Telephone call | | | 12/29/2009 | | DONE |
Tisha Gallop
|
|
|
called Dennis and told him still need contracts, if not received in 2 weeks will put company on hold for no inspections no permits. He said will bring them in today.
|
Telephone call | | | 11/25/2009 | | DONE |
Tisha Gallop
|
|
|
called and spoke with Dennis/Raistrick Const. still need contracts for FV. He said is coming in to pick up permit beginning of next week and will drop off pprwork to me then.
|
Telephone call | | | 11/6/2009 | | DONE |
Tisha Gallop
|
|
|
called and spoke with Dennis. Told him only need contracts for Diebold project and not to worry about getting contracts for 10th/Bannock building permits per Rita. He said will get Diebold contracts to me next week.
|
Telephone call | | | 10/29/2009 | | DONE |
Tisha Gallop
|
|
|
called and spoke with Dennis that because he marked no change on all values it requires an audit and I need contracts for all subs to verify values. He told me Christensen Corp. has some of the info, he doesn't have it all. I asked him to get me what he has and then I will contact Christensen Corp. He said will get it together and back to me.
|
Third Notice | | 10/16/2009 | 10/23/2009 | | DONE |
|
|
|
faxed, mailed and called
|
Telephone call | | | 10/23/2009 | | DONE |
Tisha Gallop
|
|
|
called and left voice message for Dennis/Raistrick Const. need final values and if not received w/in 2 weeks will put company on hold.
|
Third Notice | | 9/26/2009 | 10/6/2009 | | DONE |
|
|
|
faxed, mailed and called
|
Telephone call | | | 10/6/2009 | | DONE |
Tisha Gallop
|
|
|
called and left voice message for Dennis/Raistrick Const. need final values.
|
Third Notice | | 9/1/2009 | 9/16/2009 | | DONE |
|
|
|
|
Second Notice | | 8/11/2009 | 9/1/2009 | | DONE |
|
|
|
|
First Notice | | 2/27/2009 | 8/11/2009 | | DONE |
|
|
|
|
Permanent Occupancy | | | 2/27/2009 | | DONE |
Tisha Gallop
|
|
|
|
BLD-Final | 2/9/2009 | 2/10/2009 | 2/10/2009 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 2/9/2009 at 10:55:20 AM. Contact: ###-####. ok for permocc.
|
FIRE-Final Inspection | 2/9/2009 | 2/10/2009 | 2/10/2009 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 2/10/2009 | 2/10/2009 | 2/10/2009 | A | FAIL |
Troy Cobbley
|
|
|
The exit sign/emergency light at the main exit did not operate with the test switch and appears to need to be repaired. All other items were ok.
|
BLD-Framing/Rough-in | 1/16/2009 | 1/16/2009 | 1/16/2009 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 1/16/2009 at 8:11:53 AM. Contact: ###-####. Interior steel stud framed walls. no grid. Pend. plumbing ri insp.
|
Issue PAID IN FULL permit | | | 12/29/2008 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Telephone call | | | 11/6/2008 | | DONE |
|
|
|
t/c w matt rhees at ###-#### - permit ready and fees given - also need gc name and rce#
|
Permit Ready to Issue | | | 11/6/2008 | | DONE |
|
|
|
|
Plan assigned to (TLW) | | | 11/5/2008 | | PASS |
Tim L. Woodard
|
|
|
11/5/2008 13:59:16 CDM - activity updated through activity BLDA022 from case BLD08-02357.
|
Routing - PLAN CHECK | 11/4/2008 | | 11/5/2008 | | PASS |
Tim L. Woodard
|
|
|
|
Plan assigned to (CDM) | 11/5/2008 | | 11/5/2008 | | PASS |
Carl D Madsen
|
|
|
11/5/2008 13:59:16 CDM - activity updated through activity BLDA022 from case BLD08-02357.
|
Case Summary (BLD) | | | 11/5/2008 | | DONE |
|
|
|
|
Routing - FIRE | | | 11/5/2008 | | PASS |
|
|
|
Verify in field. CDM
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/5/2008 | | DONE |
|
|
|
|
1st review completed | | | 11/5/2008 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/5/2008 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 11/4/2008 | | 11/4/2008 | | PASS |
Beverly Hall
|
|
|
|
Routing - Addressing | 11/4/2008 | | 11/4/2008 | | PASS |
April Wing
|
|
|
|
Routing PW Sewer Rating | 11/4/2008 | | 11/4/2008 | | PASS |
Louise Waldorf
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/4/2008 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Application received | | 10/31/2008 | | | |
|
|
|
|