Third Notice | | 10/18/2009 | 10/19/2009 | | DONE |
|
|
|
|
Third Notice | | 9/8/2009 | 10/8/2009 | | DONE |
|
|
|
faxed
|
Second Notice | | 7/23/2009 | 9/8/2009 | | DONE |
|
|
|
|
First Notice | | 3/5/2009 | 7/23/2009 | | DONE |
|
|
|
|
Permanent Occupancy | | | 3/5/2009 | | DONE |
Barbara Stitt
|
|
|
|
FIRE-Final Inspection | 2/20/2009 | 2/20/2009 | 2/20/2009 | P | PASS |
Forrest France
|
|
|
Corrections completed per final structural inspection done by D. Hannah, life safety finaled.
|
FIRE-Final Inspection | 2/19/2009 | 2/20/2009 | 2/20/2009 | A | FAIL |
Forrest France
|
|
|
Need to provide approved door hardware at two locations including the restroom and new conference room, repair one EM light, post one fire extinguisher as indicated per plan.
|
BLD-Final | 2/19/2009 | 2/20/2009 | 2/20/2009 | P | PASS |
Dave Hannah
|
|
|
kevin Phone #: ###-#### ok for perm occ after fire oks
|
BLD-Conference | 1/28/2009 | 1/28/2009 | 1/29/2009 | P | PASS |
Dave Hannah
|
|
|
kevin Phone #: ###-####
|
Case Summary (BLD) | | | 1/21/2009 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 1/15/2009 | | DONE |
Tim L. Woodard
|
|
|
During the coarse of this project the applicant made minor variations from the approved drawings. I have reviewed these changes and they in no way effect the original plan review. The new sheets will be scanned in and attached as resubmittals. TLW
|
Plan resubmittals received | | | 1/14/2009 | | |
Barbara Stitt
|
|
|
Received 1 cover letter to Tim Woodard from CTA Architects dated 1-12-09, 2 copies of sheets G102, A101, A201, E001, E100, E200, E300, E400. One set stamped with resubmital stamp and given back to applicant 2nd set taken to Tim Woodard's desk///1-14-09 @ 4:15pm BAS
|
BLD-Framing/Rough-in | 1/9/2009 | 1/9/2009 | 1/9/2009 | P | PART |
Dave Hannah
|
|
|
Kevin Phone #: ###-#### ok to cover but arc has changed wall layout nees to resubmit a new plan showing changes
|
Issue PAID IN FULL permit | | | 12/16/2008 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/15/2008 | | DONE |
Rita DeYoung
|
|
|
|
Plan assigned to (TLW) | 11/25/2008 | | 12/15/2008 | | PASS |
Tim L. Woodard
|
|
|
12/15/2008 10:44:16 TLW - activity updated through activity BLDA022 from case BLD08-02478.
|
Routing - PLAN CHECK | 12/15/2008 | | 12/15/2008 | | PASS |
Tim L. Woodard
|
|
|
Resubmittals approved TLW Refer to plan review report.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/15/2008 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 12/15/2008 | | DONE |
|
|
|
|
Print Occupancy Form | | | 12/15/2008 | | DONE |
|
|
|
|
CHANGE STATUS TO (RDY) | | | 12/15/2008 | | DONE |
|
|
|
|
Telephone call | | | 12/15/2008 | | DONE |
|
|
|
Called Bryan left message permit ready and fees given
|
Plan resubmittals received | | | 12/9/2008 | | |
Tim L. Woodard
|
|
|
Rec'd one copy of response letter, new application for new address, and two copies of sheets G102, A101, and A201; inserted by arch rep; taken back to Tim W
|
Routing - PLAN CHECK | 12/4/2008 | | 12/4/2008 | | FAIL |
Tim L. Woodard
|
|
|
Refer to plan review report. TLW
|
Routing - FIRE | | | 12/4/2008 | | PASS |
Tim L. Woodard
|
|
|
Field Verify.
|
1st review completed | | | 12/4/2008 | | FAIL |
Tim L. Woodard
|
|
|
Failed plan check
|
Recd Pcfee & Taken To Pln CK | | | 11/25/2008 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/25/2008 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Application received | | 11/24/2008 | | | |
|
|
|
|