Third Notice | | 11/8/2010 | 11/30/2010 | | DONE |
|
|
|
mailed//all contact phone numbers disconnected, put company on hold.
|
Third Notice | | 8/30/2010 | 10/25/2010 | | DONE |
|
|
|
mailed
|
Third Notice | | 7/13/2010 | 8/16/2010 | | DONE |
|
|
|
will process FV at same time of Bld08-01776. faxed/didn't go through, mailed on 8/17
|
Second Notice | | 5/6/2010 | 5/10/2010 | | DONE |
|
|
|
|
First Notice | 4/9/2010 | 4/9/2010 | 4/26/2010 | | DONE |
Dave Hannah
|
|
|
|
BLD-Final | 4/9/2010 | 4/9/2010 | 4/9/2010 | P | PASS |
Dave Hannah
|
|
|
|
DOC - Permit Finaled | 4/9/2010 | 4/9/2010 | 4/9/2010 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 10/23/2009 | 10/26/2009 | 10/26/2009 | P | PASS |
Dave Hannah
|
|
|
Eric ###-####//will meet Aaron out on site
|
BLD-Concrete | 2/25/2009 | 2/26/2009 | 2/26/2009 | A | PART |
Dave Hannah
|
|
|
Carl- pouring at 1 Phone #: ###-#### cmu columns spec inspector will cover
|
Issue & PRINT to be Invoiced | | | 12/16/2008 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/12/2008 | | DONE |
Barbara Stitt
|
|
|
|
Inspection Record Card- Bld | | | 12/12/2008 | | DONE |
Barbara Stitt
|
|
|
|
Telephone call | | | 12/12/2008 | | DONE |
Barbara Stitt
|
|
|
Sent an email to Mike with Sommer Construction and Jim pardy to let them know the fees due and that the permit is ready for pick up///12-12-08 @ 12:09pm BAS
|
Plan assigned to (SRZ) | 11/24/2008 | 11/24/2008 | 11/26/2008 | | PASS |
Sam Zahorka
|
|
|
11/26/2008 11:22:39 SRZ - activity updated through activity BLDA022 from case BLD08-02474.
|
Routing - PLAN CHECK | 11/24/2008 | | 11/25/2008 | | PASS |
Sam Zahorka
|
|
|
|
1st review completed | | | 11/25/2008 | | DONE |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/25/2008 | | DONE |
Sam Zahorka
|
|
|
|
Application received | | 11/24/2008 | 11/24/2008 | | DONE |
Barbara Stitt
|
|
|
|
Plan Reviewer's activity | | | 11/24/2008 | | DONE |
Sam Zahorka
|
|
|
See the attached request letter for Idaho engineered early slab work. No other construction allowed under this permit. All other work to be approved per BLD08-01776. SRZ
|
Routing - Erosion and Sediment | 11/24/2008 | | 11/24/2008 | | PASS |
Sam Zahorka
|
|
|
Erosion and Sediment Control permit was issued under ESC08-00924. Ok per Steve Webb for Slab work.
|
Case Summary (BLD) | | | 11/24/2008 | | DONE |
Sam Zahorka
|
|
|
|
Case Summary (BLD) | | | 11/24/2008 | | DONE |
|
|
|
|