Case Summary (BLD) | | | 4/19/2010 | | DONE |
|
|
|
|
Second Notice | | 7/23/2009 | 7/28/2009 | | DONE |
|
|
|
|
First Notice | | 4/27/2009 | 7/23/2009 | | DONE |
|
|
|
|
Permanent Occupancy UNPAID FEE | | | 4/27/2009 | | DONE |
Tisha Gallop
|
|
|
|
BLD-Final | 4/24/2009 | 4/24/2009 | 4/24/2009 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 4/24/2009 at 7:40:50 AM. Contact: ###-####. OK for perm occ.
|
FIRE-Final Inspection | 4/23/2009 | 4/24/2009 | 4/24/2009 | A | PASS |
Forrest France
|
|
|
Fire life safety final inspection completed satisfactory, project related fire alarm and sprinkler permits finaled.
|
Zoning Approval | 4/23/2009 | 4/23/2009 | 4/23/2009 | | DONE |
Lucinda Grames
|
|
|
|
BLD-Other | 3/26/2009 | 3/27/2009 | 3/27/2009 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 3/26/2009 at 8:08:21 AM. Contact: ###-####. ceiling grid ok.
|
BLD-Energy code compliance | 2/12/2009 | 2/12/2009 | 2/12/2009 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 2/12/2009 at 10:20:05 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 2/5/2009 | 2/6/2009 | 2/6/2009 | A | PASS |
Tom Arcoraci
|
|
|
mike Phone #: ###-####
|
Issue PAID IN FULL permit | | | 1/13/2009 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Plan assigned to (CJW) | 12/5/2008 | | 12/19/2008 | | PASS |
Carl Westfall
|
|
|
12/19/2008 10:49:23 CJW - activity updated through activity BLDA022 from case BLD08-02516.
|
Routing - PLAN CHECK | 12/16/2008 | | 12/19/2008 | | PASS |
Carl Westfall
|
|
|
Completed the resubmittal review. Drawings approved.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/19/2008 | | DONE |
|
|
|
|
Print Occupancy Form | | | 12/19/2008 | | DONE |
|
|
|
|
Telephone call | | | 12/19/2008 | | DONE |
|
|
|
t/c w damon beard at ###-#### - permit ready and fees given - also need rp name
|
Telephone call | | | 12/19/2008 | | DONE |
|
|
|
t/c w damon beard at ###-#### - permit ready and fees given - also need rp name
|
Permit Ready to Issue | | | 12/19/2008 | | DONE |
|
|
|
|
Routing - FIRE | 12/12/2008 | 12/12/2008 | 12/16/2008 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
Plan resubmittals received | | | 12/16/2008 | | DONE |
|
|
|
Received 1 transmittal letter,1 response ,1 structural calc,and 2 copies of sheets A-1,A-5,A-7,M-4,M-6 taken to Carl W.
|
Telephone call | | | 12/16/2008 | | DONE |
Scott Arellano
|
|
|
New fire hydrant installation location. - The proposed alternate location for the new hydrant installation to the east side of Janeen street is acceptable. *SJA*
|
1st review completed | | | 12/16/2008 | | FAIL |
|
|
|
Failed Plan Check
|
Route to Impact Fee Review | 12/12/2008 | 12/17/2008 | 12/12/2008 | | PASS |
Cindy M. Gould
|
|
|
Tenant improvement no fees
|
Routing - PLAN CHECK | 12/9/2008 | | 12/12/2008 | | FAIL |
Carl Westfall
|
|
|
The IBC plan review was started on December 10, 2008 and was finished on December 12, 2008. Revised drawings were required. See the plan review report.
|
Routing - Design Review | 12/8/2008 | | 12/9/2008 | | PASS |
Sarah Schafer
|
|
|
Sarah Schafer. CZC08-00180
Forwarded this one on to Lucinda for review. She reviewed the Zoning certificate.
|
Routing - Erosion and Sediment | 12/5/2008 | | 12/8/2008 | | PASS |
Steven Webb
|
|
|
ESC plan waiver request approved with attached conditions. ESC08-01027. Need certified RP prior to issuance of permit. RP listed on the application is not certified.
|
Routing - PUBLIC WORKS | 12/5/2008 | | 12/5/2008 | | PASS |
Beverly Hall
|
|
|
|
Pending Assignment by JCB | 12/5/2008 | | 12/5/2008 | | DONE |
Jason Blais
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/5/2008 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Routing PW Sewer Rating | 12/5/2008 | | 12/5/2008 | | PASS |
Louise Waldorf
|
|
|
|
Intake Approval | | | 12/4/2008 | | PASS |
Dan Stuart
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/4/2008 | | |
|
|
|
|
Application received | | 12/4/2008 | | | |
|
|
|
|