Letter of compliance | | | 11/2/2009 | | DONE |
Tisha Gallop
|
|
|
|
DOC - Permit Finaled | | | 11/2/2009 | | DONE |
Tisha Gallop
|
|
|
|
FIRE-Final Inspection | 8/10/2009 | 8/10/2009 | 8/10/2009 | A | PASS |
Forrest France
|
|
|
Project related fire alarm upgrade work has been completed, fire life safety for remodel work is acceptable.
|
BLD-Final | 8/6/2009 | 8/7/2009 | 8/7/2009 | A | PASS |
Dave Hannah
|
|
|
daryl Phone #: ###-####
|
FIRE-Final Inspection | 6/24/2009 | 6/25/2009 | 6/25/2009 | A | PART |
Forrest France
|
|
|
Fire life safety inspection completed acceptable for the scope of remodel. Final pending fire alarm upgrade work at the common exit corridors per agreement on file.
|
BLD-Other | 5/7/2009 | 5/8/2009 | 5/8/2009 | A | PART |
Dave Hannah
|
|
|
Daryl- ceiling Phone #: ###-####ok to cover ceiling
|
BLD-Framing/Rough-in | 3/9/2009 | 3/10/2009 | 3/10/2009 | A | PASS |
Dave Hannah
|
|
|
Daryl Phone #: ###-#### ok to cover walls
|
Issue & PRINT to be Invoiced | | | 1/29/2009 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Routing - PLAN CHECK | 1/22/2009 | | 1/28/2009 | | PASS |
Dan Stuart
|
|
|
Resubmittals inserted into plans & Plan review modified. To permit desk to issue.
|
Plan assigned to (DRS) | 1/9/2009 | | 1/28/2009 | | PASS |
Dan Stuart
|
|
|
1/28/2009 07:05:11 DRS - activity updated through activity BLDA022 from case BLD08-02460.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/28/2009 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 1/28/2009 | | DONE |
Barbara Stitt
|
|
|
|
Override - Parcel Holds | | | 1/28/2009 | | |
|
|
|
|
Permit Ready to Issue | | | 1/28/2009 | | DONE |
Barbara Stitt
|
|
|
|
Telephone call | | | 1/28/2009 | | DONE |
Barbara Stitt
|
|
|
E-mailed Curtis and told him that permit is ready & fees due///1-28-09 BAS
|
Plan resubmittals received | | | 1/27/2009 | | |
Dan Stuart
|
|
|
Rec'd one response letter and two copies of sheets A2.0, A3.0, & A3.5- taken to Dan S
|
Routing - FIRE | 1/16/2009 | 1/16/2009 | 1/22/2009 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
1st review completed | | | 1/22/2009 | | FAIL |
|
|
|
Failed Plan Check
|
Route to Impact Fee Review | 1/16/2009 | 1/22/2009 | 1/16/2009 | | PASS |
Cindy M. Gould
|
|
|
|
Plan resubmittals requested | | | 1/16/2009 | | DONE |
|
|
|
E-mailed copy of plan review with cover letter to architect for resubmittals.
|
Routing - PLAN CHECK | 1/13/2009 | | 1/16/2009 | | FAIL |
Dan Stuart
|
|
|
Resubmittal required. Copy of plan review e-mailed to architect. Routing plans to fire code analayst for review.
|
Routing - PLUMBING | 1/12/2009 | | 1/13/2009 | | PASS |
Bill VanDegrift
|
|
|
per plans and 2003 upc --- No med gas system ---
|
Routing - PUBLIC WORKS | 1/9/2009 | | 1/12/2009 | | PASS |
Beverly Hall
|
|
|
|
Intake Approval | | | 1/9/2009 | | PASS |
Jason Blais
|
|
|
Originally submitted 11/20/08. Delay because of a communication issue with applicant and Permit Counter on whether a plan review check was going to be submitted or not.
|
Routing PW Sewer Rating | 1/9/2009 | | 1/9/2009 | | PASS |
Louise Waldorf
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/9/2009 | | DONE |
Darla L Downs
|
|
|
This plan is running behind as I thought they needed to bring in a check for the iniitil value . This is not the case we will bill ST. Lukes. ///DLD
|
Pending Assignment by JCB | 1/9/2009 | | 1/9/2009 | | DONE |
Jason Blais
|
|
|
|
Application received | | 11/20/2008 | | | |
|
|
|
|