Permit Information
Permit NumberBLD08-02600
StatusFinaled
Name PETRA INC
Site Address 5521 E WARM SPRINGS AVE
Project NameRiverstone International Lower
Customer Number 
ePlanReviewNo
Description
Riverstone International Lower School - ESC08-01050 under the grading permit--To construct a new 24,300 square foot, one story elementary school building. This building will be constructed of concrete tilt-up exterior walls and wood framed construction. This permit will also include related site improvements. All construction per the approved plans and attached comment list. DRH08-00393 - JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
PubWorks Occupancy Approval5/17/20105/17/20105/17/2010 DONE
DetailsTiffany Lowery
Final Occupancy sign off B Murphy
Second Notice 4/5/20104/22/2010 DONE
DetailsBarbara Stitt
First Notice 3/12/20103/26/2010 DONE
Permanent Occupancy  3/2/2010 DONE
BLD-Final2/16/20102/17/20102/17/2010PPASS
DetailsDave Hannah
gene- call 30 mins prior to going Phone #: ###-#### dave bathroom hardware ok ada singage wrong side of the doors 301 ok for perm occ
BLD-Final2/16/20102/16/20102/16/2010PDEFR
DetailsJim Storey
gene- call 30 mins prior to going Phone #: ###-#### to pm with 425
Case Summary (BLD)  1/7/2010  
BLD-Final12/28/200912/28/200912/28/2009PPART
DetailsDave Hannah
gene Phone #: ###-#### ok for temp occ
FIRE-Final Inspection12/28/200912/28/200912/28/2009APASS
DetailsForrest France
Fire life safety inspection passed, correction notice items completed.
Temporary Occupancy12/28/20093/28/201012/28/2009 DONE
DetailsTisha Gallop
Permanent occupancy pending sign off by Plumbing, Public Works, Zoning/Landscaping, Structural and final inspection on Grading permit Bld09-00229.
FIRE-Final Inspection12/21/200912/22/200912/22/2009ANR
DetailsForrest France
Project related fire alarm and sprinkler permit work must be finaled prior to life safety approvals. Preliminary check of EM lights and exit signs okayed with the exception of four locations.
BLD-Framing/Rough-in12/18/200912/18/200912/18/2009PPART
DetailsDave Hannah
Ceiling grid for cover inspection please-Gene Phone #: ###-#### ok to cover ceiling
BLD-Framing/Rough-in12/16/200912/17/200912/17/2009APART
DetailsDave Hannah
Gene-Ceiling grid for cover inspection please Phone #: ###-#### ok to put border tiles in after other trades ok
BLD-Energy code compliance9/30/20099/30/20099/30/2009PPART
DetailsDave Hannah
Gene-insulation on high ceiling area inspection please Phone #: ###-#### ok to cover
BLD-Energy code compliance9/18/20099/21/20099/21/2009APASS
DetailsDave Hannah
gene Phone #: ###-#### nw wing ok to cover
BLD-Energy code compliance9/15/20099/16/20099/16/2009APART
DetailsDave Hannah
gene Phone #: ###-#### se and sw wing insulation ok framing ok ok to cover
BLD-Framing/Rough-in9/9/20099/9/20099/10/2009PPART
DetailsDave Hannah
Gene-bolting hold downs and exterior insulation please Phone #: ###-#### shear ok west wing ok to cover walls
BLD-Framing/Rough-in9/2/20099/3/20099/4/2009APART
DetailsDave Hannah
Gene Phone #: ###-#### ok to insulate ext walls ok to one side int walls but crew needs to bolt down hold downs also washers on sill plates for shear walls need engineer to reveiw size and type
BLD-Framing/Rough-in8/27/20098/27/20098/27/2009PPART
DetailsDave Hannah
Gene Phone #: ###-#### high roof ok to cover
BLD-Framing/Rough-in8/17/20098/17/20098/18/2009PPART
DetailsDave Hannah
Gene-roof nailing for cover inspection please Phone #: ###-#### ok to cover roof
BLD-Other7/22/20097/22/20097/22/2009PDONE
DetailsDave Hannah
gene - please call 1/2 hr prior - nailing on the roof Phone #: ###-####
BLD-Framing/Rough-in6/30/20096/30/20097/1/2009PDEFR
DetailsDave Hannah
Gene Phone #: ###-####
BLD-Footing6/19/20096/19/20096/19/2009APART
DetailsDave Hannah
Jim ###-####- pouring at 9
Override - Parcel Holds  6/19/2009  
Override - Parcel Holds  6/19/2009  
BLD-Concrete5/26/20095/27/20095/27/2009APART
DetailsDave Hannah
Clint Phone #: ###-#### crews still working on tilt up panels
BLD-Footing4/20/20094/21/20094/21/2009APART
DetailsDave Hannah
clint Phone #: ###-####
BLD-Footing4/14/20094/15/20094/15/2009APART
DetailsDave Hannah
Clint Phone #: ###-#### int ftgs for under slab mti also on site working on geo and conc and spec inspection
Issue PAID IN FULL permit  3/30/2009 DONE
DetailsTisha Gallop
Override - Parcel Holds  3/27/2009  
Permit Ready to Issue  3/27/2009 DONE
Print Occupancy Form  3/23/2009 DONE
DetailsAlexandra L. DeYoung
Routing - PARKS DEPARTME3/20/2009 3/20/2009 PASS
DetailsBarbara Stitt
Contact David Salvage at ###-#### ext 310 concerning green belt issues--Per Davids Selvage with the Parks Department; NO Certificate of Occupancy until approved proof of conyenace of a permanet path easment & maintenace agreement in favor of either Ada County/ Boise City. Please make sure that Grading & Drainage plans (BLD09-00229) are incorporated with these notations also. For any questions please contact David at ###-#### ext 310
Routing - PLAN CHECK3/17/2009 3/17/2009 PASS
DetailsJohn Menard
PLANS/APPL TAKEN TO FRONT DESK  3/17/2009 DONE
DetailsJohn Menard
Routing - PLANNING3/16/2009 3/17/2009 PASS
DetailsAndrea Tuning
Plan assigned to (JCM)1/5/2009 3/17/2009 PASS
DetailsJohn Menard
3/17/2009 14:55:24 JCM - activity updated through activity BLDA022 from case BLD08-02600.
Routing - PLANNING3/17/2009 3/17/2009 PASS
DetailsJoshua Johnson
CUP08-00092-Josh Johnson
Routing PW Sewer Design1/6/2009 3/16/2009 PASS
DetailsJon R. Gunnerson
Connect onto sewer stub to be built by City
Routing - PLAN CHECK3/3/2009 3/16/2009 PASS
DetailsJohn Menard
Routing - PUBLIC WORKS3/16/2009 3/16/2009 PASS
DetailsBeverly Hall
Routing PW Sewer Design2/25/2009 3/3/2009 FAIL
DetailsJon R. Gunnerson
Routing PW Street Lights  3/3/2009 PASS
DetailsHank Alarcon
Routing PW Solid Waste3/3/2009 3/3/2009 PASS
DetailsPeter J. McCullough
Routing PW Street Lights3/3/2009 3/3/2009 PASS
DetailsHank Alarcon
Routing - PUBLIC WORKS2/24/2009 3/3/2009 FAIL
DetailsJohn Menard
Failed Sewer Design
Plan resubmittals received  2/26/2009  
Received two copies of a1.21, e2.0; inserted by rep. and taken back to Public Works
Plan resubmittals received  2/26/2009  
Received two copies of sheets a1.21; inserted by rep. and taken back to Public Works
Routing PW Solid Waste2/25/2009 2/26/2009 FAIL
DetailsPeter J. McCullough
Need to change trash enclosure detail drawing to show 120 degree door oening and only one dumpster (with recycle carts).
Contact Peter McCullough ###-####
Received Certificate of Value  2/25/2009 DONE
DetailsBarbara Stitt
Received revised cert of value-seperated out grading & drainage///2-25-09 BAS
Routing PW Drainage2/24/2009 2/25/2009 PASS
DetailsBrian Murphy
Plan resubmittals received  2/24/2009  
DetailsJohn Menard
Received 1 cover transmittal,3 copies of sheets A2.34, A3.22, inserted into plans
Plan Reviewer's activity  2/24/2009 PASS
DetailsJohn Menard
Reviewed and approved second structural plan revisions and calculations. JCM
Plan Reviewer's activity  2/24/2009 PASS
DetailsJohn Menard
Reviewed and approved final plan revisions with red lined notes and attached plan clarification list. JCM
Routing - PLAN CHECK2/6/2009 2/24/2009 PASS
DetailsJohn Menard
Plan resubmittals requested  2/23/2009 DONE
DetailsJohn Menard
E-mailed the architect a letter requesting additional revisions. JCM
Plan resubmittals received  2/23/2009  
DetailsJohn Menard
Received 1 cover transmittal, 1 copy of structural responses to plan review comments, 3 copies of supplemental structural cals, 3 copies of sheets S3.1, S3.2, S6.0, S6.2 and inserted into plans///2-23-09 BAS
Plan resubmittals received  2/18/2009  
DetailsJohn Menard
Received transmittal, response letter, two copies of information on Door Hardware and plan sheet pages a0.02, a2.11, a2.12, a2.33, a2.45, a3.21; inserted by arch. rep. and taken back to John Menard
Plan resubmittals requested  2/10/2009 DONE
DetailsJohn Menard
Emailed the architect a copy of the second structural review requesting revisions. JCM
Routing Off Site - STRUCTURAL2/5/2009 2/10/2009 FAIL
DetailsJohn Menard
Sending Resubs ALR - Received comment list from consulting structural engineer requesting additional revisions. JCM
Routing - FIRE2/4/20092/4/20092/6/2009 PASS
DetailsScott Arellano
Attached IFC comments to plans
1st review completed  2/6/2009 FAIL
Failed Public Works, Structural, Plan Check
Route to Impact Fee Review2/4/20092/9/20092/5/2009 PASS
DetailsCindy M. Gould
Plan Reviewer's activity  2/4/2009 DONE
DetailsJohn Menard
E-mailed the architect a copy of the plan review requesting revisions. JCM
Plan resubmittals received  2/4/2009  
DetailsJohn Menard
Rec'd one transmittal letter and response letter; three copies of structural calcs and pages s2.3, s3.1, s3.2, s6.0, s6.2- taken to John M
Routing - PLAN CHECK1/23/2009 2/4/2009 FAIL
DetailsJohn Menard
John Menard
Routing - PLANNING1/23/2009 1/23/2009 PASS
DetailsAndrea Tuning
DRH08-00393-Andrea Tuning
Plan resubmittals received  1/22/2009  
DetailsBarbara Stitt
Recieved 1 cover transmittal, 5 copies of sheets C0.01, C1.00, C2.00, C3.00, C4.00, C4.01-taken and attached to plans that are currently in plumbing///1-22-09 BAS
Plan resubmittals requested  1/22/2009 DONE
DetailsJohn Menard
E-mailed the architect a copy of the structural comment list requesting revisions. JCM
Routing Off Site - STRUCTURAL1/5/2009 1/20/2009 FAIL
DetailsJohn Menard
Called Action Courier for pick up///1-5-09 @ 11:15am BAS - Received comment list from consulting structural engineer requesting revisions. JCM
Routing - Erosion and Sediment1/16/2009 1/16/2009 PASS
DetailsSteven Webb
ESC plan approved with attached conditions. ESC08-01050
Routing - PUBLIC WORKS1/6/2008 1/16/2009 FAIL
DetailsLouise Waldorf
Refer to street lighting; site drainage; solid waste; sewer design
Routing PW Environmental1/15/2009 1/16/2009 PASS
DetailsTerry Alber
Routing PW Sewer Rating1/9/2009 1/15/2009 PASS
DetailsLouise Waldorf
Routing PW Drainage1/15/2009 1/15/2009 FAIL
DetailsBrian Murphy
SHORT CIRCUITING IN BEDS, NEED 3 TO 1 SLOPES ON SWALES NEED3 COMPLTE COPIES OF DRAINAGE PLANS. BRIAN MURPHY ###-####
Routing PW Solid Waste1/15/2009 1/15/2009 FAIL
DetailsPeter J. McCullough
Solid waste enclosure does not meet requirements. Contact: Peter McCullough, ###-####
Routing - PLANNING Land Div1/5/2009 1/6/2009 PASS
DetailsTodd Tucker
Plans ACCEPTED BY PLAN TECH  1/5/2009 DONE
DetailsBarbara Stitt
Pending Assignment by JCM1/5/2009 1/5/2009 BLDA
DetailsJohn Menard
1/5/2009 10:35:11 JCM - activity updated through activity BLDA166 from case BLD08-02600.
Application received 12/31/200812/31/2008 DONE
DetailsBarbara Stitt
Routing - PLUMBING1/16/2009 1/23/2008 PASS
DetailsBill VanDegrift
per plans and 2003 upc
PubWorks Occupancy Approval12/28/200912/28/2009  PART
DetailsBrian Murphy
Temporary occ approved per Brian Murphy