Third Notice | | 12/13/2010 | 12/27/2010 | | DONE |
|
|
|
|
Second Notice | | 11/25/2010 | 12/8/2010 | | DONE |
|
|
|
|
First Notice | | 11/4/2010 | 11/15/2010 | | DONE |
|
|
|
|
Permanent Occupancy | | | 10/25/2010 | | DONE |
Barbara Stitt
|
|
|
|
BLD-Final | 9/29/2010 | 9/29/2010 | 10/21/2010 | P | PASS |
Dave Hannah
|
|
|
Dave please see if this is can have perm occupancy? Temp Occupancy is expired--See Barb Phone #: ###-####
|
BLD-Final | 9/28/2010 | 9/29/2010 | 9/30/2010 | A | NH |
Dave Hannah
|
|
|
Dave please see if this is can have perm occupancy? Temp Occupancy is expired--See Barb Phone #: ###-#### no at site
|
BLD-Aging Inspection | 8/24/2010 | 8/24/2010 | 8/25/2010 | | PASS |
Dave Hannah
|
|
|
|
Temporary Occupancy | 3/8/2010 | 6/10/2010 | 3/8/2010 | | DONE |
Jenifer Gilliland
|
|
|
|
FIRE-Final Inspection | 12/2/2009 | 12/3/2009 | 12/3/2009 | A | PASS |
Forrest France
|
|
|
Fire life safety is acceptable pending approved hardware at the inactive door leaf on the main entry/exit pair of doors-see review comment # 5. Structural inspector to verify prior to permit final.
|
BLD-Final | 12/2/2009 | 12/3/2009 | 12/3/2009 | A | PART |
Dave Hannah
|
|
|
wants temp.//Joel Hunter ###-#### ok for temp occ needs plumbing to go perm and fix lock on front door
|
Temporary Occupancy UNPAID FEE | | | 12/3/2009 | | DONE |
Tisha Gallop
|
|
|
|
FIRE-Conference | 10/28/2009 | 10/28/2009 | 10/28/2009 | P | DONE |
Forrest France
|
|
|
On site conference regarding fire code review notes and items needed for final including EM lighting, occ. load sign, PFE's, door hardware, fire sprinkler coverage, etc.
|
BLD-Framing/Rough-in | 9/14/2009 | 9/15/2009 | 9/15/2009 | A | PART |
Dave Hannah
|
|
|
Joel-please call prior to inspection Phone #: ###-#### ok to cover plumbing wall after plumbing r/i
|
BLD-Framing/Rough-in | 9/10/2009 | 9/11/2009 | 9/11/2009 | P | PART |
Dave Hannah
|
|
|
Joel-after 2 please Phone #: ###-#### ok to cover new 2hr corrador
|
Issue PAID IN FULL permit | | | 8/20/2009 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PLAN CHECK | 6/10/2009 | | 8/14/2009 | | PASS |
Carl Westfall
|
|
|
(6-22-09) Quickly checked the architect's resubmittal. Waiting for mechanical plans. Will do a thorough resubmittal review after all the resubmittals are received. (8-14-09) A permit for the shell work (BLD09-01327) was submitted. Ventilation for this tenant space will be provided under permit BLD09-01327.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/14/2009 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/14/2009 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/14/2009 | | DONE |
|
|
|
|
Telephone call | | | 8/14/2009 | | DONE |
Barbara Stitt
|
|
|
Left voice message for Greg Eggleston that permit is ready, fees due and that we need a new cert of value to include plumbing and fire value's///8-14-09 @ 4:15pm BAS
|
Plan assigned to (CJW) | 3/9/2009 | | 8/14/2009 | | PASS |
Carl Westfall
|
|
|
8/14/2009 13:48:34 CJW - activity updated through activity BLDA022 from case BLD09-00295.
|
Plan resubmittals received | | | 6/17/2009 | | DONE |
|
|
|
received 1 response letter, and 2 copies of sheet A-101 taken to Carl W.
|
Routing - PLAN CHECK | 6/8/2009 | | 6/10/2009 | | FAIL |
Carl Westfall
|
|
|
Completed the latest resubmittal. Issues still not resolved.
|
Plan Reviewer's activity | | | 6/10/2009 | | DONE |
|
|
|
Sent an E-mail updating Rob Thornton, Larry Sundell, the tenant, the contractor, Jenifer Gilliland, and Jason Blais about this project. This project has been stalled because architects are having a problem coordinating. Sent E-mail to update all those who are, or who could be, involved.
|
Plan resubmittals received | | | 6/9/2009 | | |
Carl Westfall
|
|
|
Rec'd 2 copies of sheet A-101 and response letter- taken to Carl Westfall
|
Routing - PLAN CHECK | 3/26/2009 | | 6/8/2009 | | FAIL |
Carl Westfall
|
|
|
Comleted the 2nd resubmittal review. E-mailed Rob Thornton and Larry Sundell a list of things needed. Waiting for resubmittals.
|
Plan resubmittals received | | | 6/1/2009 | | |
Tisha Gallop
|
|
|
received response letter from architect and two copies of pages G-001, A-101; taken to Carl Westfall
|
Plan Reviewer's activity | | | 4/17/2009 | | DONE |
|
|
|
Sent the Architect an E-mail asking for revised drawings.
|
Routing - PLAN CHECK | 3/19/2009 | | 3/26/2009 | | FAIL |
Carl Westfall
|
|
|
Resubmittals received 3-25-2009. Resubmittal review completed on 3-26-2009. Sent drawings to Public Works because 2 drinking fountains were added.
|
Routing - PUBLIC WORKS | 3/26/2009 | | 3/26/2009 | | PASS |
Louise Waldorf
|
|
|
2 drinking fountains added. The sink replaces an existing sink.
|
Routing PW Sewer Rating | 3/26/2009 | | 3/26/2009 | | PASS |
Connie Baumgartner
|
|
|
|
Plan resubmittals received | | | 3/25/2009 | | |
Tisha Gallop
|
|
|
received two copies of sheets G-001, A-101; taken to Carl Westfall
|
Routing - FIRE | 3/16/2009 | 3/16/2009 | 3/19/2009 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
1st review completed | | | 3/19/2009 | | FAIL |
|
|
|
Failed Plan Check
|
Route to Impact Fee Review | 3/16/2009 | 3/19/2009 | 3/17/2009 | | PASS |
Cindy M. Gould
|
|
|
Tenant improvement no impact fees
|
Routing - PLAN CHECK | 3/9/2009 | | 3/16/2009 | | FAIL |
Carl Westfall
|
|
|
The IBC plan review was started on March 11, 2009 and was finished on March 16, 2009. Revised drawings were required. See the plan review report.
|
Application received | | 3/9/2009 | 3/9/2009 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 3/9/2009 | | PASS |
Tim L. Woodard
|
|
|
Applicant was required to submit as a Level III vs. Level II that he was hoping for. I retitled the application to be a Major TI and also went threw the Major TI checklist but did not require him to fill out all new paper work. TLW
|
Plans ACCEPTED BY PLAN TECH | | | 3/9/2009 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/9/2009 | | DONE |
Tisha Gallop
|
|
|
|
Pending Assignment by JCB | 3/9/2009 | | 3/9/2009 | | DONE |
Jason Blais
|
|
|
|