Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD09-00145
StatusFinaled
Name BRICON INC
Site Address 3330 W GRACE ST
Project NameLHTAC
Customer Number 
ePlanReviewNo
Description
Local Highway Technical Assistance Council - To construct a new 5,800 square foot, two story, wood framed office building and related site improvements. This building will be fully fire sprinkled. 1st Floor: 3,110 sq. ft. 2nd Floor: 2,690 sq. ft.. There is an existing office building on this site that will be demolished and removed from the location of the new parking lot. This building will be demolished and removed after completion of the new office building. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 8/27/20108/13/2010 DONE
Third Notice 8/7/20108/13/2010 DONE
faxed
Second Notice 7/25/20108/2/2010 DONE
First Notice 7/10/20107/15/2010 DONE
BLD-Final6/29/20106/30/20106/30/2010PPASS
DetailsTony Young
herb Phone #: ###-####,, perm occ ok,, pending zoning
PubWorks Occupancy Approval6/30/20106/30/20106/30/2010 DONE
DetailsTiffany Lowery
Zoning Approval6/30/20106/30/20106/30/2010 PASS
DetailsJosh Wilson
Parking lot and landscaping installed per plans
Permanent Occupancy UNPAID FEE  6/30/2010 DONE
DetailsTisha Gallop
BLD-Final5/6/20105/7/20105/7/2010APART
DetailsTony Young
herb Phone #: ###-####,, temp occ. ok,, need full signoffs from others,, need bottom rise off exterior stairs to be in compliance
FIRE-Final Inspection5/7/20105/7/20105/7/2010PPASS
DetailsForrest France
Reinspection for C/N items completed satisfactory. Fire life safety passed.
FIRE-Final Inspection5/6/20105/7/20105/7/2010AFAIL
DetailsForrest France
Need to repair one exit sign first floor west side, two EM lights second floor are not operational, exit discharge light at the main entry is not functional, missing fire stop at some penetrations in the rated ceiling at the riser room.
Temporary Occupancy UNPAID FEE  5/7/2010 DONE
DetailsTisha Gallop
Per Jason Blais ok to issue temp occupancy without ACHD signature.
Zoning Approval Temp5/6/20105/6/20105/6/2010 DONE
DetailsHal Simmons
Temporary occupancy okay. Landscaping must be installed within 60-days.
Case Summary (BLD)  5/5/2010 DONE
FIRE-Alarm Testing5/4/20105/4/20105/4/2010PDONE
DetailsForrest France
See project related FIR permit activities for fire alarm and sprinkler inspection notes, discussed signage at the riser and FACP room door, review notes, list of general life safety requirements, etc.
FIRE-Final Inspection5/3/20105/3/20105/3/2010AFAIL
DetailsForrest France
Refer to fire code review note item #19, discussed knox box installation and remainder of issues for final.
BLD-Final4/29/20104/29/20104/29/2010PNR
DetailsTony Young
Herb Phone #: ###-####,, correction posted,, need trades,, etc,, on site walk through
BLD-Wall cover3/30/20103/30/20103/30/2010PPASS
DetailsTony Young
herb Phone #: ###-####,, ceiling grid ok
BLD-Framing/Rough-in2/22/20102/23/20102/23/2010AFAIL
DetailsTony Young
Ceiling grid inspection please-Herb Phone #: ###-####,, need trades signed off for above ceiling,, on site walk through,, should be ok on ceiling after trades
BLD-Energy code compliance1/11/20101/11/20101/11/2010PPASS
DetailsTony Young
Herb Phone #: ###-####
BLD-Conference1/4/20101/5/20101/5/2010APART
DetailsTony Young
jerel,, 11am please,, frame conference
w/ framer and contractor,, ok to insulate now,, still has a c/notice
BLD-Framing/Rough-in12/28/200912/29/200912/29/2009AFAIL
DetailsTony Young
herb Phone #: ###-####
,, 2 page c/n posted
BLD-Framing/Rough-in12/28/200912/28/200912/28/2009PPART
DetailsTony Young
herb Phone #: ###-####
conf only,, need to get special inspection reports
BLD-Other8/14/20098/14/20098/14/2009PPASS
DetailsDave Hannah
foundation wall inspection// wants to pour at 2:30, has special inspection by MTI//Herb Brice Phone #: ###-#### ok to pour foundation
BLD-Footing8/12/20098/13/20098/13/2009APART
DetailsTony Young
Mark Phone #: ###-####
ok pending sp
BLD-Conference8/12/20098/12/20098/12/2009PPASS
DetailsTony Young
Mark Phone #: ###-####
ftgs, wip,, will need a special inspection
Issue PAID IN FULL permit  7/28/2009 DONE
Print Occupancy Form  4/15/2009 DONE
Details
Telephone call  4/15/2009 DONE
Details
left vm for patrick at ###-#### - permit ready and fees given - also need gc name, rce#, rp name and ACHD receipt
Permit Ready to Issue  4/15/2009 DONE
Details
Routing - PLAN CHECK4/10/2009 4/14/2009  
DetailsJohn Menard
Plan resubmittals received  4/14/2009  
DetailsTisha Gallop
Received five copies of sheets C1.0, C2.0, C3.0; inserted by arch. rep. and taken back to John Menard
Routing - PUBLIC WORKS4/14/2009 4/14/2009 PASS
DetailsBeverly Hall
Routing PW Drainage4/14/2009 4/14/2009 PASS
DetailsBrian Murphy
Routing - PLAN CHECK4/14/2009 4/14/2009 PASS
DetailsJohn Menard
PLANS/APPL TAKEN TO FRONT DESK  4/14/2009 DONE
DetailsJohn Menard
Plan assigned to (JCM)2/10/2009 4/14/2009 PASS
DetailsJohn Menard
4/14/2009 15:47:06 JCM - activity updated through activity BLDA022 from case BLD09-00145.
Routing - PUBLIC WORKS4/6/2009 4/10/2009 FAIL
DetailsLouise Waldorf
Refer to site drainage: Brian Murphy ###-####
Routing PW Drainage4/10/2009 4/10/2009 FAIL
DetailsBrian Murphy
need detail to match geotech report brian murphy ###-####
Plan resubmittals received  4/9/2009  
DetailsTisha Gallop
Received one copy stormwater management report and three copies of sheet C3.0; inserted by arch. rep. and taken back to Brian Murphy
Routing - PLAN CHECK3/26/2009 4/6/2009  
DetailsJohn Menard
Routing - PLANNING3/25/2009 3/26/2009 PASS
DetailsJosh Wilson
See redlines-- East setback must be 15.00 feet-- plans show 14.83 feet
Routing - PUBLIC WORKS3/19/2009 3/25/2009 FAIL
DetailsLouise Waldorf
Refer to site drainage: Contact Brian Murphy ###-####
Routing PW Drainage3/20/2009 3/25/2009 FAIL
DetailsBrian Murphy
NEED TO ACCOUNT FOR SMALL PARKING LOT DRAINAGE. BRIAN MURPHY ###-####
Routing PW Sewer Design3/25/2009 3/25/2009 PASS
DetailsJon R. Gunnerson
Connect onto existing sewer service provided.
Routing - FIRE3/17/2009 3/19/2009 PASS
DetailsScott Arellano
Attached updated IFC comments to plans
Plan Reviewer's activity  3/17/2009 PASS
DetailsJohn Menard
Reviewed and approved structural and nonstructural revised construction documents. JCM
Routing - PLAN CHECK3/3/2009 3/17/2009 PASS
DetailsJohn Menard
Plan resubmittals received  3/16/2009  
DetailsJohn Menard
Received 1 cover transmittal, 2 copies of C1.0, C2.0, C3.0, L1.0, A1.1, A1.2, A2.1, A2.2, A3.1, A3.2, A3.3, A5.6, A6.4, S1.0,S2.0, S3.0, S3.1, S4.0, S5.0, S5.1, S5.2, S5.3, S6.0, S6.1, S6.2, S7.0, S7.1 and inserted into plans by the architects office and returned to John Menard's desk///3-16-09 @ 4:15pm BAS
1st review completed  3/3/2009 FAIL
Failed Public Works, Structural, Plan Check, Fire
Routing - FIRE2/26/2009 3/3/2009 FAIL
DetailsScott Arellano
Faxed and emailed resubmittal items to architect.
Route to Impact Fee Review2/26/20093/3/20092/27/2009 PASS
DetailsCindy M. Gould
Plan resubmittals requested  2/26/2009 DONE
DetailsJohn Menard
Emailed the architect a copy of the plan review requesting revisions. JCM
Routing - PLAN CHECK2/24/2009 2/26/2009 FAIL
DetailsJohn Menard
Routing Off Site - STRUCTURAL2/10/2009 2/25/2009 FAIL
DetailsJohn Menard
Received comment list from consulting structural engineer requesting revisions. JCM
Plan resubmittals requested  2/25/2009 DONE
DetailsJohn Menard
Emailed the architect a copy of the structural review requesting revisions. JCM
Routing - PLANNING2/23/2009 2/24/2009 PASS
DetailsJosh Wilson
DRH08-00392 Josh Wilson OK
Routing - PLUMBING2/20/2009 2/23/2009 PASS
DetailsBill VanDegrift
per plans and 2003 upc
Routing - PUBLIC WORKS2/10/2009 2/20/2009 FAIL
DetailsLouise Waldorf
Refer to sewer design & site drainage
Routing - Erosion and Sediment2/20/2009 2/20/2009 PASS
DetailsSteven Webb
ESC plan approved with attached conditions. ESC09-00046
Routing PW Sewer Design2/10/2009 2/20/2009 FAIL
DetailsJon R. Gunnerson
Sanitary sewer service already provided.
Routing PW Drainage2/19/2009 2/20/2009 FAIL
DetailsBrian Murphy
OFFSITE RUNOFF? NO MONITORING WELL 5 FOOT SEPERATION SHORT CIRCUITING
Routing PW Solid Waste  2/18/2009 PASS
DetailsPeter J. McCullough
Approved for 95-gallon carts only
Routing PW Street Lights2/17/2009 2/17/2009 PASS
DetailsHank Alarcon
Routing PW Sewer Rating2/10/2009 2/10/2009 PASS
DetailsLouise Waldorf
Plans ACCEPTED BY PLAN TECH  2/10/2009 DONE
DetailsAlexandra L. DeYoung
Recd Pcfee & Taken To Pln CK  2/10/2009 DONE
DetailsAlexandra L. DeYoung
Plan routing begun/NEW & ADDTN  2/10/2009 DONE
DetailsAlexandra L. DeYoung
Routing - PLANNING Land Div2/10/2009 2/10/2009 PASS
DetailsDave Abo
Multiple platted lots and vacated alley under one tax parcel number.
Pending Assignment by JCM2/10/2009 2/10/2009 BLDA
DetailsJohn Menard
2/10/2009 10:19:01 JCM - activity updated through activity BLDA166 from case BLD09-00145.
Application received 2/9/20092/9/2009 DONE
DetailsAlexandra L. DeYoung