Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD08-02579
StatusFinaled
Name DOUG LASHER CONSTRUCTION
Site Address 877 S CAPITOLA WAY
Project Name 
Customer Number 
ePlanReviewNo
Description
This permit is for the construction of a new two story single family dwelling with an attached garage. The main story is 1247 square feet of living space with a den and one bathroom as well as an attached garage of 1247 square feet. The second story is 1801 square feet with four bedrooms, two bathrooms and a bonus room. There is a covered front patio of 145 square feet and a covered back patio of 128 square feet. THE PERMIT HOLDER is responsible to comply with section R602.10 for wall bracing or build to an engineered design. The side setbacks have eaves that extend to within the five foot fire separation distance and will be rated to one hour on the underneath side per the detail on the approved plans. R-2D zoning district and building setbacks per Planning and Zoning. Built per all approved plans, red lining and plan review report. (BSP)
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final5/13/20095/14/20095/15/2009PPASS
DetailsDave Hannah
Bryan Phone #: ###-####
DOC - Permit Finaled5/15/20095/15/20095/15/2009PPASS
DetailsDave Hannah
BLD-Final5/11/20095/13/20095/14/2009PCANC
DetailsDave Hannah
Bryan Phone #: ###-####
BLD-Framing/Rough-in3/20/20093/23/20093/23/2009APASS
DetailsDave Hannah
Brian-stocco paper & sofit sheet rock Phone #: ###-#### ok to cover ext
BLD-Energy code compliance3/10/20093/11/20093/11/2009PPASS
DetailsDave Hannah
Scheduled by a contractor via Hello! on 3/10/2009 at 12:41:37 PM. Contact: ###-####. c/n items completed ok to cover
BLD-Framing/Rough-in3/9/20093/10/20093/10/2009PPART
DetailsDave Hannah
bryan Phone #: ###-#### ok to insulate but c/n on site
BLD-Final3/9/20093/10/20093/10/2009ANR
DetailsDave Hannah
bryan Phone #: ###-####
BLD-Framing/Rough-in3/6/20093/9/20093/9/2009PNR
DetailsDave Hannah
bryan Phone #: ###-#### needs mec r/i and seal package
BLD-Footing1/26/20091/26/20091/26/2009PPASS
DetailsDave Hannah
Bryan Phone #: ###-####
Issue PAID IN FULL permit  1/26/2009 DONE
Plan assigned to (BSP)12/29/200812/29/200812/30/2008 PASS
DetailsBen S. Pavelka
12/30/2008 12:34:18 BSP - activity updated through activity BLDA022 from case BLD08-02579.
Case Summary (BLD)  12/30/2008 DONE
PLANS/APPL TAKEN TO FRONT DESK  12/30/2008 DONE
Inspection Record Card- Bld  12/30/2008 DONE
Details
Telephone call  12/30/2008 DONE
Details
left vm for doug lasher at ###-#### - permit ready and fees given
Permit Ready to Issue  12/30/2008 DONE
Details
Routing - PLAN CHECK12/24/2008 12/30/2008 PASS
DetailsBen S. Pavelka
Route to Impact Fee Review12/22/200812/26/200812/29/2008 PASS
DetailsCindy M. Gould
Plans ACCEPTED BY PLAN CHECK  12/29/2008  
DetailsBen S. Pavelka
Routing - PUBLIC WORKS12/23/2008 12/24/2008 PASS
DetailsLouise Waldorf
Routing - PLANNING12/22/2008 12/23/2008 PASS
DetailsLucinda Grames
Routing - Addressing12/22/2008 12/22/2008 PASS
DetailsChris Pichardo
Application received 12/22/2008   
DetailsAlexandra L. DeYoung