Description
(SAMMY'S) Permit to convert an existing printing shop ("B") to a new youth lounge ("A-2"). Space will be used for assembly purposes. This use is defined as an A-2 occupancy. Work to include: [installation of interior non-bearing walls to create one office, two accessible restrooms, one utility closet, and an open lounge area,] installation of a 60 square foot platform, installation of new doors and associated hardware, new plumbing, new electrical, and installation of interior finishes in compliance with chapter 8 of the IBC. This building is required to be sprinklered under a separate permit pulled threw Boise City Fire Dept. in compliance with the NFPA 13 standard. Planning approval by Josh Wilson per DRH08-00354.**TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 10/16/200910/6/2009 DONE
Third Notice 9/14/200910/6/2009 DONE
e-mailed and called owner rep. Lawrence Ross/mailed to tenant.
Telephone call  10/6/2009 DONE
DetailsTisha Gallop
called Don w/Idaho Backhoe, he said had nothing to do with project and was not GC or didn't do any work out there.
Telephone call  10/6/2009 DONE
DetailsTisha Gallop
received phone call from Lawrence Ross (leasing agent) and he said that the tenant is the one who paid for the remodeling and is the only one that know what the values are. Lawrence also said he has no contact info for the tenat, all the phone #'s he has are disconnected and he has no address but this one. Lawrence said he will fill out the final values to the best of his knowlege and get them back to me.//received final values signed by Lawrence Ross on 10/6/09
Telephone call  10/5/2009 DONE
DetailsTisha Gallop
called and left my name and phone number for Lawrence Ross (owner rep) to call me back.
Third Notice 8/5/20099/14/2009 DONE
DetailsTisha Gallop
faxed to owner representative on Registered Design Prof. in Charge Page and mailed to project address.
Second Notice 7/24/20098/5/2009 DONE
PUT HOLD ON NEED FULL ADDRESS,PHONE NUMBER,FAX NUMBER ///DLD 7-24-09
First Notice 7/20/20097/24/2009 DONE
sent by mail
Permanent Occupancy UNPAID FEE  7/20/2009 DONE
BLD-Final7/17/20097/17/20097/17/2009PPASS
DetailsJim Storey
final ok
Print Occupancy Form  7/16/2009 DONE
DetailsAlexandra L. DeYoung
Case Summary (BLD)  7/16/2009 DONE
Zoning Approval7/1/20097/1/20097/1/2009 PASS
DetailsJosh Wilson
Landscaping completed and bonidng may be released.
BLD-Final5/22/20095/26/20095/26/2009ANR
DetailsJim Storey
Wendy Kurdy ###-#### pending p&z
Temporary Occupancy UNPAID FEE  4/3/2009 DONE
DetailsTisha Gallop
BLD-Final3/26/20093/27/20093/27/2009PPART
DetailsJim Storey
final ok pending p&z final sign off of bond.
FIRE-Final Inspection3/27/20093/27/20093/27/2009PPASS
DetailsForrest France
Corrections verified for completion, fire life safety accepted.
BLD-Final3/25/20093/26/20093/26/2009PFAIL
DetailsJim Storey
Sammy Phone #: ###-#### exit hardware on frnt doors/ ada grab bar vert/ protection under sink/ ele/plm
FIRE-Conference3/25/20093/25/20093/25/2009PDONE
DetailsForrest France
Regarding hardware requirements for main entry/exit doors 104 and 105-panic hardware needed per approved plans, notes, door schedule and hardware group as previously discussed due to the "A" occupancy type.
Zoning Approval Temp3/20/20093/20/20093/20/2009 PASS
DetailsJosh Wilson
Temporary occupancy granted for a maximum of 180 days. A surety for $13,500 in required landscaping has been submitted to the City.
FIRE-Conference3/12/20093/12/20093/12/2009PDONE
DetailsForrest France
On site conference with the owner regarding fire code review notes and plan annotations for fire life safety issues. Identified items #3,7 and 8 in need of attention.
Telephone call  2/26/2009 DONE
Spoke with Alan Grant (###-####) regarding landscaping and site improvements that cannot be completed until spring. Stated that we would need a surety of 110% of cost of improvements (verified by bids) in place prior to Zoning signature for Temp. Occ.
Issue PAID IN FULL permit  2/12/2009 DONE
DetailsBarbara Stitt
Print Occupancy Form  12/19/2008 DONE
Telephone call  12/19/2008 DONE
Details
left vm for john reseigh at ###-#### - permit ready and fees given - also need gc name, rce#, rp name and ACHD receipt
Permit Ready to Issue  12/19/2008 DONE
Details
Plan assigned to (TLW)11/1/2008 12/18/2008 PASS
DetailsTim L. Woodard
12/18/2008 16:10:16 TLW - activity updated through activity BLDA022 from case BLD08-02302.
Routing - PLAN CHECK11/25/2008 12/18/2008 PASS
DetailsTim L. Woodard
Per attached letter from LRK and Plan Review Report. TLW
Plan resubmittals received  12/18/2008  
DetailsTim L. Woodard
Rec'd one copy of transmittal letter, and three copies of sheets L1.0 & A0.0; taken to Tim W
Routing - PLANNING12/18/2008 12/18/2008 PASS
DetailsJosh Wilson
Walked plans to Josh had him sign off then. He approved plans based on the new sheets submitted today A0.0 and L1.0 and DRH08-00394. TLW
PLANS/APPL TAKEN TO FRONT DESK  12/18/2008 DONE
DetailsTim L. Woodard
Case Summary (BLD)  12/18/2008 DONE
Plan resubmittals received  12/17/2008  
DetailsTim L. Woodard
Received 1 copy of response letter to Tim Woodard dated 12-16-08 from John Reseigh and 2 copies of sheet A1.1 and taken to Tim Woodard's desk///12-17-08 @ 12:34pm BAS
Routing - FIRE11/21/200811/21/200811/25/2008 PASS
DetailsScott Arellano
Attached IFC comments to plans
1st review completed  11/25/2008 FAIL
Failed Planning, Plan Check
Route to Impact Fee Review11/21/200811/26/200811/24/2008 PASS
DetailsCindy M. Gould
existing building no impact fees
Routing - PLAN CHECK11/4/2008 11/21/2008 FAIL
DetailsTim L. Woodard
Refer to plan review report.
Routing - PLANNING11/4/2008 11/4/2008 FAIL
DetailsCody Riddle
Left message with architect at 1:18 p.m. today. The change in use from retail to lounge may require additional parking. A site plan confirming parking layout, etc. will be required.
Routing - Erosion and Sediment11/3/2008 11/4/2008 PASS
DetailsSteven Webb
ESC plan waiver approved with attached conditions. ESC08-00970
Routing - PLAN CHECK10/27/2008 11/3/2008 PEND
DetailsTim L. Woodard
Needs to route to Erosion & Sediment Control and Planning first prior to the Building review.
Routing - PUBLIC WORKS10/24/2008 10/27/2008 PASS
DetailsBeverly Hall
Application received 10/24/200810/24/2008 DONE
DetailsBarbara Stitt
Plans ACCEPTED BY PLAN TECH  10/24/2008 DONE
DetailsAlexandra L. DeYoung
Recd Pcfee & Taken To Pln CK  10/24/2008 DONE
DetailsAlexandra L. DeYoung