Permit NumberBLD08-02332
StatusFinaled
Name COMMUNITY CONTRACTING CORP
Site Address 1020 W MAIN ST Unit: 104
Project NameALASKA BLDG-VANILLA FINISH 104
Customer Number 
ePlanReviewNo
Description
(VANILLA FINISH)(SUITE 104) 3/19/09 - PLAN MODIFICATION REDUCING SCOPE OF WORK FOR THIS VANILLA FINISH REMOVING STAIRS TO UPPER LEVEL AND WALLING OFF THE UPPER 343 SQ. FT. LEVEL, REDUCING THE FLOOR AREA TO 1,665 SQ. FT. DRS Remodel to an existing space to split the space into two tenant areas. This tenant area will be 2,008 sq. ft. "VANILLA FINISH", unoccupied space. Separate application, plans, reviews, approval, permit and inspection for future tenant occupancy is required. The adjacent "Platinum Salon" tenant will be 2,587 sq. ft. and be done under BLD08-02331. Work to include.construction for separation from adjacent tenant space, Platinum Salon; construction of new stairway, guards and handrails to access the indicated 343 sq. ft. mezzanine to be a part of this space. Modifications as required for sprinkler system, electrical and mechanical. This permit does not allow occupancy. A separate permit is to be obtained for occupancy. NOTE: This building is fully fire sprinklered for substitution of one-hour construction. drs
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 7/25/20108/2/2010 DONE
First Notice6/18/20106/18/20107/15/2010 DONE
DetailsDave Hannah
BLD-Final6/18/20106/18/20106/18/2010PPASS
DetailsDave Hannah
DOC - Permit Finaled6/18/20106/18/20106/18/2010PPASS
DetailsDave Hannah
Telephone call  4/3/2009 DONE
Details
left vm for mark sanders at ###-#### - permit (plan mod) ready and fees given
Override - Parcel Holds  4/3/2009  
Override - Parcel Holds  4/3/2009  
CHANGE STATUS TO (ISS)  4/3/2009 DONE
DetailsTisha Gallop
(F) Reprint permit  4/3/2009 DONE
DetailsTisha Gallop
Routing - PLAN CHECK4/1/2009 4/1/2009 PASS
DetailsDan Stuart
This permit is tied to same plan for Platinum Saolon for which resubmittals are required. Reviewed plan changes reviewed and copy for job site was placed in Dave Hannah's out box for delivery to site.
BLD-Framing/Rough-in3/17/20093/18/20093/19/2009APASS
DetailsDave Hannah
jim - cover Phone #: ###-####
Plan Modification Accepted  3/19/2009 DONE
Plans submitted through Dave Hannah, Structural Inspector. Modified floor plan removing the stairs to the upper mezzanine level and separating the three mezzanine level rooms from the scope of work of VANILL FINISh permit.Three upper rooms will be part of future tenant improvement permit for proposed tenant in northwest corner of second level. Approved copy of modified plan to Dave Hannah to take to project site to become part of reviewed plans.
Override - Parcel Holds3/17/20091/1/19003/17/2009  
rough in cover
Plan resubmittals received  3/12/2009  
DetailsBarbara Stitt
Received 1 cover transmittal, 2 copies of sheets A1.0, A2.0, A3.0 and taken to Dave Hannah's box///3-12-09 @ 11:20am BAS
Telephone call  1/23/2009 DONE
DetailsCathy Brown
lft vm with mark sanders ###-#### that permit and fees are ready to be picked up
Permit Ready to Issue  1/23/2009 DONE
DetailsCathy Brown
Issue PAID IN FULL permit  1/23/2009 DONE
Plan assigned to (DRS)11/1/2008 1/22/2009 PASS
DetailsDan Stuart
1/22/2009 15:09:40 DRS - activity updated through activity BLDA022 from case BLD08-02332.
PLANS/APPL TAKEN TO FRONT DESK  1/22/2009 PASS
Inspection Record Card- Bld  1/22/2009 DONE
DetailsCathy Brown
Routing - PLAN CHECK12/3/2008 1/20/2009 PASS
DetailsDan Stuart
Resubmittals of 1/20/09 addressed code concerns for this scope of work. To permit desk to issue.
Plan resubmittals received  12/18/2008  
DetailsDan Stuart
Received 1 response letter to Dan Stuart dated 12-18-08 from Mark Sanders, 1 copy of intent letter dated 12-16-08 from Nicole Keulman, 3 copies of sheets A1.0, A3.0 and taken to Dan Stuart///12-18-08 BAS
Plan resubmittals received  12/10/2008  
DetailsBarbara Stitt
Received 1 response letter to Dan Stuart dated 12-8-08 from Mark Sanders, 2 copies of sheets A1.0, A2.0, A3.0 and taken to Dan Stuart's office///12-10-08 BAS
Routing - FIRE12/1/200812/1/200812/3/2008 PASS
DetailsScott Arellano
Attached IFC comments to plans
1st review completed  12/3/2008 FAIL
Failed Plan Check
Route to Impact Fee Review12/1/200812/4/200812/1/2008 PASS
DetailsCindy M. Gould
Tenant improvement no impact fees
Plan resubmittals requested  12/1/2008 DONE
Routing - PLAN CHECK11/3/2008 12/1/2008 FAIL
DetailsDan Stuart
COPY OF PLAN REVIEW TO ARCHITECT. PLANS ROUTED TO FIRE CODE ANALYST.
Routing PW Sewer Rating11/3/2008 11/3/2008 PASS
DetailsLouise Waldorf
Pending Assignment by JCB10/28/2008 11/1/2008 DONE
DetailsJason Blais
Plans ACCEPTED BY PLAN TECH  10/29/2008 DONE
DetailsAlexandra L. DeYoung
Recd Pcfee & Taken To Pln CK  10/29/2008 DONE
DetailsAlexandra L. DeYoung
Application received 10/28/2008   
DetailsAlexandra L. DeYoung
Routing - PUBLIC WORKS11/1/2008    
This permit is attached to plans with another permit that needs to be reviewed by Public Works. Scope of work on this permit does not need Public Works review.