Information based on query as of Friday, August 16, 2024.
Permit Information
Permit NumberBLD09-00273
StatusFinaled
Name DAVE EVANS CONSTRUCTION
Site Address 10159 W OVERLAND RD
Project NameThree Rivers Agency
Customer Number 
ePlanReviewNo
Description
(Three Rivers Agency Office building) For the construction of a new office building and related site work on an existing lot with additional work to include the build out of the tenant space to include multiple offices, break room and two accessible restrooms.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 2/9/20102/9/2010 DONE
Third Notice 1/13/20101/26/2010 DONE
faxed, mailed and called
Third Notice 11/30/200912/30/2009 DONE
faxed
Second Notice 11/14/200911/25/2009 DONE
First Notice 10/26/200911/4/2009 DONE
Permanent Occupancy  10/16/2009 DONE
DetailsTisha Gallop
BLD-Final10/14/200910/15/200910/15/2009PPASS
DetailsMike Jordan
dave Phone #: ###-####. ok for perm occ.
Zoning Approval10/15/200910/15/200910/15/2009 PASS
DetailsJosh Wilson
BLD-Final10/13/200910/13/200910/13/2009PNR
DetailsMike Jordan
Dave Phone #: ###-####. Needs zoning final.
FIRE-Final Inspection10/12/200910/12/200910/12/2009PPASS
DetailsTroy Cobbley
life safety passed
FIRE-Final Inspection10/9/200910/12/200910/12/2009AFAIL
DetailsTroy Cobbley
provide indicator at the main exit
BLD-Framing/Rough-in8/7/20098/7/20098/7/2009PPASS
DetailsJim Sly
Dave Phone #: ###-####
F & E pass
BLD-Framing/Rough-in7/30/20097/30/20097/30/2009PFAIL
DetailsMike Jordan
Dave B Phone #: ###-####. Provide simpson A35 at top and bottom plates at 6x6 wall kicker,both sides. Install correct length 3/4 inch thru bolts at north awening into kicker. Provide LSTA15 simpson straps at all blocking. c/n posted. ok to insul.
BLD-Framing/Rough-in6/29/20096/29/20096/29/2009PPART
DetailsMike Jordan
Shear nail inspection please-Dave Phone #: ###-####. Exterior shear nailing ok.
BLD-Foundation5/29/20096/1/20096/1/2009PPASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 5/29/2009 at 5:22:18 PM. Contact: ###-####.
BLD-Footing5/28/20095/29/20095/29/2009APART
DetailsMike Jordan
Scheduled by a contractor via Hello! on 5/28/2009 at 1:27:32 PM. Contact: ###-####.
Issue PAID IN FULL permit  4/16/2009  
Routing - PLAN CHECK3/20/2009 3/27/2009 PASS
DetailsCarl D Madsen
Telephone call  3/27/2009 DONE
DetailsCarl D Madsen
Left a message with Robert Powell that I still needed the elevation on the front entry landing. 3-27-09 CDM
PLANS/APPL TAKEN TO FRONT DESK  3/27/2009 DONE
DetailsCarl D Madsen
Print Occupancy Form  3/27/2009 DONE
DetailsBarbara Stitt
Permit Ready to Issue  3/27/2009 DONE
DetailsBarbara Stitt
Telephone call  3/27/2009 DONE
DetailsBarbara Stitt
Left a voice message for Scott Grady and told him that permit is ready, fees due and need ACHD required prior to issuance///3-27-09 @ 2:00pm BAS
Plan assigned to (CDM)3/5/2009 3/27/2009 PASS
DetailsCarl D Madsen
3/27/2009 11:51:13 CDM - activity updated through activity BLDA022 from case BLD09-00273.
Plan resubmittals received  3/26/2009  
DetailsTisha Gallop
received response letter, skylight regulations from Kalwall Corpoation, and two copies of sheets A0.0, A1.0, A8.0, EN-1; inserted by arch. rep. and taken back to Carl Madsen.
Route to Impact Fee Review3/19/20093/24/20093/23/2009 PASS
DetailsCindy M. Gould
Credit given for house that was demolished BLD08-02521
Routing - FIRE3/19/20093/19/20093/20/2009 PASS
DetailsScott Arellano
Attached IFC comments to plans
1st review completed  3/20/2009 FAIL
Failed Plan Check
Telephone call  3/19/2009 DONE
DetailsCarl D Madsen
Talked to Robert Powell at Evans Construction about resubmital items. 3-19-09 CDM
Plan resubmittals requested  3/19/2009 DONE
E-mailed plan review report 3-19-09 CDM
Routing - Erosion and Sediment3/12/2009 3/13/2009 PASS
DetailsSteven Webb
ESC plan approved with attached conditons. ESC09-00095
Routing - PLANNING3/13/2009 3/13/2009 PASS
DetailsJosh Wilson
Routing - PLUMBING3/13/2009 3/13/2009 PASS
DetailsDaryl Spivey
per plans and 2003 upc
Routing - PLAN CHECK3/13/2009 3/13/2009 FAIL
DetailsCarl D Madsen
Resubmitals required 3-19-09
Application received 3/5/20093/12/2009 DONE
Routing - PUBLIC WORKS3/5/2009 3/12/2009 PASS
DetailsBeverly Hall
Routing PW Drainage  3/12/2009 PASS
DetailsBrian Murphy
Sub approved drainage plan
Routing PW Sewer Rating3/12/2009 3/12/2009 PASS
DetailsLouise Waldorf
Routing PW Solid Waste3/12/2009 3/12/2009 PASS
DetailsPeter J. McCullough
Trash Enclosure gates must open 120 degrees minimum.
Peter McCullough ###-####
Routing PW Street Lights  3/9/2009 PASS
DetailsHank Alarcon
Routing PW Sewer Design3/6/2009 3/6/2009 PASS
DetailsJon R. Gunnerson
Connect to sanitary sewer services provided.
Recd Pcfee & Taken To Pln CK  3/5/2009 DONE
DetailsDarla L Downs
Routing - PLANNING Land Div3/5/2009 3/5/2009 PASS
DetailsDave Abo
Lot 2, Block 1 of Honeymoon Cove Subdivision.
Pending Assignment by JCM3/5/2009 3/5/2009 DONE
DetailsJohn Menard
Plans ACCEPTED BY PLAN TECH  3/5/2009 DONE
DetailsDarla L Downs
Plan routing begun/NEW & ADDTN  3/5/2009 DONE
DetailsDarla L Downs