BLD-Final | 3/10/2009 | 3/11/2009 | 3/11/2009 | A | PASS |
Mike Jordan
|
|
|
Don Phone #: ###-####
|
DOC - Permit Finaled | 3/11/2009 | 3/11/2009 | 3/11/2009 | P | PASS |
Mike Jordan
|
|
|
Letter of compliance issued.
|
BLD-Final | 3/9/2009 | 3/10/2009 | 3/10/2009 | A | NR |
Mike Jordan
|
|
|
Don Phone #: ###-####. Still has open elec. permit that needs finaled and also needs a zoning sign off. Called Don to let him know of outstanding items.
|
Zoning Approval | 3/9/2009 | 3/9/2009 | 3/10/2009 | | DONE |
Sue Cummings
|
|
|
Zoning OK to issue occupancy 3/10/09 SAC
|
BLD-Other | 2/10/2009 | 2/10/2009 | 2/10/2009 | P | CANC |
Bill VanDegrift
|
|
|
just needed the contractors phone number
|
BLD-Framing/Rough-in | 12/8/2008 | 12/8/2008 | 12/8/2008 | P | PASS |
Mike Jordan
|
|
|
don Phone #: ###-####. Framing in detached shop ok.
|
BLD-Framing/Rough-in | 11/19/2008 | 11/20/2008 | 11/20/2008 | A | CANC |
Mike Jordan
|
|
|
don Phone #: ###-####. Performed insp. yesterday.
|
BLD-Framing/Rough-in | 11/19/2008 | 11/19/2008 | 11/19/2008 | P | PASS |
Mike Jordan
|
|
|
Verified 5/8 type x at ceiling and one hr. wall.
|
BLD-Framing/Rough-in | 11/18/2008 | 11/19/2008 | 11/19/2008 | A | NR |
Mike Jordan
|
|
|
don Note: drywall - if possible 10:00 am please Phone #: ###-####
|
BLD-Energy code compliance | 11/17/2008 | 11/18/2008 | 11/18/2008 | A | PASS |
Mike Jordan
|
|
|
don Phone #: ###-####
|
BLD-Framing/Rough-in | 11/14/2008 | 11/17/2008 | 11/17/2008 | A | PASS |
Mike Jordan
|
|
|
don Phone #: ###-####. ok to insul.
|
BLD-Framing/Rough-in | 11/13/2008 | 11/14/2008 | 11/14/2008 | P | NR |
Mike Jordan
|
|
|
don Phone #: ###-####
|
BLD-Conference | 10/27/2008 | 10/27/2008 | 10/27/2008 | P | DONE |
Mike Jordan
|
|
|
don Phone #: ###-####. On site to discuss 1hr. wall requirements with contractor for adu. It was decided to go with a 1hr wall up to ceiling and construct a draftstop in attic area and use 5/8 type X on ceiling in adu side.
|
BLD-Foundation | 10/21/2008 | 10/22/2008 | 10/22/2008 | A | PASS |
Mike Jordan
|
|
|
Don Phone #: ###-####
|
BLD-Footing | 10/20/2008 | 10/20/2008 | 10/20/2008 | P | PASS |
Mike Jordan
|
|
|
don Phone #: ###-####
|
Routing Walk-In (BLD) | 10/20/2008 | 10/20/2008 | 10/20/2008 | P | PASS |
Perry Paine
|
|
|
|
Case Summary (BLD) | | | 10/20/2008 | | |
|
|
|
|
Inspection Record Card- Bld | | | 10/20/2008 | | |
|
|
|
|
Route to Impact Fee Review | 10/14/2008 | 10/17/2008 | 10/15/2008 | | PASS |
Cindy M. Gould
|
|
|
|
Routing Walk-In (BLD) | 10/14/2008 | 10/14/2008 | 10/15/2008 | P | DONE |
Perry Paine
|
|
|
10/15/2008 11:07:10 PEP - activity updated through activity BLDA022 from case BLD08-02214.
|
Case Summary (BLD) | | | 10/15/2008 | | |
|
|
|
|
Inspection Record Card- Bld | | | 10/15/2008 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/15/2008 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 10/15/2008 | | |
|
|
|
|
Telephone call | | | 10/15/2008 | | DONE |
Cathy Brown
|
|
|
tlk to don ###-#### that permit and fees are ready to be picked up but needs to take the esc class and said that has signed up for the class
|
Permit Ready to Issue | | | 10/15/2008 | | DONE |
Cathy Brown
|
|
|
|
Issue PAID IN FULL permit | | | 10/15/2008 | | DONE |
|
|
|
|
Plan assigned to (PEP) | | | 10/15/2008 | | PASS |
Perry Paine
|
|
|
10/15/2008 11:07:10 PEP - activity updated through activity BLDA022 from case BLD08-02214.
|
Routing - PLAN CHECK | 10/14/2008 | | 10/15/2008 | | PASS |
Perry Paine
|
|
|
|
Routing - Addressing | 10/14/2008 | | 10/14/2008 | | PASS |
Chris Pichardo
|
|
|
|
Routing - PUBLIC WORKS | 10/14/2008 | | 10/14/2008 | | PASS |
Louise Waldorf
|
|
|
|
Routing - PLANNING | 10/14/2008 | | 10/14/2008 | | PASS |
Sue Cummings
|
|
|
CAA08-00251- Sue Cummings-routed to Cody Riddle
|
Application received | | 10/14/2008 | | | |
Alexandra L. DeYoung
|
|
|
|