First Notice | | 5/18/2009 | 8/5/2009 | | DONE |
|
|
|
|
FIRE-Final Inspection | 5/14/2009 | 5/18/2009 | 5/18/2009 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Final | 5/14/2009 | 5/18/2009 | 5/18/2009 | P | PASS |
Mike Jordan
|
|
|
forrest Phone #: ###-####. ok for perm occ.
|
Permanent Occupancy | | | 5/18/2009 | | DONE |
Tisha Gallop
|
|
|
|
BLD-Other | 4/30/2009 | 5/1/2009 | 5/1/2009 | A | PASS |
Mike Jordan
|
|
|
Forrest- racking Phone #: ###-####
|
BLD-Framing/Rough-in | 4/27/2009 | 4/28/2009 | 4/28/2009 | A | PASS |
Mike Jordan
|
|
|
forrest - ceiling cover Phone #: ###-####
|
BLD-Framing/Rough-in | 4/24/2009 | 4/27/2009 | 4/27/2009 | A | PART |
Mike Jordan
|
|
|
forrest Phone #: ###-####. Needs to install clips on all main and cross runners. Will check on final.
|
BLD-Framing/Rough-in | 4/6/2009 | 4/7/2009 | 4/7/2009 | A | PASS |
Mike Jordan
|
|
|
Forrest Phone #: ###-####. Framing in restrooms. Also verified with contractor that backing is fire treated wood.
|
BLD-Framing/Rough-in | 4/3/2009 | 4/6/2009 | 4/6/2009 | A | PASS |
Mike Jordan
|
|
|
Forrest Phone #: ###-####. Grid has been installed as per plan.
|
BLD-Framing/Rough-in | 4/1/2009 | 4/3/2009 | 4/3/2009 | A | PART |
Mike Jordan
|
|
|
Forrest Phone #: ###-####. Needs to install gird as per approved plan or get rfi fro architect. Interio framed walls ok.
|
CHANGE STATUS TO (ISS) | | | 4/1/2009 | | DONE |
Tisha Gallop
|
|
|
picked up and paid for plan mod
|
(F) Reprint permit | | | 4/1/2009 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 3/31/2009 | | DONE |
|
|
|
left vm for brian hare at ###-#### - permit ready (plan mod) and fees given
|
Override - Parcel Holds | | | 3/31/2009 | | |
|
|
|
|
Plan assigned to (TLW) | 3/20/2009 | | 3/30/2009 | | PASS |
Tim L. Woodard
|
|
|
3/30/2009 15:56:10 TLW - activity updated through activity BLDA022 from case BLD08-02528.
|
Routing - PLAN CHECK | 3/20/2009 | | 3/30/2009 | | PASS |
Tim L. Woodard
|
|
|
Approved as submitted. TLW
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/30/2009 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 3/30/2009 | | DONE |
Tim L. Woodard
|
|
|
|
Plan Modification Accepted | | | 3/20/2009 | | |
Tim L. Woodard
|
|
|
Plan modification accepted for BLD08-02528 for the redesign of storefront structural framing, changes to stockyoom & hallwayframing dimensions & shelving fixtures. Due to placement of rear demising wall by landlord.on sheets A000,A101,A104,A300,A301,S200,S300,S400. routed to Tim W.
|
Issue PAID IN FULL permit | | | 3/6/2009 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/27/2009 | | DONE |
|
|
|
|
Telephone call | | | 1/27/2009 | | DONE |
Cathy Brown
|
|
|
tlk to jay smith for moria ###-#### that permit and fees are ready to be picked up but needs GC/RCE#
|
Permit Ready to Issue | | | 1/27/2009 | | DONE |
Cathy Brown
|
|
|
|
Routing - PLAN CHECK | 1/8/2009 | | 1/26/2009 | | PASS |
Tim L. Woodard
|
|
|
Resubmittals appear to address all issues. TLW
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/26/2009 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 1/26/2009 | | DONE |
|
|
|
|
Plan assigned to (TLW) | 12/9/2008 | | 1/26/2009 | | PASS |
Tim L. Woodard
|
|
|
1/26/2009 17:18:02 TLW - activity updated through activity BLDA022 from case BLD08-02528.
|
Plan resubmittals received | | | 1/16/2009 | | |
Tim L. Woodard
|
|
|
Rec'd by mail- response letter and three copies of sheets A002 & A102.1- taken to Tim W
|
Routing - FIRE | 1/5/2009 | | 1/8/2009 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
1st review completed | | | 1/8/2009 | | FAIL |
|
|
|
Failed Plan Check
|
Routing - PLAN CHECK | 12/10/2008 | | 1/5/2009 | | FAIL |
Tim L. Woodard
|
|
|
Refer to plan review report. TLW
|
Routing - PUBLIC WORKS | 12/9/2008 | | 12/10/2008 | | PASS |
Louise Waldorf
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/9/2008 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/9/2008 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Application received | | 12/9/2008 | | | |
Alexandra L. DeYoung
|
|
|
|