Second Notice | | 4/8/2010 | 4/16/2010 | | DONE |
Barbara Stitt
|
|
|
|
First Notice | 3/18/2010 | 3/18/2010 | 3/29/2010 | | DONE |
Dave Hannah
|
|
|
|
BLD-Final | 3/18/2010 | 3/18/2010 | 3/18/2010 | P | PASS |
Dave Hannah
|
|
|
|
DOC - Permit Finaled | 3/18/2010 | 3/18/2010 | 3/18/2010 | P | PASS |
Dave Hannah
|
|
|
|
FIRE-Final Inspection | 3/11/2009 | 3/12/2009 | 3/12/2009 | P | PASS |
Forrest France
|
|
|
Fire life safety inspection passed per activity notes 2/26, verified with contractor inspection record has been signed.
|
BLD-Final | 3/11/2009 | 3/12/2009 | 3/12/2009 | P | PASS |
Dave Hannah
|
|
|
Joe Phone #: ###-#### ok for c.c
|
Letter of compliance | | | 3/12/2009 | | DONE |
Tisha Gallop
|
|
|
|
Letter of compliance | | | 3/12/2009 | | DONE |
Tisha Gallop
|
|
|
|
FIRE-Conference | 3/11/2009 | 3/11/2009 | 3/11/2009 | P | DONE |
Forrest France
|
|
|
Regarding fire life safety inspection requirements for permit final.
|
BLD-Final | 2/25/2009 | 2/26/2009 | 2/26/2009 | P | PART |
Dave Hannah
|
|
|
Joe Phone #: ###-####second floor restrooms ok to use and one of the two on ground floor
|
FIRE-Final Inspection | 2/25/2009 | 2/26/2009 | 2/26/2009 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
FIRE-Final Inspection | 2/25/2009 | 2/25/2009 | 2/25/2009 | P | PART |
Troy Cobbley
|
|
|
The first and second floor restrooms are ok to occupy.
|
FIRE-Final Inspection | 2/12/2009 | 2/12/2009 | 2/13/2009 | P | NR |
Forrest France
|
|
|
Pending project related fire sprinkler permit work.
|
FIRE-Final Inspection | 2/3/2009 | 2/3/2009 | 2/3/2009 | P | FAIL |
Troy Cobbley
|
|
|
This inspection was for the first and second floor restrooms. Sprinkler modifications are required due to existing sprinkler heads being located too far from the ceiling and possibly obstructed by duct work and soffits. One sprinkler upright has been painted.. Life safety will be ok in the first and second floor restrooms once a sprinkler permit is issued, inspected and passed.
|
BLD-Final | 2/2/2009 | 2/3/2009 | 2/3/2009 | A | FAIL |
Dave Hannah
|
|
|
joe Phone #: ###-#### needs fire final and fix several ada issuse
|
BLD-Framing/Rough-in | 12/15/2008 | 12/15/2008 | 12/16/2008 | P | PART |
Dave Hannah
|
|
|
bill Phone #: ###-#### ground floor back corrador duct wook ok to cover
|
BLD-Framing/Rough-in | 12/1/2008 | 12/2/2008 | 12/2/2008 | A | PART |
Dave Hannah
|
|
|
bill Phone #: ###-#### ok to cover ceiling on second floor corrador
|
Issue PAID IN FULL permit | | | 12/1/2008 | | DONE |
|
|
|
|
CHANGE STATUS TO (RDY) | | | 11/28/2008 | | DONE |
|
|
|
|
Telephone call | | | 11/28/2008 | | DONE |
|
|
|
called Nate Coombs permit ready and fee given
|
Permit Ready to Issue | | | 11/28/2008 | | DONE |
Rita DeYoung
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/26/2008 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Plan assigned to (TLW) | 11/26/2008 | | 11/26/2008 | | DONE |
Tim L. Woodard
|
|
|
Assigned to Ben Pavelka. (BSP)
|
Recd Pcfee & Taken To Pln CK | | | 11/26/2008 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Plan assigned to (BSP) | 11/26/2008 | | 11/26/2008 | | PASS |
Ben S. Pavelka
|
|
|
11/26/2008 16:15:25 BSP - activity updated through activity BLDA022 from case BLD08-02487.
|
Routing - FIRE | | | 11/26/2008 | | PASS |
Ben S. Pavelka
|
|
|
Field Verify
|
Case Summary (BLD) | | | 11/26/2008 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 11/26/2008 | | 11/26/2008 | | PASS |
Ben S. Pavelka
|
|
|
|
1st review completed | | | 11/26/2008 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/26/2008 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/26/2008 | | DONE |
|
|
|
|
Application received | | 11/25/2008 | 11/25/2008 | | DONE |
Alexandra L. DeYoung
|
|
|
|