Third Notice | | 9/8/2009 | 9/15/2009 | | DONE |
|
|
|
|
Third Notice | | 8/11/2009 | 9/8/2009 | | DONE |
|
|
|
|
Second Notice | | 7/22/2009 | 8/11/2009 | | DONE |
|
|
|
|
First Notice | | 7/17/2009 | 7/22/2009 | | DONE |
|
|
|
|
FIRE-Conference | 7/17/2009 | 7/17/2009 | 7/17/2009 | P | DONE |
Troy Cobbley
|
|
|
I went over the gas cabinet requirements with Greg. He is limited to 504 cubic feet as per fire review note #12.
|
BLD-Final | 7/16/2009 | 7/17/2009 | 7/17/2009 | A | PASS |
Jim Sly
|
|
|
Greg Phone #: ###-#### OK for Perm Occ.
|
Permanent Occupancy UNPAID FEE | | | 7/17/2009 | | DONE |
|
|
|
|
BLD-Final | 7/15/2009 | 7/16/2009 | 7/16/2009 | P | NR |
Jim Sly
|
|
|
greg Phone #: ###-#### Need Zoning final
|
FIRE-Final Inspection | 7/15/2009 | 7/16/2009 | 7/16/2009 | A | PASS |
Troy Cobbley
|
|
|
Fire life safety passed
|
Zoning Approval | 7/16/2009 | 7/16/2009 | 7/16/2009 | | PASS |
Andrea Tuning
|
|
|
The applicant only completed interior tenant improvements and a zoning inspection was not needed due to the fact that the building, parking and landscaping was completed in 2006.
|
FIRE-Final Inspection | 7/13/2009 | 7/14/2009 | 7/15/2009 | P | FAIL |
Troy Cobbley
|
|
|
Life safety will be ok to final when the project related fire alarm and fire sprinkler drawings have been modified to exclude sutie 325
|
Override - Parcel Holds | 7/15/2009 | 1/1/1900 | 7/15/2009 | | |
|
|
|
3rd floor
|
Override - Parcel Holds | 7/15/2009 | 1/1/1900 | 7/15/2009 | | |
|
|
|
3rd floor
|
Override - Parcel Holds | 7/13/2009 | 1/1/1900 | 7/13/2009 | | |
|
|
|
fire life safety
|
BLD-Framing/Rough-in | 7/9/2009 | 7/9/2009 | 7/9/2009 | P | PASS |
Tom Arcoraci
|
|
|
Ceiling grid for cover-Greg Phone #: ###-####
|
Override - Parcel Holds | 7/9/2009 | 1/1/1900 | 7/9/2009 | | |
|
|
|
not in the affected area
|
BLD-Framing/Rough-in | 6/1/2009 | 6/1/2009 | 6/1/2009 | P | PART |
Mike Jordan
|
|
|
INterior frmaed walls only. No grid.Pend. plumbing ri insp.
|
BLD-Framing/Rough-in | 5/29/2009 | 6/1/2009 | 6/1/2009 | A | NR |
Mike Jordan
|
|
|
Greg-3rd floor Phone #: ###-####. Rescheduled for pm. Still needs plumbing ri insp.
|
BLD-Framing/Rough-in | 5/29/2009 | 5/29/2009 | 5/29/2009 | P | NR |
Mike Jordan
|
|
|
Greg ###-####. Needs plumbing ri first.
|
Override - Parcel Holds | 5/29/2009 | 1/1/1900 | 5/29/2009 | | |
|
|
|
this is on 3rd floor
|
Override - Parcel Holds | | | 5/29/2009 | | |
|
|
|
|
BLD-Conference | 5/14/2009 | 5/15/2009 | 5/15/2009 | A | DONE |
Mike Jordan
|
|
|
Greg Phone #: ###-####. Noted that contractor has resubmitted plans for additional work.
|
FIRE-Conference | 5/13/2009 | 5/14/2009 | 5/14/2009 | A | DONE |
Troy Cobbley
|
|
|
I contacted Layton construction about the attached FIR permit. Per the BLD permit all of the work is on the third floor. The attached FIR is for work on the second floor that they are not a part of.
|
Issue PAID IN FULL permit | | | 5/8/2009 | | DONE |
|
|
|
|
Plan assigned to (SRZ) | 4/7/2009 | | 5/5/2009 | | PASS |
Sam Zahorka
|
|
|
5/5/2009 13:09:13 SRZ - activity updated through activity BLDA022 from case BLD09-00427.
|
Routing - PLAN CHECK | 4/24/2009 | | 5/5/2009 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/5/2009 | | DONE |
Sam Zahorka
|
|
|
|
Print Occupancy Form | | | 5/5/2009 | | DONE |
|
|
|
|
Telephone call | | | 5/5/2009 | | DONE |
|
|
|
left vm for jeremy hobbs at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 5/5/2009 | | DONE |
|
|
|
|
Routing - FIRE | | | 4/24/2009 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
Routing - FIRE | 4/22/2009 | | 4/24/2009 | | FAIL |
Scott Arellano
|
|
|
Faxed and emailed resubmittal items to architect.
|
1st review completed | | | 4/24/2009 | | FAIL |
|
|
|
Failed Fire
|
Routing - PLAN CHECK | 4/9/2009 | | 4/22/2009 | | PEND |
Sam Zahorka
|
|
|
Routed to Fire.
|
Case Summary (BLD) | | | 4/22/2009 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PUBLIC WORKS | 4/7/2009 | | 4/9/2009 | | PASS |
Beverly Hall
|
|
|
|
Routing PW Sewer Rating | 4/7/2009 | | 4/8/2009 | | PASS |
Connie Baumgartner
|
|
|
|
Pending Assignment by JCB | 4/6/2009 | | 4/7/2009 | | DONE |
Jason Blais
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/6/2009 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/6/2009 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 4/3/2009 | | PASS |
Sam Zahorka
|
|
|
|
Application received | | 4/3/2009 | | | |
|
|
|
|