Case Summary (BLD) | | | 4/20/2010 | | DONE |
Sam Zahorka
|
|
|
|
Second Notice BLD | 3/4/2009 | 3/4/2009 | 3/11/2009 | | DONE |
Alexandra L. DeYoung
|
|
|
First Notice has not been responded to.
|
First Notice | | 1/29/2009 | 3/4/2009 | | DONE |
|
|
|
|
Permanent Occupancy UNPAID FEE | | | 1/29/2009 | | DONE |
Tisha Gallop
|
|
|
|
BLD-Final | 1/27/2009 | 1/28/2009 | 1/28/2009 | A | PASS |
Dave Hannah
|
|
|
dean Phone #: ###-#### ok for perm occ
|
BLD-Final | 1/22/2009 | 1/23/2009 | 1/23/2009 | A | PART |
Dave Hannah
|
|
|
dean Phone #: ###-#### everything ok but needs a plumbing final
|
FIRE-Final Inspection | 1/22/2009 | 1/22/2009 | 1/22/2009 | P | PASS |
Forrest France
|
|
|
Life safety inspection passed, contractor to replace one lamp at the EM light fixture in the stairway to the mezzanine as discussed.
|
BLD-Other | 12/16/2008 | 12/17/2008 | 12/17/2008 | A | PART |
Dave Hannah
|
|
|
dean Note: ceiling grid Phone #: ###-#### ok to cover ceiling also I have a letter from the engineer oking structal on clouds I also talked with Roy McGlothin on 12/16 at around 10:00am about framing changes on clouds he told me that he was ok with everything
|
BLD-Framing/Rough-in | 12/11/2008 | 12/12/2008 | 12/12/2008 | A | FAIL |
Dave Hannah
|
|
|
dean Phone #: ###-#### letter from engineer dont ok clouds
|
BLD-Framing/Rough-in | 11/26/2008 | 12/1/2008 | 12/1/2008 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 11/26/2008 at 2:57:22 PM. ok to cover walls but need the engineer to ok the constrution of the lighing clouds hanging down from ceiling not per plans
|
BLD-Framing/Rough-in | 11/3/2008 | 11/3/2008 | 11/4/2008 | P | PASS |
Dave Hannah
|
|
|
dean Phone #: ###-#### ok to sheet floor under safe
|
Issue PAID IN FULL permit | | | 10/31/2008 | | DONE |
|
|
|
|
Telephone call | | | 10/23/2008 | | DONE |
|
|
|
t/c w mike falash at ###-#### - permit ready and fees given - also need ACHD receipt
|
Permit Ready to Issue | | | 10/23/2008 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 10/17/2008 | | 10/22/2008 | | PASS |
Carl D Madsen
|
|
|
10/22/2008 14:16:59 CDM - activity updated through activity BLDA022 from case BLD08-02241.
|
Routing - PLAN CHECK | 10/17/2008 | | 10/22/2008 | | PASS |
Carl D Madsen
|
|
|
|
Case Summary (BLD) | | | 10/22/2008 | | DONE |
|
|
|
|
1st review completed | | | 10/22/2008 | | DONE |
|
|
|
|
Routing - FIRE | | | 10/22/2008 | | PASS |
|
|
|
Verfy in field
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/22/2008 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/22/2008 | | DONE |
|
|
|
|
Telephone call | | | 10/22/2008 | | DONE |
|
|
|
Left a message for Bob Ross that the plans would need be approved by ACHD since there is a chang in occupancy. 10-22-08 CDM
|
Plans ACCEPTED BY PLAN TECH | | | 10/17/2008 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/17/2008 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Plan assigned to (R_H) | 10/17/2008 | | 10/17/2008 | | DONE |
Ron Hill
|
|
|
|
Application received | | 10/16/2008 | | | |
|
|
|
|