Information based on query as of Friday, August 16, 2024.
Permit Information
Permit NumberBLD08-02241
StatusFinaled
Name FALASH & ROSS CONSTRUCTION
Site Address 921 W JEFFERSON ST
Project NameHal Davis Jewlers
Customer Number 
ePlanReviewNo
Description
This will be a change in occupancy from a B to an M. For the interior tenant improvements to an existing space per the approved plans. The improvements will include the construction of two office spaces, the installation of a new 6 sided modular vault (see the attached engineering and specification sheets for the supporting construction and vault installation instructions), changing the existing water fountain to a high-low accessible unit adding vertical grab bars to the existing ADA bathrooms and changing out the bathroom countertops and sinks. There will also be patch and repair of the existing suspended ceiling system, the placement of display cases and miscellaneous interior finishes. The building includes 4689 sq.ft. on the first story with a 804 sq.ft. mezzanine and a 1175 sq.ft. unimproved mechanical basement. This project does not include any improvements to the mezzanine. CDM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  4/20/2010 DONE
DetailsSam Zahorka
Second Notice BLD3/4/20093/4/20093/11/2009 DONE
DetailsAlexandra L. DeYoung
First Notice has not been responded to.
First Notice 1/29/20093/4/2009 DONE
Permanent Occupancy UNPAID FEE  1/29/2009 DONE
DetailsTisha Gallop
BLD-Final1/27/20091/28/20091/28/2009APASS
DetailsDave Hannah
dean Phone #: ###-#### ok for perm occ
BLD-Final1/22/20091/23/20091/23/2009APART
DetailsDave Hannah
dean Phone #: ###-#### everything ok but needs a plumbing final
FIRE-Final Inspection1/22/20091/22/20091/22/2009PPASS
DetailsForrest France
Life safety inspection passed, contractor to replace one lamp at the EM light fixture in the stairway to the mezzanine as discussed.
BLD-Other12/16/200812/17/200812/17/2008APART
DetailsDave Hannah
dean Note: ceiling grid Phone #: ###-#### ok to cover ceiling also I have a letter from the engineer oking structal on clouds I also talked with Roy McGlothin on 12/16 at around 10:00am about framing changes on clouds he told me that he was ok with everything
BLD-Framing/Rough-in12/11/200812/12/200812/12/2008AFAIL
DetailsDave Hannah
dean Phone #: ###-#### letter from engineer dont ok clouds
BLD-Framing/Rough-in11/26/200812/1/200812/1/2008APART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 11/26/2008 at 2:57:22 PM. ok to cover walls but need the engineer to ok the constrution of the lighing clouds hanging down from ceiling not per plans
BLD-Framing/Rough-in11/3/200811/3/200811/4/2008PPASS
DetailsDave Hannah
dean Phone #: ###-#### ok to sheet floor under safe
Issue PAID IN FULL permit  10/31/2008 DONE
Telephone call  10/23/2008 DONE
Details
t/c w mike falash at ###-#### - permit ready and fees given - also need ACHD receipt
Permit Ready to Issue  10/23/2008 DONE
Details
Plan assigned to (CDM)10/17/2008 10/22/2008 PASS
DetailsCarl D Madsen
10/22/2008 14:16:59 CDM - activity updated through activity BLDA022 from case BLD08-02241.
Routing - PLAN CHECK10/17/2008 10/22/2008 PASS
DetailsCarl D Madsen
Case Summary (BLD)  10/22/2008 DONE
1st review completed  10/22/2008 DONE
Routing - FIRE  10/22/2008 PASS
Verfy in field
PLANS/APPL TAKEN TO FRONT DESK  10/22/2008 DONE
Print Occupancy Form  10/22/2008 DONE
Details
Telephone call  10/22/2008 DONE
Left a message for Bob Ross that the plans would need be approved by ACHD since there is a chang in occupancy. 10-22-08 CDM
Plans ACCEPTED BY PLAN TECH  10/17/2008 DONE
DetailsAlexandra L. DeYoung
Recd Pcfee & Taken To Pln CK  10/17/2008 DONE
DetailsAlexandra L. DeYoung
Plan assigned to (R_H)10/17/2008 10/17/2008 DONE
DetailsRon Hill
Application received 10/16/2008