Second Notice | | 7/24/2009 | 8/5/2009 | | DONE |
|
|
|
This permit finaled on the web by Bill Waterfield
|
First Notice | | 5/27/2009 | 7/24/2009 | | DONE |
|
|
|
|
BLD-Final | 5/22/2009 | 5/26/2009 | 5/27/2009 | A | PASS |
Dave Hannah
|
|
|
bill Phone #: ###-####
|
Permanent Occupancy UNPAID FEE | | | 5/27/2009 | | DONE |
Alexandra L. DeYoung
|
|
|
|
FIRE-Final Inspection | 5/21/2009 | 5/22/2009 | 5/22/2009 | A | PASS |
Forrest France
|
|
|
Noted plan modification okayed, fire life safety final walkthrough passed.
|
FIRE-Final Inspection | 5/19/2009 | 5/20/2009 | 5/20/2009 | P | FAIL |
Troy Cobbley
|
|
|
The life safety will be ok to pass when the project related fire sprinkler permit is passed
|
Case Summary (BLD) | | | 5/6/2009 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/6/2009 | | DONE |
Tisha Gallop
|
|
|
|
FIRE-Final Inspection | 4/29/2009 | 4/30/2009 | 4/30/2009 | A | FAIL |
Forrest France
|
|
|
Project is not in condition for final fire life safety at this time, FIR09-00101 is not ready for final, some items incomplete including door hardware, floor finishes, drop ceilings not in place, etc. Notified contractor that a separate tenant permit request for occupancy is needed per the project description prior to use.
|
BLD-Other | 4/28/2009 | 4/29/2009 | 4/29/2009 | P | PASS |
Dave Hannah
|
|
|
Bill- ceiling Phone #: ###-####
|
BLD-Framing/Rough-in | 1/22/2009 | 1/22/2009 | 1/23/2009 | P | PASS |
Dave Hannah
|
|
|
bill Phone #: ###-####
|
Plan assigned to (CDM) | 12/5/2008 | 12/5/2008 | 12/10/2008 | | PASS |
Carl D Madsen
|
|
|
12/10/2008 08:20:31 CDM - activity updated through activity BLDA022 from case BLD08-02488.
|
Case Summary (BLD) | | | 12/10/2008 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/10/2008 | | |
|
|
|
|
Inspection Record Card- Bld | | | 12/10/2008 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 12/10/2008 | | 12/10/2008 | | PASS |
Carl D Madsen
|
|
|
|
Routing - FIRE | | | 12/10/2008 | | PASS |
|
|
|
Verify in field CDM
|
Telephone call | | | 12/10/2008 | | DONE |
|
|
|
t/c w jeff likes at ###-#### - permit ready and fees given - also need gc name and rce #
|
Permit Ready to Issue | | | 12/10/2008 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 12/10/2008 | | DONE |
|
|
|
|
Plan assigned to (TLW) | 11/28/2008 | | 12/9/2008 | | DEFR |
Tim L. Woodard
|
|
|
Reassigned plans to Carl M.
|
Plan resubmittals received | | | 12/8/2008 | | |
Carl D Madsen
|
|
|
Rec'd transmittal letter, revised copy of application, and three copies of sheet A1.1; taken to Carl M
|
1st review completed | | | 12/5/2008 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 11/28/2008 | | 12/5/2008 | | FAIL |
Carl D Madsen
|
|
|
Waiting on documentation of correct address. The plans indicate that the work is being done on the Key Bank Building but the address is not consistent with that structure. Left a message with Jeff Likes at BRS 12-5-08 for further information CDM
|
Recd Pcfee & Taken To Pln CK | | | 11/28/2008 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/28/2008 | | DONE |
Darla L Downs
|
|
|
|
Application received | | 11/25/2008 | | | |
|
|
|
|