Permit Information
Permit NumberBLD09-00253
StatusFinaled
Name KING EXCAVATION
Site Address 2900 S CURTIS RD
Project NameBoise Airport Shuttle Parking
Customer Number 
ePlanReviewNo
Description
(Boise Airport Shuttle Parking Lot Expansion - Entry Canopy/Restroom building) To construct a new 211 sq.ft. restroom building and an entry canopy with vehicular drive lanes intended for parking/traffic control. The restroom building consists of one fully accessible Mens restroom and one fully accessible Womens restroom. The exterior walls will be constructed with 8-inch CMU block walls and a thermoplastic membrane roofing system. The Entry canopy construction consists of steel columns on concrete bases, flush vertical seam metal panel wall system, architectural composite metal (ACM) wall panel system, metal panel soffit system, and a thermo plastic membrane roofing. All work per the approved plans, Engineering, and Plan review report. DRH08-00268 **SRZ**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
First Notice 2/7/20102/11/2010 DONE
BLD-Aging Inspection1/20/20101/20/20101/20/2010 PASS
DetailsTom Arcoraci
DOC - Permit Finaled1/20/20101/20/20101/20/2010PPASS
DetailsTom Arcoraci
Letter of compliance  1/20/2010 DONE
Details
BLD-Final11/19/200911/20/200911/20/2009PPASS
DetailsTom Arcoraci
Garett Phone #: ###-####
FIRE-Final Inspection11/19/200911/20/200911/20/2009APASS
DetailsTroy Cobbley
life safety passed
FIRE-Final Inspection11/19/200911/19/200911/19/2009PCANC
DetailsTroy Cobbley
Overbooked no inspection was performed. Garrett said he would reschedule for tomorrow. Garret Phone #: ###-####
BLD-Energy code compliance11/18/200911/19/200911/19/2009ADONE
DetailsTom Arcoraci
Garret Phone #: ###-####
Zoning Approval11/19/200911/19/200911/19/2009 PASS
DetailsJosh Wilson
BLD-Final11/17/200911/18/200911/18/2009ANR
DetailsTom Arcoraci
Garet Phone #: ###-####
BLD-Other11/10/200911/10/200911/10/2009PPASS
DetailsTom Arcoraci
BLD-Aging Inspection11/10/200911/10/200911/10/2009 PASS
DetailsTom Arcoraci
BLD-Framing/Rough-in9/9/20099/10/20099/10/2009APASS
DetailsJim Storey
Greg Phone #: ###-####
BLD-Framing/Rough-in9/9/20099/9/20099/9/2009PNR
DetailsJim Sly
smith Phone #: ###-####
Need Electr R/I............Firebblocking.......Talked to Contr about Special insp Concrete and CMU. OK pending STRATA tests and approvals.
BLD-Framing/Rough-in8/11/20098/12/20098/12/2009ACANC
DetailsDave Hannah
garrett Phone #: ###-#### needs to fire block top of plumbing chase and get all other trades to finish rough-in and get thier inspections. this is for office area only
BLD-Other7/7/20097/7/20097/8/2009PPASS
DetailsTom Arcoraci
BLD-Footing6/5/20096/8/20096/8/2009PPASS
DetailsTom Arcoraci
Garret Phone #: ###-####
Issue PAID IN FULL permit  6/4/2009 DONE
DetailsTisha Gallop
Permit Ready to Issue  5/26/2009 DONE
DetailsBarbara Stitt
Inspection Record Card- Bld  5/26/2009 DONE
Routing - PLAN CHECK5/21/2009 5/22/2009 PASS
DetailsSam Zahorka
PLANS/APPL TAKEN TO FRONT DESK  5/22/2009 DONE
DetailsSam Zahorka
Inspection Record Card- Bld  5/22/2009 DONE
Details
Plan assigned to (SRZ)3/3/2009 5/22/2009 PASS
DetailsSam Zahorka
5/22/2009 08:39:09 SRZ - activity updated through activity BLDA022 from case BLD09-00253.
Routing - Erosion and Sediment5/21/2009 5/21/2009 PASS
DetailsSteven Webb
ESC approved w/attached conditions per SGW
Routing - PLAN CHECK4/13/2009 5/21/2009 PEND
DetailsSam Zahorka
Pending Erosion and sediment to Pass. Routed to ESC.
Telephone call  4/13/2009 DONE
DetailsSam Zahorka
Called Architect and updated him on status of permit. Pending ESC to pass. SRZ
Routing - PLUMBING4/13/2009 4/13/2009 PASS
DetailsBill VanDegrift
1st review completed  4/2/2009 FAIL
Failed Erosion & Soil Control, Plumbing
Routing - FIRE4/1/2009 4/2/2009 PASS
DetailsScott Arellano
Attached IFC comments to plans
Routing - PLAN CHECK3/19/2009 4/1/2009 PEND
DetailsSam Zahorka
Pending others to pass. Routed to Fire
Case Summary (BLD)  3/31/2009 DONE
DetailsSam Zahorka
Routing - PLANNING3/18/2009 3/19/2009 PASS
DetailsJosh Wilson
DRH08-00268 Josh Wilson
Routing - PLUMBING3/17/2009 3/18/2009 FAIL
DetailsBill VanDegrift
premise protection must be located inside the building.
Routing - Erosion and Sediment3/17/2009 3/17/2009 FAIL
DetailsSteven Webb
ESC plan does not meet BMC 8-17 requirements. ESC09-00093
Routing - PUBLIC WORKS3/5/2009 3/17/2009 PASS
DetailsBeverly Hall
Routing PW Sewer Rating  3/17/2009 PASS
DetailsLouise Waldorf
Routing PW Solid Waste  3/12/2009 PASS
DetailsPeter J. McCullough
All waste to be taken off-site (no dumpsters).
Routing PW Street Lights  3/12/2009 PASS
DetailsHank Alarcon
Routing PW Drainage3/5/2009 3/11/2009 PASS
DetailsBrian Murphy
Routing PW Sewer Design3/11/2009 3/11/2009 PASS
DetailsJon R. Gunnerson
connect onto existing sewer service provided
Routing - PLANNING Land Div3/3/2009 3/5/2009 PASS
DetailsDave Abo
Country Club Subdivision No. 4.
Plans ACCEPTED BY PLAN TECH  3/3/2009 DONE
DetailsTisha Gallop
Recd Pcfee & Taken To Pln CK  3/3/2009 DONE
DetailsTisha Gallop
Plan routing begun/NEW & ADDTN  3/3/2009 DONE
DetailsTisha Gallop
Pending Assignment by JCM3/3/2009 3/3/2009 BLDA
DetailsJohn Menard
3/3/2009 14:01:31 JCM - activity updated through activity BLDA160 from case BLD09-00253.
Application received 3/3/2009  DONE
DetailsTisha Gallop