Third Notice | | 8/31/2009 | 9/17/2009 | | DONE |
Barbara Stitt
|
|
|
|
Second Notice | | 7/22/2009 | 8/31/2009 | | DONE |
|
|
|
|
First Notice | | 4/16/2009 | 7/22/2009 | | DONE |
|
|
|
|
Permanent Occupancy UNPAID FEE | | | 4/16/2009 | | DONE |
Barbara Stitt
|
|
|
|
BLD-Final | 4/13/2009 | 4/14/2009 | 4/14/2009 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 4/13/2009 at 4:30:51 PM. Contact: ###-####. ok for perm occ
|
BLD-Final | 4/1/2009 | 4/2/2009 | 4/2/2009 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 3/31/2009 at 9:55:23 AM. Contact: ###-####. ok for temp occ ook for perm after the cover on the duct work in the star tower is completed
|
Temporary Occupancy UNPAID FEE | | | 4/2/2009 | | DONE |
Tisha Gallop
|
|
|
|
BLD-Final | 3/31/2009 | 4/1/2009 | 4/1/2009 | P | CANC |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 3/31/2009 at 9:55:23 AM. Contact: ###-####.
|
FIRE-Final Inspection | 4/1/2009 | 4/1/2009 | 4/1/2009 | P | PASS |
Forrest France
|
|
|
Fire life safety inspection completed acceptable.
|
FIRE-Final Inspection | 3/31/2009 | 4/1/2009 | 4/1/2009 | A | NR |
Forrest France
|
|
|
Project related fire sprinkler permit work is not ready for final, noted one overspaced head at the kitchen area due to relocated wall. Remainder of life safety items inspected okayed including fire alarm and type one hood.
|
FIRE-Final Inspection | 3/31/2009 | 3/31/2009 | 3/31/2009 | P | NR |
Forrest France
|
|
|
Project related fire alarm, hood suppression, and fire sprinkler permit work has not been scheduled for inspection or approved for final.
|
BLD-Framing/Rough-in | 3/24/2009 | 3/24/2009 | 3/25/2009 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 3/24/2009 at 10:16:15 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 3/25/2009 | 3/25/2009 | 3/25/2009 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 3/25/2009 at 9:18:37 AM. Contact: ###-####.ok to cover shaft
|
BLD-Framing/Rough-in | 3/16/2009 | 3/17/2009 | 3/18/2009 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 3/16/2009 at 3:40:01 PM. Contact: ###-####.ok to cover walls
|
Issue PAID IN FULL permit | | | 3/2/2009 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/23/2009 | | DONE |
|
|
|
|
Telephone call | | | 2/23/2009 | | DONE |
|
|
|
t/c w andy at ###-#### - permit ready and fees given
|
Override - Parcel Holds | | | 2/23/2009 | | |
|
|
|
|
Permit Ready to Issue | | | 2/23/2009 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/20/2009 | | PASS |
|
|
|
|
Plan assigned to (DRS) | 1/23/2009 | | 2/20/2009 | | PASS |
Dan Stuart
|
|
|
2/20/2009 08:39:01 DRS - activity updated through activity BLDA022 from case BLD09-00074.
|
Routing - FIRE | 2/12/2009 | | 2/18/2009 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
Plan resubmittals received | | | 2/13/2009 | | |
Tisha Gallop
|
|
|
received transmittal, 1pg. duct wrap info, and two copies of page a2.10; put in with plans and returned to fire review box
|
Routing - PLAN CHECK | 2/5/2009 | | 2/12/2009 | | FAIL |
Dan Stuart
|
|
|
Resubmittals of 2/11/09 are incomplete. E-mail to architect to provide requires submittals.
|
Plan resubmittals requested | | | 2/12/2009 | | DONE |
|
|
|
E-mail to architect.
|
Plan resubmittals received | | | 2/11/2009 | | |
|
|
|
received 1 transmittal and 2 copies of sheets A2.10,M1.00 taken to Dan S.
|
Routing - FIRE | 2/2/2009 | 2/2/2009 | 2/5/2009 | | FAIL |
Scott Arellano
|
|
|
Faxed and emailed resubmittal items to architect.
|
1st review completed | | | 2/5/2009 | | FAIL |
|
|
|
Failed Plan Check, Fire
|
Route to Impact Fee Review | 2/2/2009 | 2/5/2009 | 2/4/2009 | | PASS |
Cindy M. Gould
|
|
|
Tenant improvement in existing building
|
Plan resubmittals requested | | | 2/2/2009 | | DONE |
|
|
|
Plan review e-mailed to architect for resubmittals.
|
Routing - PLAN CHECK | 1/26/2009 | | 2/2/2009 | | FAIL |
Dan Stuart
|
|
|
Resubmittals required. Plan review e-mailed to architect. Routing plans to fire code analyst.
|
Routing - PLUMBING | 1/23/2009 | | 1/26/2009 | | PASS |
Bill VanDegrift
|
|
|
per plans and 2003 upc. SEE A2.2 FOR ADDED HAND SINK.
|
Routing - PUBLIC WORKS | 1/23/2009 | | 1/23/2009 | | PASS |
Beverly Hall
|
|
|
|
Pending Assignment by JCB | 1/22/2009 | | 1/23/2009 | | DONE |
Jason Blais
|
|
|
|
Routing PW Sewer Rating | 1/23/2009 | | 1/23/2009 | | PASS |
Louise Waldorf
|
|
|
|
Routing PW Environmental | 1/23/2009 | | 1/23/2009 | | PASS |
Terry Alber
|
|
|
No grease abatement shown: Ok at this time. Should grease be found in sewer, adequate abatement will be required. Contact Terry Alber ###-####
|
Application received | | 1/22/2009 | 1/22/2009 | | |
Alexandra L. DeYoung
|
|
|
|
Intake Approval | | | 1/22/2009 | | PASS |
|
|
|
Conducted the plan intake meeting. Application approved for submission.
|
Routing - PLAN CHECK | 2/18/2009 | | 2/20/2008 | | PASS |
Dan Stuart
|
|
|
Resubmittal sheet of 2/13/09 inserted into plans. Modified attached plan review. Plans to permit desk for issue.
|