Third Notice | | 9/1/2009 | 9/8/2009 | | DONE |
|
|
|
|
Second Notice | | 7/24/2009 | 9/1/2009 | | DONE |
|
|
|
|
First Notice | | 4/7/2009 | 7/24/2009 | | DONE |
|
|
|
|
Permanent Occupancy UNPAID FEE | | | 4/7/2009 | | DONE |
|
|
|
|
FIRE-Final Inspection | 4/1/2009 | 4/2/2009 | 4/2/2009 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Final | 4/1/2009 | 4/2/2009 | 4/2/2009 | A | PASS |
Mike Jordan
|
|
|
ron Phone #: ###-####. ok for perm occ. Also received and reveiwed cooler specs, ok. Will have elec. scanned into permit.
|
FIRE-Final Inspection | 3/31/2009 | 4/1/2009 | 4/1/2009 | A | FAIL |
Troy Cobbley
|
|
|
The new wall has caused the existing sprinkler pendants to be overspaced and a separate permit is required for this work. All other life safety items are ok to pass when this fire sprinkler work is complete.
|
BLD-Framing/Rough-in | 3/30/2009 | 3/31/2009 | 3/31/2009 | A | PASS |
Mike Jordan
|
|
|
cal Phone #: ###-####. Interior wood framed wall ok.
|
BLD-Framing/Rough-in | 3/27/2009 | 3/30/2009 | 3/30/2009 | P | NR |
Mike Jordan
|
|
|
Cal Phone #: ###-####. Framing not yet constructed. Also needs to pull elec. permit. contractor was notified.
|
Issue PAID IN FULL permit | | | 3/10/2009 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PLAN CHECK | 3/6/2009 | | 3/9/2009 | | PASS |
Carl D Madsen
|
|
|
|
Routing - Addressing | 3/5/2009 | | 3/9/2009 | | PASS |
Chris Pichardo
|
|
|
|
Routing - FIRE | | | 3/9/2009 | | PASS |
|
|
|
Verify in field CDM
|
1st review completed | | | 3/9/2009 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 3/9/2009 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/9/2009 | | |
|
|
|
|
Print Occupancy Form | | | 3/9/2009 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/9/2009 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Telephone call | | | 3/9/2009 | | DONE |
|
|
|
left vm for cal meyers at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 3/9/2009 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 3/6/2009 | | 3/6/2009 | | PASS |
Beverly Hall
|
|
|
|
Routing PW Sewer Rating | 3/6/2009 | | 3/6/2009 | | PASS |
Louise Waldorf
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/5/2009 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/5/2009 | | DONE |
Darla L Downs
|
|
|
Mech value of $ 750.00 did not see the plans for that
|
Application received | | 3/5/2009 | | | |
|
|
|
|