Case Summary (BLD) | | | 9/2/2011 | | |
|
|
|
|
BLD-Aging Inspection | 11/4/2010 | 11/4/2010 | 11/9/2010 | | CANC |
Mike Jordan
|
|
|
|
DOC - Permit Expired | 11/9/2010 | 11/9/2010 | 11/9/2010 | P | PASS |
Mike Jordan
|
|
|
All finals have been completed. permit is expired. No one to pick up certificate of occupancy.
|
BLD-Final | 4/3/2009 | 4/6/2009 | 4/6/2009 | A | PASS |
Mike Jordan
|
|
|
Todd- Phone #: ###-####
|
FIRE-Final Inspection | 4/3/2009 | 4/6/2009 | 4/6/2009 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.
|
BLD-Final | 3/30/2009 | 3/30/2009 | 3/30/2009 | P | NR |
Tom Arcoraci
|
|
|
TODD Phone #: ###-#### PLEASE CALL 20 MIN BEFORE GOING OUT.
|
FIRE-Final Inspection | 3/30/2009 | 3/30/2009 | 3/30/2009 | A | FAIL |
Troy Cobbley
|
|
|
Provide panic/fire haredware on the two south facing exterior exit doors. Provide panic/fire hardware on the two exit doors from the conference room 103 and provide the correct door swing. These items have been addressed on the city approved plans.
|
BLD-Framing/Rough-in | 3/26/2009 | 3/27/2009 | 3/27/2009 | A | PASS |
Tom Arcoraci
|
|
|
Todd Please call 20min before going out Phone #: ###-####
|
Issue PAID IN FULL permit | | | 3/26/2009 | | DONE |
|
|
|
|
Plan assigned to (TLW) | 3/17/2009 | | 3/25/2009 | | PASS |
Tim L. Woodard
|
|
|
3/25/2009 14:20:34 TLW - activity updated through activity BLDA022 from case BLD09-00340.
|
Plan resubmittals received | | | 3/25/2009 | | DONE |
|
|
|
received 1 letter,and 2 copies of sheet A2.1 taken to Tim W.
|
Routing - PLAN CHECK | 3/25/2009 | | 3/25/2009 | | PASS |
Tim L. Woodard
|
|
|
Resubmittals recieved and approved. TLW
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/25/2009 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 3/25/2009 | | DONE |
|
|
|
|
Telephone call | | | 3/25/2009 | | DONE |
|
|
|
Called Jim ,permit ready and fee given ///DLD
|
Permit Ready to Issue | | | 3/25/2009 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/25/2009 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 3/17/2009 | | 3/23/2009 | | FAIL |
Tim L. Woodard
|
|
|
Plan Review Report sent to architect.
|
1st review completed | | | 3/23/2009 | | FAIL |
Tim L. Woodard
|
|
|
|
Plan resubmittals received | | | 3/19/2009 | | |
Tisha Gallop
|
|
|
received two copies of sheet A2.1; taken to Tim Woodard
|
Application received | | 3/17/2009 | 3/17/2009 | | DONE |
Barbara Stitt
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/17/2009 | | DONE |
Barbara Stitt
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/17/2009 | | DONE |
Barbara Stitt
|
|
|
|