BLD-Final | 9/10/2009 | 9/11/2009 | 9/15/2009 | P | PASS |
Tony Young
|
|
|
george Phone #: ###-####
|
DOC - Permit Finaled | 9/15/2009 | 9/15/2009 | 9/15/2009 | P | PASS |
Tony Young
|
|
|
|
BLD-Final | 9/9/2009 | 9/10/2009 | 9/10/2009 | A | NR |
Tony Young
|
|
|
george Phone #: ###-####
|
BLD-Final | 9/8/2009 | 9/9/2009 | 9/9/2009 | A | CANC |
Tony Young
|
|
|
george Phone #: ###-####
|
BLD-Final | 9/4/2009 | 9/4/2009 | 9/8/2009 | P | PART |
Tony Young
|
|
|
george Phone #: ###-#### conf on job,, need front steps to meet code,, fire caulk
|
BLD-Grading Inspection | 9/8/2009 | 9/8/2009 | 9/8/2009 | A | BOND |
Terry Records
|
|
|
Approved house occupancy with $2,000.00 bond to ensure that grading is done according to plan. Bond has been submitted.
|
BLD-Energy code compliance | 7/9/2009 | 7/9/2009 | 7/9/2009 | P | PASS |
Tony Young
|
|
|
George Phone #: ###-####
|
BLD-Framing/Rough-in | 7/1/2009 | 7/2/2009 | 7/2/2009 | A | PASS |
Tony Young
|
|
|
george Phone #: ###-####
|
BLD-Framing/Rough-in | 7/1/2009 | 7/1/2009 | 7/2/2009 | P | FAIL |
Tony Young
|
|
|
george Phone #: ###-#### need energy seal
|
BLD-Wall cover | 6/18/2009 | 6/19/2009 | 6/19/2009 | A | CANC |
Dave Hannah
|
|
|
George Phone #: ###-#### shear ok to cover ext
|
BLD-Foundation | 5/28/2009 | 5/28/2009 | 5/28/2009 | P | PART |
Tony Young
|
|
|
wip
|
BLD-Footing | 5/27/2009 | 5/28/2009 | 5/28/2009 | A | PART |
Tony Young
|
|
|
Sebastian Phone #: ###-#### pier ftgs wip
|
BLD-Footing | 5/27/2009 | 5/27/2009 | 5/28/2009 | P | PART |
Tony Young
|
|
|
Sebastian Phone #: ###-#### wip
|
PubWorks Subgrade Approval | 5/27/2009 | 5/27/2009 | 5/27/2009 | | DONE |
Terry Records
|
|
|
Footing subgrade has been approved by the geotechnical engineer
|
Issue PAID IN FULL permit | | | 5/27/2009 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Route to Impact Fee Review | 4/7/2009 | 4/10/2009 | 4/16/2009 | | PASS |
Cindy M. Gould
|
|
|
|
Plan assigned to (BSP) | 4/7/2009 | 4/7/2009 | 4/16/2009 | | PASS |
Ben S. Pavelka
|
|
|
4/16/2009 09:10:29 BSP - activity updated through activity BLDA022 from case BLD09-00445.
|
Routing - PLAN CHECK | 4/9/2009 | | 4/16/2009 | | PASS |
Ben S. Pavelka
|
|
|
Plan review complete, needs to be routed to Fire. BSP 4-15-09
|
Routing - FIRE | | | 4/16/2009 | | PASS |
|
|
|
No fire sprinklers required based on the house proximity to Wintercamp Rd. (Eyrie Sub. # 3)
|
Case Summary (BLD) | | | 4/16/2009 | | DONE |
Ben S. Pavelka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/16/2009 | | DONE |
Ben S. Pavelka
|
|
|
|
Inspection Record Card- Bld | | | 4/16/2009 | | DONE |
|
|
|
|
Telephone call | | | 4/16/2009 | | DONE |
|
|
|
left message w don for george at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 4/16/2009 | | DONE |
|
|
|
|
1st review completed | | | 4/15/2009 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 4/8/2009 | | 4/9/2009 | | PASS |
Steven Webb
|
|
|
ESC plan approved with attached conditions. ESC09-00159
|
Routing - PLANNING | 4/7/2009 | | 4/8/2009 | | PASS |
Lucinda Grames
|
|
|
|
Application received | | 4/7/2009 | 4/7/2009 | | DONE |
Barbara Stitt
|
|
|
|
Routing - Addressing | 4/7/2009 | | 4/7/2009 | | PASS |
Chris Pichardo
|
|
|
|
Routing - PUBLIC WORKS | 4/7/2009 | | 4/7/2009 | | PASS |
Louise Waldorf
|
|
|
|
Routing - PUBLIC WORKS GRADING | 4/7/2009 | | 4/7/2009 | | PASS |
Terry Records
|
|
|
Approved as Category 3
|