordan
Jim Phone #: ###-####
BLD-Framing/Rough-in3/9/20093/9/20093/10/2009PCANC
DetailsMike Jordan
Scheduled by a contractor via Hello! on 3/9/2009 at 7:00:02 AM. Contact: ###-####.
BLD-Framing/Rough-in3/6/20093/9/20093/9/2009APASS
DetailsMike Jordan
Jim Phone #: ###-####. 1st. floor, 2nd. layer of 5/8 typex rock bothsides for 2hr. fire wall.
BLD-Framing/Rough-in3/6/20093/6/20093/6/2009PPART
DetailsMike Jordan
Jim Phone #: ###-####. 1st. floor, 1st layer of 5/8 type x rock, one side only for 2hr. fire wall.
BLD-Framing/Rough-in3/5/20093/5/20093/5/2009PNR
DetailsMike Jordan
jim Phone #: ###-####
BLD-Framing/Rough-in3/3/20093/4/20093/4/2009ANR
DetailsMike Jordan
Jim Phone #: ###-####
BLD-Framing/Rough-in3/3/20093/3/20093/3/2009PNR
DetailsMike Jordan
Scheduled by a contractor via Hello! on 3/3/2009 at 7:37:19 AM. Contact: ###-####.
BLD-Framing/Rough-in3/2/20093/2/20093/2/2009PCANC
DetailsMike Jordan
jim Phone #: ###-####
BLD-Footing2/23/20092/23/20092/23/2009APASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 2/23/2009 at 6:49:35 AM. Contact: ###-####.
BLD-Footing2/20/20092/20/20092/20/2009PPASS
DetailsMike Jordan
Interior footings ok.
BLD-Energy code compliance1/29/20091/30/20091/30/2009APASS
DetailsMike Jordan
Jim Phone #: ###-####. Rigid foam insul. at interior side of stemwall.
BLD-Foundation1/27/20091/28/20091/28/2009PNR
DetailsMike Jordan
bill Phone #: ###-####
BLD-Footing1/26/20091/26/20091/26/2009PPASS
DetailsMike Jordan
bill Phone #: ###-####
Plan assigned to (BSP)12/31/200812/31/20081/20/2009 PASS
DetailsCarl D Madsen
1/20/2009 10:10:51 CDM - activity updated through activity BLDA022 from case BLD08-02193.
PLANS/APPL TAKEN TO FRONT DESK  1/20/2009  
Routing - PLANNING Land Div1/20/2009 1/20/2009 PASS
DetailsTodd Tucker
Inspection Record Card- Bld  1/20/2009 DONE
Details
Permit Ready to Issue  1/20/2009 DONE
DetailsBarbara Stitt
Issue PAID IN FULL permit  1/20/2009  
DetailsBarbara Stitt
Routing - PLAN CHECK12/23/2008 1/20/2009 PASS
DetailsCarl D Madsen
Route to Impact Fee Review10/13/200810/16/20081/14/2009 PASS
DetailsCindy M. Gould
Case Summary (BLD)  1/14/2009 DONE
Telephone call  12/31/2008  
Called Jim Larkin at ###-#### to notify him of resubmittals required for separation wall, res check and water closet clearances. Faxed resubmital request to ###-####. 12-29-08 BSP
Plans ACCEPTED BY PLAN CHECK  12/31/2008  
DetailsBen S. Pavelka
Routing - PLANNING12/19/2008 12/23/2008 PASS
DetailsMatthew A Halitsky
Routing - PLANNING  12/19/2008 PASS
DetailsLucinda Grames
See site plan attached to construction plans. Routed to Matt H.
Plan resubmittals received  12/9/2008 DONE
DetailsAlexandra L. DeYoung
Routing - PLANNING Land Div10/14/2008 10/14/2008 FAIL
DetailsCody Riddle
Final plat has not been approved for associated subdivision. Contacted applicant on 10/14/2008. CER
Routing - PUBLIC WORKS10/14/2008 10/14/2008 PASS
DetailsLouise Waldorf
Routing - Addressing10/14/2008 10/14/2008 PASS
DetailsChris Pichardo
Application received 10/13/2008