Permit Information
Permit NumberBLD09-00168
StatusFinaled
Name EPSTEIN CONSTRUCTION INC
Site Address 2390 E FREIGHT ST
Project NameWinco Distribution Center
Customer Number 
ePlanReviewNo
Description
Dispatch and Maintenance Building - To construct a new 12,395 square foot, one story with 960 square foot storage mezzanine, pre-engineered metal office and maintenance building and related site improvements. This building contains an 8,265 square foot vehicle repair bay and storage areas and a 4,130 square foot dispatch office area. All construction per the approved plans and attached comment list. DRH07-00594 JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 3/29/20104/15/2010 DONE
Third Notice 3/9/20103/15/2010 DONE
e-mailed and faxed Stu White
Third Notice 2/23/20102/23/2010 DONE
e-mailed Stu White and faxed
Second Notice 2/5/20102/18/2010 DONE
First Notice 1/23/20101/26/2010 DONE
FIRE-Final Inspection1/13/20101/13/20101/13/2010PPASS
DetailsForrest France
Fire life safety passed, see activity notes completed 1/6/10.
Permanent Occupancy UNPAID FEE  1/13/2010 DONE
BLD-Final1/11/20101/11/20101/11/2010PPASS
DetailsJim Storey
c/n made ok
BLD-Final1/5/20101/6/20101/6/2010APASS
DetailsForrest France
Fire life safety is satisfactory pending door hardware at three locations is repaired- to be completed prior to structural final as discussed.
BLD-Final1/5/20101/5/20101/6/2010PFAIL
DetailsJim Storey
final set per angie b. door hardware stil pending replacment per c/n
PubWorks Occupancy Approval1/6/20101/6/20101/6/2010 DONE
DetailsAngela Brosious
Ok for final occupancy per Jim Wylie.
Zoning Approval1/5/20101/5/20101/5/2010 DONE
DetailsSarah Schafer
BLD-Aging Inspection12/15/200912/15/200912/15/2009 PART
DetailsJim Storey
temp occ ok/ need to verify auto fluss bolts are instaled at double doors first floor south east side of building from shop area.Also pending Public Works sign off.
BLD-Conference12/15/200912/15/200912/15/2009PPART
DetailsJim Storey
temp occ ok/ need to verify auto fluss bolts are instaled at double doors first floor south east side of building from shop area. Also pending public works sign off.
FIRE-Final Inspection9/15/20099/16/20099/17/2009APART
DetailsForrest France
TOC approved.
FIRE-Alarm Testing9/15/20099/16/20099/17/2009APART
DetailsForrest France
TOC approved.
Temporary Occupancy UNPAID FEE  9/17/2009 DONE
BLD-Final9/16/20099/16/20099/16/2009PPART
DetailsJim Storey
temp occ ok/ need to verify auto fluss bolts are instaled at double doors first floor south east side of building from shop area.
FIRE-Final Inspection9/9/20099/10/20099/10/2009APART
DetailsForrest France
George Phone #: ###-####
BLD-Final9/9/20099/10/20099/10/2009AFAIL
DetailsJim Storey
George Phone #: ###-#### stair riser over 7 inches at top.
BLD-Final9/8/20099/9/20099/9/2009PFAIL
DetailsJim Storey
George Phone #: ###-####
FIRE-Final Inspection9/8/20099/9/20099/9/2009ANR
DetailsForrest France
Project related fire alarm permit work must pass inspection for final status prior to building fire life safety approval.
BLD-Framing/Rough-in8/25/20098/26/20098/26/2009APART
DetailsJim Storey
Steve-Ceiling grid for cover inspection please Phone #: ###-#### ok to cover upon mech and ele aprovals.
BLD-Framing/Rough-in8/6/20098/7/20098/7/2009APASS
DetailsJim Storey
JC Phone #: ###-####
BLD-Aging Inspection7/13/20097/13/20097/13/2009 PART
DetailsJim Storey
si almost complet/ walked structure wip
BLD-Other5/12/20095/12/20095/12/2009PPASS
DetailsBill VanDegrift
Permit Issued-STOP WORK REMOVED- per Bill VanDeGrift.
ajb
Issue PAID IN FULL permit  5/8/2009 DONE
DetailsTisha Gallop
Print Occupancy Form  5/7/2009 DONE
Details
Telephone call  5/7/2009 DONE
Called and E-mailed Stu White and let him know permit is ready to pick up.
Permit Ready to Issue  5/7/2009 DONE
Details
Plan assigned to (JCM)2/17/20092/17/20095/6/2009 PASS
DetailsJohn Menard
5/6/2009 16:20:44 JCM - activity updated through activity BLDA022 from case BLD09-00168.
Routing - PLAN CHECK5/1/2009 5/6/2009 PASS
DetailsJohn Menard
Plan resubmittals received  5/6/2009 DONE
received 1 transmittal,and 2 copies of sheet M-006 taken to John M.
PLANS/APPL TAKEN TO FRONT DESK  5/6/2009 DONE
DetailsJohn Menard
BLD-Foundation5/1/20095/1/20095/1/2009PFAIL
DetailsBill VanDegrift
plumbing has been installed and covered without a permit or inspection. expose all piping, secure a permit, apply a test to all underground piping and call for inspection. THIS IS A STOP WORK ORDER, NO ADDITIONAL WORK OF ANY KIND SHALL BE PERFORMED UNTILL BLD09-00168 HAS BEEN ISSUED.
Routing - PLAN CHECK4/22/2009 5/1/2009  
Routing - PLAN CHECK5/1/2009 5/1/2009 FAIL
DetailsCarl Westfall
Did the resubmittal review for John Menard. Found that the Envelope Compliance Certificate for this project still did not match the drawings. Called Stuart White with Epstein and left a detailed message explaining the defficiency.
Plan resubmittals received  4/30/2009  
Received 1 transmittal,2 door hardware,1 response, and 2 copies of sheets DM-A101,DM-A102,DM-P-100,DM-P-500, DM-P-501
Routing - FIRE4/21/2009 4/22/2009 PASS
DetailsScott Arellano
Attached updated IFC comments to plans.
Routing - PUBLIC WORKS4/16/2009 4/21/2009 PASS
DetailsBeverly Hall
Routing PW Drainage4/16/2009 4/21/2009 PASS
DetailsJim Wyllie
Approval is for building only. Truck fuel island, fuel tanks, spill containment sump and appurtenant piping to be reviewed and approved under separate submittal. Jim Wyllie / ###-####
Routing - PLUMBING4/21/2009 4/21/2009 PASS
DetailsBill VanDegrift
Routing PW Environmental4/20/2009 4/20/2009 PASS
DetailsWalt Baumgartner
Rev'd by Terry Alber. OK.
Routing - Erosion and Sediment4/21/2009 4/20/2009 PASS
DetailsBill VanDegrift
per plans and 2003 upc
Plan Reviewer's activity  4/15/2009 PASS
DetailsJohn Menard
Reviewed and approved structural revisions. JCM
Plan resubmittals requested  4/15/2009 DONE
DetailsJohn Menard
E-mailed the architect requesting revisions. JCM
Routing - PLAN CHECK3/13/2009 4/15/2009 FAIL
DetailsJohn Menard
Plan resubmittals received  4/8/2009  
DetailsTisha Gallop
Received response letter, three copies of supplemental structural calculations, and two copies of sheets DM-T1, DM-T2, DM-A100, DM-A101, DM-A102, DM-S-100, DM-P-100, DM-P-500, DM-P-501, DM-P-700; inserted by LEG and taken back to John Menard
Route to Impact Fee Review3/11/20093/16/20093/13/2009 PASS
DetailsCindy M. Gould
Routing - FIRE3/11/20093/11/20093/13/2009 FAIL
DetailsScott Arellano
Faxed and emailed resubmittal items to architect.
1st review completed  3/13/2009 FAIL
Failed Public Works, Structural, Plumbing, Planning, Plan Check, Fire
Plan resubmittals requested  3/11/2009 DONE
DetailsJohn Menard
emailed the architect requesting revisions. JCM
Plan resubmittals requested  3/11/2009 DONE
DetailsJohn Menard
Emailed the architect a copy of plan review requesting revisions. JCM
Routing - PLAN CHECK2/27/2009 3/11/2009 FAIL
DetailsJohn Menard
John Menard
Plan resubmittals requested  3/9/2009 DONE
DetailsJohn Menard
Emailed the applicant a copy of the structural review requesting revisions. JCM
Routing Off Site - STRUCTURAL2/17/2009 3/6/2009 FAIL
DetailsJohn Menard
Received comment list from consulting structural engineer requesting revisions. JCM
Routing - PLANNING2/25/2009 2/27/2009 PASS
DetailsSarah Schafer
DRH07-00594 Sarah S.

Approved per DRH07-00594 and DRH08-00146.
Routing - PLUMBING2/24/2009 2/25/2009 FAIL
DetailsBill VanDegrift
UPC 910.4- vents required on combination waste and vent system branches. provide locations of additional fixtures upstream of the interceptor per detail on page DM-P-100. fuel island? complete public works review prior to plumbing approval.
Routing - Erosion and Sediment2/23/2009 2/24/2009 PASS
DetailsClint A Smith
Please Refer to ESC08-00491
Routing - PUBLIC WORKS2/18/2009 2/23/2009 FAIL
DetailsLouise Waldorf
Refer to Drainage & Environmental
Routing PW Drainage  2/20/2009 FAIL
DetailsBrian Murphy
Sheet DM-P-100 - This sheet shows interior floor drains that discharge to the storm drian. All interior floor drains must go to sanitary sewer. Sheet P--501 - This sheet contains details (such as Trench Drain, Settling and Reclame Pit, Wash Water Reclamation Tank) that are not a part of this building. Remove details or note "Not A Part". Jim Wyllie / ###-####)
Routing PW Solid Waste  2/20/2009 PASS
DetailsPeter J. McCullough
Routing PW Environmental  2/20/2009 FAIL
DetailsWalt Baumgartner
Plan sheet DM-P-100 indicates inside shop drains route to storm system. Must route to sanitary sewer or obtain ok from PW Drainage group for connection to storm system.
Routing PW Street Lights  2/19/2009 PASS
DetailsHank Alarcon
Routing PW Sewer Rating2/18/2009 2/18/2009 PASS
DetailsLouise Waldorf
Routing - PLANNING Land Div2/17/2009 2/18/2009 PASS
DetailsDave Abo
Parcel B on ROS08-00014.
Routing PW Sewer Design2/18/2009 2/18/2009 PASS
DetailsJon R. Gunnerson
Connect onto public sewer stub provided in Warehouse Way.
Plan routing begun/NEW & ADDTN  2/17/2009 DONE
DetailsTisha Gallop
Telephone call  2/17/2009 DONE
DetailsTisha Gallop
Called Action Couriers for pick up
Recd Pcfee & Taken To Pln CK  2/17/2009 DONE
DetailsTisha Gallop
Plans ACCEPTED BY PLAN TECH  2/13/2009 DONE
DetailsTisha Gallop
Application received 2/12/20092/12/2009 DONE
DetailsTisha Gallop