BLD-Final | 12/1/2009 | 12/2/2009 | 12/2/2009 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Internet Inspection Request from: James Larkin
|
DOC - Permit Finaled | 12/2/2009 | 12/2/2009 | 12/2/2009 | P | PASS |
Mike Jordan
|
|
|
Cert. of occ. issued.
|
Zoning Approval | 8/3/2009 | 8/3/2009 | 8/3/2009 | | DONE |
Matthew A Halitsky
|
|
|
|
BLD-Other | 4/3/2009 | 4/3/2009 | 4/3/2009 | P | PASS |
Mike Jordan
|
|
|
Jim- building wrap Phone #: ###-####.. Verified installation of weather resistive barrier.
|
BLD-Other | 3/20/2009 | 3/20/2009 | 3/20/2009 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 3/20/2009 at 7:01:46 AM. Contact: ###-####. double layer 5/8 type x rock under soffitt.
|
BLD-Framing/Rough-in | 3/9/2009 | 3/9/2009 | 3/10/2009 | P | CANC |
Mike Jordan
|
|
|
Jim Phone #: ###-####
|
BLD-Energy code compliance | 3/6/2009 | 3/9/2009 | 3/9/2009 | A | PASS |
Mike Jordan
|
|
|
Jim Phone #: ###-####. ok to rock.
|
BLD-Energy code compliance | 3/5/2009 | 3/5/2009 | 3/5/2009 | P | CANC |
Mike Jordan
|
|
|
jim Phone #: ###-####
|
BLD-Framing/Rough-in | 3/5/2009 | 3/5/2009 | 3/5/2009 | P | PASS |
Mike Jordan
|
|
|
jim Phone #: ###-####. ok to insul.
|
BLD-Framing/Rough-in | 2/23/2009 | 2/23/2009 | 2/23/2009 | P | CANC |
Mike Jordan
|
|
|
jim Phone #: ###-####
|
BLD-Framing/Rough-in | 2/19/2009 | 2/20/2009 | 2/20/2009 | P | CANC |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 2/19/2009 at 10:03:02 PM. Contact: ###-####.
|
BLD-Framing/Rough-in | 2/19/2009 | 2/19/2009 | 2/19/2009 | P | NR |
Mike Jordan
|
|
|
jim - firewalls Phone #: ###-####
|
BLD-Framing/Rough-in | 2/18/2009 | 2/19/2009 | 2/19/2009 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 2/18/2009 at 5:14:42 PM. Contact: ###-####. 2nd layer type x rock from ceiling to roof deck, also verified nailing on type x rock for overbuilds and rated plywood for 4ft. parapet at overbuilds.
|
BLD-Framing/Rough-in | 2/18/2009 | 2/18/2009 | 2/18/2009 | P | PASS |
Mike Jordan
|
|
|
Jim Phone #: ###-####. 2nd. floor, 2nd. layer, both sides, type x rock for 2hr. wall, also 1st. layer from ceiling to roof deck.
|
BLD-Framing/Rough-in | 2/17/2009 | 2/17/2009 | 2/17/2009 | P | PASS |
Mike Jordan
|
|
|
Jim- Fire wall Phone #: ###-####. 2nd. floor, 5/8 type x rock, remaining side.
|
BLD-Framing/Rough-in | 2/11/2009 | 2/13/2009 | 2/17/2009 | P | PART |
Mike Jordan
|
|
|
jim - fire wall Phone #: ###-####. 2nd. floor, 5/8type x rock one side only for 2hr. wall.
|
BLD-Framing/Rough-in | 2/10/2009 | 2/11/2009 | 2/11/2009 | P | PASS |
Mike Jordan
|
|
|
Jim Phone #: ###-####. 1st. floor, 2nd. layer 5/8 typex rock for 2hr. wall both sides.
|
BLD-Framing/Rough-in | 2/10/2009 | 2/11/2009 | 2/11/2009 | A | PART |
Mike Jordan
|
|
|
Jim Phone #: ###-####. 1st floor, 5/8 type x rock for 2hr. wall, remaining side.
|
BLD-Framing/Rough-in | 2/10/2009 | 2/10/2009 | 2/10/2009 | P | PART |
Mike Jordan
|
|
|
Jim Phone #: ###-####. 1st.floor, 5/8type x rock for 2hr. wall. one side only.
|
BLD-Energy code compliance | 1/23/2009 | 1/23/2009 | 1/23/2009 | P | PASS |
Mike Jordan
|
|
|
jim Phone #: ###-####. Rigid insul. at interior side of stemwal.
|
BLD-Foundation | 1/22/2009 | 1/22/2009 | 1/22/2009 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Foundation | 1/21/2009 | 1/22/2009 | 1/22/2009 | A | NR |
Mike Jordan
|
|
|
bill Phone #: ###-####. Rescheduled for pm.
|
BLD-Footing | 1/20/2009 | 1/21/2009 | 1/21/2009 | A | PASS |
Mike Jordan
|
|
|
Exterior perimeter footings.
|
Plan assigned to (BSP) | 1/6/2009 | 1/6/2009 | 1/20/2009 | | PASS |
Carl D Madsen
|
|
|
1/20/2009 10:24:39 CDM - activity updated through activity BLDA022 from case BLD08-02207.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/20/2009 | | |
|
|
|
|
Routing - PLANNING Land Div | 1/20/2009 | | 1/20/2009 | | PASS |
Todd Tucker
|
|
|
|
Inspection Record Card- Bld | | | 1/20/2009 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/20/2009 | | DONE |
Barbara Stitt
|
|
|
|
Routing - PUBLIC WORKS | 1/20/2009 | | 1/20/2009 | | PASS |
Louise Waldorf
|
|
|
|
Routing - PLAN CHECK | 1/2/2008 | | 1/20/2009 | | PASS |
Carl D Madsen
|
|
|
Needs routed to Planning for DR and then to Land division. (BSP)
|
Issue PAID IN FULL permit | | | 1/20/2009 | | DONE |
|
|
|
|
Route to Impact Fee Review | 10/13/2008 | 10/16/2008 | 1/16/2009 | | PASS |
Cindy M. Gould
|
|
|
|
Case Summary (BLD) | | | 1/15/2009 | | DONE |
|
|
|
|
Routing - PLANNING | 1/9/2009 | | 1/9/2009 | | PASS |
Matthew A Halitsky
|
|
|
Needs routed to Planning for DR and then to Land division. (BSP)
|
Plan resubmittals requested | | | 1/8/2009 | | DONE |
|
|
|
Jim Larkin brought in 2 cover sheets and 2 copies of sheets A1.12,A6.1 ,EMP1.1 AND 5 COPIES OF SHEETS a2.1 a3.1,a4.1,a5.1 Carl M took plans to Ben's desk
|
Plans ACCEPTED BY PLAN CHECK | | | 1/6/2009 | | |
Ben S. Pavelka
|
|
|
|
Routing - PLANNING | 12/18/2008 | | 12/19/2008 | | PASS |
Sue Cummings
|
|
|
See site plan attached to construction plans. Routed to Matt H.
|
Routing - Addressing | 10/15/2008 | | 10/15/2008 | | PASS |
Chris Pichardo
|
|
|
|
Routing - PLANNING | 10/15/2008 | | 10/15/2008 | | FAIL |
Lucinda Grames
|
|
|
Final plat of subdivision not yet applied for.
|
Routing - PLANNING | 12/19/2008 | | 1/2/2008 | | FAIL |
Matthew A Halitsky
|
|
|
DR Mod needed. Notified applicant 1/2/2008.
|
Application received | | 10/13/2008 | | | |
|
|
|
|