DOC-Permit Expired | 5/21/2010 | 5/21/2010 | 5/21/2010 | | DONE |
Dave Hannah
|
|
|
Permit expired by limitations.
|
BLD-Aging Inspection | 6/26/2009 | 6/26/2009 | 6/29/2009 | | PASS |
Dave Hannah
|
|
|
work in progress
|
CHANGE STATUS TO (ISS) | | | 6/25/2009 | | DONE |
|
|
|
|
(F) Reprint permit | | | 6/25/2009 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/19/2009 | | DONE |
Barbara Stitt
|
|
|
|
Telephone call | | | 6/19/2009 | | DONE |
|
|
|
Left voice message for Brian Garrett and told him that permit is ready & fees due///6-19/09 @ 10:25am BAS
|
Telephone call | | | 6/19/2009 | | DONE |
|
|
|
Called and told Ron Junke that permit is ready & fees due///6-19-09 @ 10:30am BAS
|
Permit Ready to Issue | | | 6/19/2009 | | DONE |
|
|
|
|
Routing - FRONT DESK | 6/16/2009 | | 6/19/2009 | | PASS |
Barbara Stitt
|
|
|
Barbara Stitt
|
Routing - FIRE | 6/10/2009 | | 6/16/2009 | | PASS |
Scott Arellano
|
|
|
Plans are approved with no seperate review comments.
|
1st review completed | | | 6/16/2009 | | FAIL |
|
|
|
Failed Public Works
|
Routing - PLANNING | 6/3/2009 | | 6/9/2009 | | PASS |
Matthew A Halitsky
|
|
|
Matt Hallitsky
Routed to Josh Johnson.
|
Routing - PLANNING | | | 6/9/2009 | | PASS |
Joshua Johnson
|
|
|
Josh Johnson
|
Routing - PUBLIC WORKS | 5/28/2009 | | 6/3/2009 | | PASS |
Beverly Hall
|
|
|
|
Plan resubmittals received | | | 6/3/2009 | | |
Brian Murphy
|
|
|
Received 2 copies of sheets C0.01, C1.00, C2.00, C3.00, C3.01, C4.00, C4.01 and taken to Brian Murphy///6-3-09 @ 8:05am BAS
|
Routing PW Street Lights | | | 6/3/2009 | | PASS |
Hank Alarcon
|
|
|
|
Routing PW Solid Waste | | | 6/3/2009 | | PASS |
Peter J. McCullough
|
|
|
|
Routing PW Sewer Design | 6/1/2009 | | 6/2/2009 | | PASS |
Jon R. Gunnerson
|
|
|
Connect 6-inch service into main line and NOT into manhole. Stub to be provided by the City.
|
Routing PW Drainage | 5/29/2009 | | 6/1/2009 | | PASS |
Brian Murphy
|
|
|
REVISIONS TO DRAINAGE. BRIAN MURPHY ###-####
|
Routing PW Sewer Rating | 6/1/2009 | | 6/1/2009 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 5/28/2009 | | 5/28/2009 | | PASS |
April Wing
|
|
|
|
Plan Modification Accepted | | | 5/26/2009 | | DONE |
Barbara Stitt
|
|
|
Plan modification accepted for revised parking at the north side of parking lot-flip angled spaces from north side of drive aisle to south side, add parrallel spots to north side. Received 1 cover transmittal, 1 copy of drainage report dated 5-12-09, 3 copies of sheets C0.01, C1.00, C2.00, C3.00, C3.01, C4.00, C4.01
|
Routing - PARKS DEPARTME | 3/20/2009 | | 3/20/2009 | | PASS |
Barbara Stitt
|
|
|
Certificate of Occupancy until approved proof of conyenace of a permanet path easment & maintenace agreement in favor of either Ada County/ Boise City. Please make sure that Building permit plans (BLD08-02600) are incorporated with these notations also. For any questions please contact David at ###-#### ext 310
|
Issue PAID IN FULL permit | | | 3/9/2009 | | DONE |
Barbara Stitt
|
|
|
|
(F) Reprint permit | | | 3/9/2009 | | DONE |
|
|
|
|
Telephone call | | | 3/6/2009 | | DONE |
Barbara Stitt
|
|
|
Left voice message for Ben Miller and Ron Junke that permit is ready & fees due///3-6-09 @ 10:53am BAS
|
Permit Ready to Issue | | | 3/6/2009 | | DONE |
Barbara Stitt
|
|
|
|
Routing - PLANNING | 3/6/2009 | | 3/6/2009 | | PASS |
Joshua Johnson
|
|
|
This plan ok to be approved however prior to building permit a site plan indicating how a round about can be accomodated must be submitted.
|
Routing - PLANNING | 3/4/2009 | | 3/6/2009 | | PASS |
Matthew A Halitsky
|
|
|
DRH08-00234
Routed to Josh J.
Grading only.
|
Routing - PLAN CHECK | 3/6/2009 | | 3/6/2009 | | PASS |
Barbara Stitt
|
|
|
Barbara Stitt
|
Routing - FIRE | 3/4/2009 | 3/4/2009 | 3/4/2009 | | PASS |
Scott Arellano
|
|
|
Approved under sheel permit of BLD08-02600 on 2-6-09 BAS
|
Route to Impact Fee Review | 3/4/2009 | 3/4/2009 | 3/4/2009 | | PASS |
Cindy M. Gould
|
|
|
Originally approved under shell building permit BLD08-02600 on 2-5-09
|
Routing PW Sewer Design | 2/26/2009 | | 3/4/2009 | | PASS |
Jon R. Gunnerson
|
|
|
Contact Boise City Public Works Department prior to ANY sewer construction.
|
Routing - PLUMBING | 3/3/2009 | | 3/4/2009 | | PASS |
Bill VanDegrift
|
|
|
Passed under BLD08-02600 on 1-23-09
|
Routing PW Sewer Design | 3/4/2009 | | 3/4/2009 | | PASS |
Jon R. Gunnerson
|
|
|
Contact Public Works prior to any sewer construction
|
Routing - PUBLIC WORKS | 3/4/2009 | | 3/4/2009 | | PASS |
Beverly Hall
|
|
|
|
Routing PW Street Lights | 2/26/2009 | | 3/3/2009 | | PASS |
Hank Alarcon
|
|
|
|
Routing - Erosion and Sediment | 3/3/2009 | | 3/3/2009 | | PASS |
Clint A Smith
|
|
|
ESC08-01050 plan approved with attached conditions. FOR GRADING AND DRAINAGE ONLY.
|
Routing - PUBLIC WORKS | 2/26/2009 | | 3/3/2009 | | FAIL |
Louise Waldorf
|
|
|
Refer to sewer design
|
Plans ACCEPTED BY PLAN TECH | | | 2/26/2009 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/26/2009 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PLANNING Land Div | 2/26/2009 | | 2/26/2009 | | PASS |
Todd Tucker
|
|
|
|
Routing PW Solid Waste | 2/26/2009 | | 2/26/2009 | | PASS |
Peter J. McCullough
|
|
|
|
Plan resubmittals received | | | 2/26/2009 | | DONE |
Barbara Stitt
|
|
|
Received two copies of e2.0; inserted by rep. and taken back to Public Works
|
Routing PW Drainage | 2/26/2009 | | 2/26/2009 | | PASS |
Brian Murphy
|
|
|
|
Application received | | 2/25/2009 | 2/25/2009 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (B_S) Barb | 5/26/2009 | | | | |
Barbara Stitt
|
|
|
|