Information based on query as of Tuesday, July 16, 2024.
Permit Information
Permit NumberBLD09-00109
StatusFinaled
Name STOCK CONSTRUCTION MANAGEMENT
Site Address 3536 W HILL RD
Project NameHillside Jr. High Locker Room
Customer Number 
ePlanReviewNo
Description
(Hillside Junior High - Locker Room Addition & NFPA 13 Fire Suppression / Alarm System) To build a 4,058 sq. ft. locker room addition on the northeast end of the existing 70,641 sq. ft. school building; construction of an 8", 2-hour, masonry fire barrier wall separating the new Type V-B construction from the existing Type VB construction. The new construction will be constructed of non-combustible materials per approved Alternate Request Letter on file, approved by Building Official & Fire Marshall. The entire school (new and existing) will be fully fire sprinklered per NFPA 13 as regulated by the fire department as part of this permit. A Grading & Drainage with site utilities permit is being issued under BLD09-00108. Work includes construction of a reinforced concrete foundation, stem wall, piers, footings and concrete slab; assembly of a pre-manufacture steel building frame with metal skin siding and roofing, construction of reinforced masonry fire barrier wall with protected 90 minute door opening and fire/smoke dampers at duct penetrations at the south end wall and north end steel frame wall, insulation and finishes; fully accessible shower / locker / restrooms for boys and girls; installation of suspended ceiling grid system, electrical, mechanical, plumbing, fire suppression and alarm systems, all per reviewed plans. This lot is within the floodplain area. An elevation certificate has been submitted and accepted by Jim Wylie, Public Works Dept. drs CUP08-00132
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 11/24/200911/16/2009 DONE
Third Notice 10/25/200911/10/2009 DONE
faxed and mailed
Second Notice 10/9/200910/15/2009 DONE
First Notice 9/26/20099/29/2009 DONE
Permanent Occupancy  9/16/2009 DONE
DetailsTisha Gallop
BLD-Final9/14/20099/15/20099/15/2009APASS
DetailsTony Young
Harry Phone #: ###-####
card was signed by inspector, but open alarm permit in computer
Zoning Approval9/15/20099/15/20099/15/2009 PASS
DetailsDavid Moser
CUP08-00132
Temporary Occupancy UNPAID FEE  9/15/2009 DONE
DetailsTisha Gallop
FIRE-Final Inspection9/14/20099/14/20099/14/2009PPASS
DetailsTroy Cobbley
life safety passed. the emergency lights have been repaired.
FIRE-Final Inspection9/11/20099/11/20099/11/2009PFAIL
DetailsTroy Cobbley
Both of the exit discharge lights need repaired and the emergency light in the north exit corridor from the new locker room needs repaired. I notified the general contractor that when the forward flush on the sprinkler system was performed all of the dirt and debri would be washed down to Hill Road and cause problems with Erosion Control.
BLD-Final9/11/20099/11/20099/11/2009PNR
DetailsTony Young
Harry Phone #: ###-####
need trades
BLD-Other8/24/20098/25/20098/25/2009APASS
DetailsMike Jordan
Harry Phone #: ###-####. Ceiling grid ok.
BLD-Framing/Rough-in7/24/20097/27/20097/27/2009APART
DetailsTony Young
harry Phone #: ###-####
2 hr ok
BLD-Framing/Rough-in7/23/20097/24/20097/24/2009APART
DetailsJim Storey
perry Phone #: ###-#### ok to cover all but hard lid so to insp. of 2 hr fire stopping above ceilling.
Elevation Cert Rec'd-Final  6/11/2009 PASS
BLD-Other5/11/20095/12/20095/12/2009ADONE
DetailsMike Jordan
Herry Phone #: ###-####. Will have special insp. Noted some changes in rebar, check rfi. Will recall footing insp when ready. Also noted bottom of footing has been approved by special insp. agency.
Issue PAID IN FULL permit  5/8/2009 DONE
PLANS/APPL TAKEN TO FRONT DESK  5/6/2009 PASS
Print Occupancy Form  5/6/2009 DONE
Details
Telephone call  5/6/2009 DONE
Details
t/c w scott henson at ###-#### - permit ready and fees given - also need gc name and rce#
Permit Ready to Issue  5/6/2009 DONE
Details
Routing - PLAN CHECK4/27/2009 5/6/2009 PASS
DetailsDan Stuart
Plans approved by all reviewing agencies W/ conditions of reviewing agencies attached to and considered part of the reviewed plans. Inserted new S-1 Sheet and calc sheet and modified plan review conditions.To permit desk to issue.
Routing Off Site - STRUCTURAL5/5/2009 5/6/2009 PASS
DetailsDan Stuart
Letter from Structural Engineer, Keith Jones, approving structural. New Sheet S-1 and calculations provided to indicate correct rebar lap for masonry wall.
Plan assigned to (DRS)2/2/2009 5/6/2009 PASS
DetailsDan Stuart
5/6/2009 07:40:28 DRS - activity updated through activity BLDA022 from case BLD09-00109.
Telephone call  5/5/2009 DONE
Talked with Steve Call, Design Engineer for metal building foundation and CMU wall. Center column bolting to be (4) 3/4" x 12" in length. Redlined on plans.
Plan resubmittals received  5/5/2009  
Received 1 transmittal,3 re-bar 8 1/2 x11 and 3 copies of sheet S1.0 taken to Dan S.
Routing Off Site - STRUCTURAL4/27/2009 4/30/2009 FAIL
DetailsDan Stuart
Resubmittals required for slender masonry wall design for lap splices and details on Sheet S1.0. Sent by e-mail to architect.
Plan resubmittals requested  4/30/2009 DONE
Copy of items needing corrected and resubmitted e-mailed to architect.
Plan resubmittals received  4/24/2009  
DetailsTisha Gallop
Received transmittal, three copies of plans for pre-engineered steel building, three copies of calcs for pre-engineered steel building, three copies of supplemental structural calcs and plan sheets S2.0, S2.1, S3.1; inserted by arch. rep. and taken back to Dan Stuart
Routing - PLAN CHECK3/6/2009 3/9/2009 FAIL
DetailsDan Stuart
New plan sheet A1.1 inserted into plans. Revised corrected Alternate Request Letter provided for review for approval by building offical and fire marshall. Copy of letter to building official.
Structural plans, engineering calcs and verification that current design data for foundation is compliant with structural building plans when received. Copy e-mailed to architect.
Route to Impact Fee Review3/6/20093/11/20093/6/2009 PASS
DetailsCindy M. Gould
Plan resubmittals received  3/6/2009  
DetailsDan Stuart
Received four copies of sheet A1.1; taken to Dan Stuart
Plan Reviewer's activity  3/5/2009 DONE
Began review of plan resubmittals of 2/23/09. Note on Plan Sheet A1.1 concerning the Alternate Request Letter and the type of construction for the new building were incorrect. E-mailed architect indicating information to be added to Sheet A1.1 concerning alternate request and the approval there of by the Building Official & Fire Marshall. Requested four corrected copies of this sheet.
Plan resubmittals requested  3/5/2009 DONE
Requested corrected Sheet A1.1, four copies, with corrected note & details for the Alternate Request Letter and correct construction type for the new addition to Scott Henson.
Plan Reviewer's activity  3/5/2009 DONE
Notified by architect that the modified Alternate Request Letter of 2/23/09 was not the alternate signed by the B.O & F. M. I reviwed the signed document and he was correct. I reviewed the alternate request letter of 2/23/09 and found that the code analysis for the original building and then the code analysis with the new addition to the existing with the new sprinkler system were not corrected per my e-mail to architect of 2/22/09. I added suggested corrections to the code analysis data to sheet 1 & 2 of alternate request letter and code equations used and e-mailed to architect to correct on letter and then resubmit pages 1 & 2 and I will take to building official and fire marshall for there signature so that all data in the letter is correct and in agreement with proposals for acceptance by Boise City.
Plan Reviewer's activity  3/5/2009 DONE
Notified by e-mail that the project had gone out to bid and once awarded the winning contractor would work on providing building four sets of plans and three sets of design / engineering calcs all stamped by and Idaho licensed structural engineer for review. Once received, the plans will be imediately routed to Boise City PDS contract structural review engineering company for review and comment. It was estimated by architect that this could be in two to three weeks. I will continue the review process on plan resubmittals of 2/23/09.
Routing - PLAN CHECK2/19/2009 3/5/2009 FAIL
DetailsDan Stuart
Incorrect data on plans for code analysis and incorrect data in Alternate request letter. Corrections suggested for code analysis to plans and to the Alternate letter were e-mailed to the architect.
Resubmittals required.
Plan resubmittals received  3/5/2009 DONE
received 1 transmittal and 1 plan acceptance from ACHD. taken to Dan S.
Plan Reviewer's activity  2/26/2009 DONE
Received copy of approval of alternate for Hillside Jr. High with signatures of George Slane, B.O. and Mark Senteno, Fire Marshall and sent PDF copy to Scott Henson, LCA, for his records.
Plan resubmittals received  2/25/2009  
DetailsDan Stuart
Received transmittal, response letter, Project Start Up for Special Inspection application, three copies of Structural Calculations, and four copies of plan sheets A1.1, A2.0, A5.0, A6.0, U1, M0.0, M3.0, M4.0; inserted by arch. rep. and taken back to Dan Stuart
Routing - PUBLIC WORKS2/18/2009 2/19/2009 PASS
DetailsBeverly Hall
Routing PW Flood Plain2/19/2009 2/19/2009 PASS
DetailsJim Wyllie
Received Elevation Certificate showing compliance with Boise City Floodplain Ordinance Requirements. Jim Wyllie / ###-####
Routing - Erosion and Sediment2/19/2009 2/19/2009 PASS
DetailsSteven Webb
ESC plan approved under BLD09-00108
Routing - FIRE2/12/20093/6/20092/18/2009 PASS
DetailsScott Arellano
Attached IFC comments to plans
1st review completed  2/18/2009 FAIL
Failed Public Works, Erosion & Soil Control, and Plan Check
Routing - PLAN CHECK2/18/2009 2/18/2009 FAIL
DetailsDan Stuart
Routing plans back to public works for flood plain recheck.
Plan resubmittals requested  2/12/2009 DONE
Plan review report with required resubmittals e-mailed to architect.
Routing - PLAN CHECK2/5/2009 2/12/2009 FAIL
DetailsDan Stuart
Resubmittals required. Original structural submittals and engineering for metal building were not provided. Copy of plan review e-mailed to architect. Routing to fire code analyst for review.
Routing - PLANNING2/4/2009 2/9/2009 PASS
DetailsDavid Moser
cup08-00132 David Moser
Routing - PLUMBING2/4/2009 2/4/2009 PASS
DetailsBill VanDegrift
locker rooms and grading plans ok
Routing PW Drainage2/3/2009 2/4/2009 PASS
DetailsBrian Murphy
LESS THAN 10 %.
Routing - Erosion and Sediment2/4/2009 2/4/2009 FAIL
DetailsSteven Webb
This ESC permit is to cover Bld09-00108 (grading/drainage) and Bld09-00109 (building addition) for Hillside Jr High School. ok per Jason B.
Routing - PUBLIC WORKS2/3/2009 2/4/2009 FAIL
DetailsLouise Waldorf
Refer to flood plain review by JEW
Routing PW Sewer Rating  2/4/2009 PASS
DetailsLouise Waldorf
Routing PW Flood Plain2/4/2009 2/4/2009 FAIL
DetailsJim Wyllie
Elevation Certificate not provided with building plans. Elevation Certificate showing compliance with Boise City Floodplain Ordinance needs to be provided prior to building permit approval. Jim Wyllie / ###-####
Routing - PLANNING Land Div2/2/2009 2/3/2009 PASS
DetailsTodd Tucker
Property is larger than five acres in size.
Routing - Addressing2/3/2009 2/3/2009 PASS
DetailsApril Wing
Pending Assignment by JCM2/2/2009 2/2/2009 BLDA
DetailsJohn Menard
2/2/2009 11:35:01 JCM - activity updated through activity BLDA168 from case BLD09-00109.
Routing Off Site - STRUCTURAL2/2/2009 2/2/2009 FAIL
DetailsDan Stuart
No structural plans and calculations submitted for the pre-engineered metal building. Plans will be routed for outside review after receiving required structural plans and calcs. JCM
Plans ACCEPTED BY PLAN TECH  2/2/2009 DONE
DetailsTisha Gallop
Recd Pcfee & Taken To Pln CK  2/2/2009 DONE
DetailsTisha Gallop
Plan routing begun/NEW & ADDTN  2/2/2009 DONE
DetailsTisha Gallop
Application received 1/30/2009   
Routing - PUBLIC WORKS GRADING    PASS
DetailsTerry Records
Not hillside