Information based on query as of Saturday, August 17, 2024.
Permit Information
Permit NumberBLD08-02395
StatusFinaled
Name HEARTLAND CONSTRUCTION LLC
Site Address 1675 S MAPLE GROVE RD
Project NameCommunity Connection - Bld B
Customer Number 
ePlanReviewNo
Description
Community Connection - Building B - To demolish and remove an existing single family dwelling and other out buildings; and to construct a new 7,670 square foot, one story, wood framed office building and related site improvements. The tenant is a limited office use consisting of instructional independence learning and physical therapy for handicapped individuals. This building will contain teen rooms, adult room, recreation room, therapy rooms, offices, conference rooms, reception area, restrooms, break room and lunch room. There is a 1,165 square foot, unfinished area for future expansion. The future unfinished area will require a separate tenant improvement permit to finish for occupancy. This building will be fully fire sprinkled. All construction per the approved plans and attached comment list. DRH07-00579 JCM NEED RP PRIOR TO ISSUANCE. 8-6-09 FINAL CERT OF VALUE $ 757,102.00 ///DLD
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 7/24/20098/6/2009 DONE
Second Notice 7/22/20098/6/2009 DONE
First Notice 6/29/20097/22/2009 DONE
sent by mail
BLD-Final6/29/20096/29/20096/29/2009PCANC
DetailsMike Jordan
christine Phone #: ###-####. ok for perm occ.
FIRE-Final Inspection6/29/20096/29/20096/29/2009PPASS
DetailsTroy Cobbley
Life safety passed.
Permanent Occupancy  6/29/2009 DONE
DetailsAlexandra L. DeYoung
Permanent Occupancy  6/29/2009 DONE
DetailsAlexandra L. DeYoung
FIRE-Final Inspection6/25/20096/26/20096/26/2009PFAIL
DetailsTroy Cobbley
The project related fire alarm and fire sprinkler permits need finaled and two exit discharge lights on the east side did not work.
PubWorks Occupancy Approval6/23/20096/23/20096/23/2009 DONE
DetailsTerry Records
Final grading and drainage approved.
Zoning Approval6/19/20096/22/20096/22/2009 PASS
DetailsJosh Wilson
BLD-Framing/Rough-in6/9/20096/10/20096/10/2009APASS
DetailsMike Jordan
christine - ceiling grid Phone #: ###-####
BLD-Other5/15/20095/15/20095/15/2009PPASS
DetailsMike Jordan
Chistine Phone #: ###-####. 1hr. const. for fire riser room.
BLD-Other5/13/20095/14/20095/14/2009ACANC
DetailsMike Jordan
christine - 1 hr construction on a fire riser Phone #: ###-####
BLD-Energy code compliance5/11/20095/11/20095/11/2009PPASS
DetailsMike Jordan
Christine Phone #: ###-####
BLD-Final5/7/20095/8/20095/8/2009ACANC
DetailsMike Jordan
christine Phone #: ###-####
BLD-Framing/Rough-in5/8/20095/8/20095/8/2009APASS
DetailsMike Jordan
christine Phone #: ###-####
BLD-Framing/Rough-in4/28/20094/29/20094/29/2009ANR
DetailsMike Jordan
Christine Phone #: ###-####. Needs ri. imsp. from other trades first.
BLD-Other3/31/20094/1/20094/1/2009APART
DetailsMike Jordan
Christine- roof nailing Phone #: ###-####. Nailing for roof ok.
BLD-Framing/Rough-in3/26/20093/26/20093/26/2009PPART
DetailsMike Jordan
Shear Inspection -christine Phone #: ###-####. Exterior shear nailing only, ok. Also gave contactor c/n noting to resubmit mezzanine drawing and all applicable engineering showing use of bonus trusses in leiu of TJI and additional square footage.
BLD-Foundation3/2/20093/3/20093/3/2009APASS
DetailsMike Jordan
ian Phone #: ###-####. Perimeter stemwalls and pedestals on column pad footings. ok.
BLD-Footing3/2/20093/2/20093/2/2009PPASS
DetailsMike Jordan
Ian Phone #: ###-####. Exterior column pad footings.
BLD-Footing2/25/20092/26/20092/26/2009PPASS
DetailsMike Jordan
ian Phone #: ###-####. Perimeter footings ok.
Issue PAID IN FULL permit  2/24/2009 DONE
Telephone call  2/18/2009  
DetailsAlexandra L. DeYoung
LM for chad with Dave- permit ready, fees given, also need ACHD and RP
Permit Ready to Issue  2/18/2009 DONE
DetailsAlexandra L. DeYoung
Plan assigned to (JCM)11/12/2008 2/17/2009 PASS
DetailsJohn Menard
2/17/2009 15:08:42 JCM - activity updated through activity BLDA022 from case BLD08-02395.
Routing - PLAN CHECK12/12/2008 2/17/2009 PASS
DetailsJohn Menard
Plan resubmittals received  2/17/2009  
DetailsJohn Menard
Received transmittal and two copies of pages A2.2, A2.4; inserted by Architect and taken back to John Menard
Plan Reviewer's activity  2/17/2009 PASS
DetailsJohn Menard
Reviewed and approved final revised plans with red lined notes and attached plan review clarification notes. JCM
PLANS/APPL TAKEN TO FRONT DESK  2/17/2009 DONE
DetailsJohn Menard
Print Occupancy Form  2/17/2009 DONE
DetailsAlexandra L. DeYoung
Plan Reviewer's activity  1/29/2009 PASS
DetailsJohn Menard
Reviewed and approved structural revisions. JCM
Plan resubmittals requested  1/29/2009 DONE
DetailsJohn Menard
E-mailed the architect requesting additional revisions. JCM
Plan resubmittals received  1/28/2009  
DetailsJohn Menard
Rec'd four copies of sheets S0.1, S1.2, S3.2, S5.1, A2.2, A2.4, A9.2 and four copies of structural calcs- inserted by architect- taken to John M
Routing - PUBLIC WORKS12/10/2008 12/12/2008 PASS
DetailsBeverly Hall
Routing - PLUMBING12/12/2008 12/12/2008 PASS
DetailsBill VanDegrift
per plans and 2003 upc
Routing PW Sewer Design11/14/2008 12/11/2008 PASS
DetailsJon R. Gunnerson
Connect onto existing 6-inch service provided.
Routing PW Drainage12/10/2008 12/10/2008 PASS
DetailsTerry Records
Routing - PLAN CHECK12/8/2008 12/10/2008  
DetailsJohn Menard
Routing - FIRE12/3/200812/3/200812/8/2008 PASS
DetailsScott Arellano
Attached IFC comments to plans
1st review completed  12/8/2008 FAIL
Failed PW, Plumbing, Plan Check
Plan resubmittals received  12/4/2008  
DetailsBarbara Stitt
Received 9 sets of sheets C2, C3, C4, C5, C6 were inserted into plans BLD08-02293, and BLD08-02295 and sheets C2 & C3 into BLD08-02292 by architects office and returned to desks taken from 12-4-08 BAS
Route to Impact Fee Review12/3/200812/8/200812/3/2008 PASS
DetailsCindy M. Gould
Routing - PLAN CHECK12/3/2008 12/3/2008 FAIL
DetailsJohn Menard
Plan resubmittals requested  12/2/2008 DONE
DetailsJohn Menard
E-mailed the architect a copy of the plan review requesting revisions. JCM
Plan resubmittals requested  11/25/2008 DONE
DetailsJohn Menard
E-mailed the architect a copy of the structural plan review comment requesting revisions. JCM
Routing Off Site - STRUCTURAL11/12/2008 11/21/2008 FAIL
DetailsJohn Menard
Called Action Couriers for pick up - Received commen list from consulting structural engineer requesting revisions. JCM
Routing - PLANNING11/20/2008 11/20/2008 PASS
DetailsJosh Wilson
drh 07-00597 Josh W. PASS DR

cup07-00177 Sue H.
Routing - PLUMBING11/18/2008 11/20/2008 FAIL
DetailsBill VanDegrift
need to pass sewer design prior to plumbing acceptance.
Routing - Erosion and Sediment11/17/2008 11/18/2008 PASS
DetailsSteven Webb
ESC plan approved with attached conditions. ESC08-00981
Routing - PUBLIC WORKS11/14/2008 11/17/2008 FAIL
DetailsConnie Baumgartner
Refer to Sewer Design - Jon Gunnerson & Drainage - Terry Records.
Routing PW Solid Waste11/17/2008 11/17/2008 PASS
DetailsPeter J. McCullough
Routing PW Drainage11/17/2008 11/17/2008 FAIL
DetailsBrian Murphy
Grading permit failed
Routing PW Street Lights  11/17/2008 PASS
DetailsHank Alarcon
Routing PW Sewer Rating11/14/2008 11/14/2008 PASS
DetailsConnie Baumgartner
Routing - PLANNING Land Div11/12/2008 11/14/2008 PASS
DetailsTodd Tucker
Parcel has not changed since it was annexed into the city.
Plans ACCEPTED BY PLAN TECH  11/12/2008  
DetailsDarla L Downs
Plan routing begun/NEW & ADDTN  11/12/2008  
DetailsDarla L Downs
Pending Assignment by JCM11/12/2008 11/12/2008 BLDA
DetailsJohn Menard
11/12/2008 11:32:02 JCM - activity updated through activity BLDA166 from case BLD08-02395.
Application received 11/10/2008   
Application received 11/10/2008   
Routing PW Sewer Design12/10/2008    
DetailsJon R. Gunnerson