First Notice | 5/28/2009 | 5/28/2009 | 8/24/2009 | | DONE |
Mike Jordan
|
|
|
|
BLD-Final | 5/27/2009 | 5/28/2009 | 5/28/2009 | A | PASS |
Mike Jordan
|
|
|
Scott Phone #: ###-####
|
DOC - Permit Finaled | 5/28/2009 | 5/28/2009 | 5/28/2009 | P | PASS |
Mike Jordan
|
|
|
Letter of compliance issued.
|
BLD-Final | 5/8/2009 | 5/8/2009 | 5/8/2009 | P | NR |
Mike Jordan
|
|
|
scott Phone #: ###-####. Still needs plumbing final.
|
FIRE-Final Inspection | 5/5/2009 | 5/6/2009 | 5/6/2009 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.
|
BLD-Final | 4/27/2009 | 4/28/2009 | 4/28/2009 | A | NR |
Mike Jordan
|
|
|
steve Phone #: ###-####. Needs life/safety first. called and left message with Steve at provided phone number.
|
BLD-Framing/Rough-in | 2/23/2009 | 2/23/2009 | 2/23/2009 | P | PASS |
Dave Hannah
|
|
|
steve Phone #: ###-####
|
Issue PAID IN FULL permit | | | 2/13/2009 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (CDM) | 1/30/2009 | 1/30/2009 | 2/11/2009 | | PASS |
Carl D Madsen
|
|
|
2/11/2009 11:51:28 CDM - activity updated through activity BLDA022 from case BLD09-00103.
|
Routing - PLAN CHECK | 2/10/2009 | | 2/11/2009 | | PASS |
Carl D Madsen
|
|
|
|
Routing - FIRE | | | 2/11/2009 | | PASS |
|
|
|
Verify in field 2-11-09 CDM
|
1st review completed | | | 2/11/2009 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/11/2009 | | |
|
|
|
|
Case Summary (BLD) | | | 2/11/2009 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 2/11/2009 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/11/2009 | | DONE |
|
|
|
|
Telephone call | | | 2/11/2009 | | DONE |
|
|
|
Called left message permit ready and fee given.
|
Routing - PUBLIC WORKS | 1/30/2009 | | 2/2/2009 | | PASS |
Beverly Hall
|
|
|
|
Routing PW Sewer Rating | 2/2/2009 | | 2/2/2009 | | PASS |
Louise Waldorf
|
|
|
|
Routing PW Environmental | 2/2/2009 | | 2/2/2009 | | PASS |
Walt Baumgartner
|
|
|
coffee bar addition, ok
|
Plans ACCEPTED BY PLAN TECH | | | 1/30/2009 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/30/2009 | | DONE |
Tisha Gallop
|
|
|
pln chk fee in safe, will be paid upon submittal of several other McDonald's store projects of the same scope; ok per Rita to begin plan review
|
Application received | | 1/30/2009 | | | |
|
|
|
|