First Notice | | 5/26/2011 | 5/16/2011 | | DONE |
Tisha Gallop
|
|
|
final cert of value provided by Bill Matter at time of expiration; scanned into documents.
|
Zoning Approval | 3/24/2011 | 3/24/2011 | 3/24/2011 | | DONE |
Josh Wilson
|
|
|
|
DOC-Permit Expired | 3/23/2011 | 3/23/2011 | 3/23/2011 | | DONE |
Jim Sly
|
|
|
Permit expired by limitations.
|
Reopen Permit (ISS) | | | 3/22/2011 | | DONE |
Tisha Gallop
|
|
|
ok to reopen per Bob A.
|
Plan assigned to (LEG) Tisha | 3/25/2009 | | 9/4/2010 | | DONE |
Tisha Gallop
|
|
|
|
DOC-Permit Expired | 5/21/2010 | 5/21/2010 | 5/21/2010 | | DONE |
Jim Sly
|
|
|
Permit expired by limitations.
|
CHANGE STATUS TO (ISS) | | | 9/9/2009 | | DONE |
Tisha Gallop
|
|
|
picked up and paid for plan mod
|
(F) Reprint permit | | | 9/9/2009 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PLAN CHECK | 9/4/2009 | | 9/4/2009 | | PASS |
Tisha Gallop
|
|
|
passed all depts needed for plan modification
|
Case Summary (BLD) | | | 9/4/2009 | | DONE |
|
|
|
|
Telephone call | | | 9/4/2009 | | DONE |
Tisha Gallop
|
|
|
called Martin Santoyo and told him plan mod approved and fees due
|
Permit Ready to Issue | | | 9/4/2009 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PLUMBING | 9/3/2009 | | 9/4/2009 | | PASS |
Bill VanDegrift
|
|
|
provide 1% grade on 4" horizontal rain water line to catch basin if existing conditions allow.
|
Routing - PLANNING | 9/3/2009 | | 9/3/2009 | | PASS |
Joshua Johnson
|
|
|
CUP09-00049, CVA09-00026 Josh Johnson
|
Routing PW Drainage | 9/2/2009 | | 9/3/2009 | | PASS |
Brian Murphy
|
|
|
|
Routing - PUBLIC WORKS | 9/3/2009 | | 9/3/2009 | | PASS |
Beverly Hall
|
|
|
|
Routing - Addressing | 9/2/2009 | | 9/2/2009 | | PASS |
April Wing
|
|
|
|
Routing - Erosion and Sediment | 9/1/2009 | | 9/1/2009 | | PASS |
Tisha Gallop
|
|
|
Per SGW original ESC plan ok not need any revisions for plan modification.
|
Plan Modification Accepted | | | 9/1/2009 | | DONE |
Tisha Gallop
|
|
|
Accepted plan modification for Bld09-00375 (Grading/drainage parking lot for Evergreen Plaza) to mofify the parking lot as the West side of the Boise Barber College building for furture drive-through. Plan modification includes roof drain (route to plumbing). Submitted on sheet SD3 and dwg#3361 (11"x17"); routed to PW, Planning, Plumbing and ESC.
|
BLD-Aging Inspection | 7/20/2009 | 7/20/2009 | 7/20/2009 | | PASS |
Tom Arcoraci
|
|
|
|
Inspection Record Card- Bld | | | 4/10/2009 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 4/10/2009 | | DONE |
Tisha Gallop
|
|
|
spoke to Bill Matter and told him permit is ready, fee, and need GC, RCE
|
Permit Ready to Issue | | | 4/10/2009 | | DONE |
Tisha Gallop
|
|
|
|
Issue PAID IN FULL permit | | | 4/10/2009 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PLAN CHECK | 4/9/2009 | | 4/9/2009 | | PASS |
Tisha Gallop
|
|
|
passed all departments, took copy of plans to records
|
Routing - PUBLIC WORKS | 4/6/2009 | | 4/9/2009 | | PASS |
Beverly Hall
|
|
|
|
Routing PW Drainage | 4/9/2009 | | 4/9/2009 | | PASS |
Brian Murphy
|
|
|
|
1st review completed | | | 4/6/2009 | | FAIL |
|
|
|
Failed Public Works
|
Routing - PLAN CHECK | 4/6/2009 | | 4/6/2009 | | PEND |
Tisha Gallop
|
|
|
routed to PW
|
Routing - FIRE | 4/2/2009 | | 4/6/2009 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
Plan resubmittals received | | | 4/3/2009 | | DONE |
Tisha Gallop
|
|
|
received transmittal and five copies of sheet C2.1; inserted by LEG and taken back to fire review.
|
Routing - Erosion and Sediment | 4/1/2009 | | 4/2/2009 | | PASS |
Steven Webb
|
|
|
ESC plan waiver approved with attached conditions. ESC09-00137
|
Routing - PLANNING | 4/2/2009 | | 4/2/2009 | | PASS |
Josh Wilson
|
|
|
CZC08-00105 Josh Wilson
|
Routing - PUBLIC WORKS | 3/30/2009 | | 4/1/2009 | | FAIL |
Connie Baumgartner
|
|
|
Failed by Brian Murphy, contact a ###-####.
|
Routing PW Street Lights | 4/1/2009 | | 4/1/2009 | | PASS |
Hank Alarcon
|
|
|
|
Routing PW Drainage | 3/31/2009 | | 3/31/2009 | | FAIL |
Brian Murphy
|
|
|
Waiting on drainage sheets from Dave Marks. Brian Murphy ###-####
|
Routing - PLANNING Land Div | 3/25/2009 | | 3/30/2009 | | PASS |
Dave Abo
|
|
|
Approved for grading.
|
Plans ACCEPTED BY PLAN TECH | | | 3/25/2009 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/25/2009 | | DONE |
Tisha Gallop
|
|
|
|
Application received | | 3/25/2009 | | | |
|
|
|
|