Information based on query as of Thursday, July 25, 2024.
Permit Information
Permit NumberBLD09-00467
StatusFinaled
Name CM COMPANY
Site Address 519 N 9TH ST
Project NameBOISE HIGH SCHOOL
Customer Number 
ePlanReviewNo
Description
(BOISE HIGH SCHOOL - MUSIC BUILDING UPGRADE) This permit is to install new A/C units in the existing Music Building at Boise High School. Approval per approved plans on file. Work to include: demolition and removal of old A/C units, installation of new A/C units, and interior finishes in compliance with chapter 8 of the 2006 IBC. This building is fully fire sprinklered any alterations or modifications to the sprinkler system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA #13 as regulated by the fire department. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 10/31/200911/5/2009 DONE
DetailsBarbara Stitt
Second Notice 9/28/200910/21/2009 DONE
First Notice8/25/20098/25/20099/18/2009 DONE
DetailsTony Young
Letter of compliance  9/16/2009 DONE
DetailsTisha Gallop
BLD-Final8/24/20098/25/20098/25/2009APASS
DetailsTony Young
Craig Phone #: ###-####
DOC - Permit Finaled8/25/20098/25/20098/25/2009PPASS
DetailsTony Young
FIRE-Final Inspection8/21/20098/24/20098/24/2009APASS
DetailsForrest France
Fire life safety inspection passed.
Issue PAID IN FULL permit  4/27/2009 DONE
DetailsTisha Gallop
Received Certificate of Value  4/24/2009 DONE
DetailsTisha Gallop
Received revised cert of value from the GC: new project value is $76,224; ele $15,000; plm incl. in mech.; mech $40,000; fire sprinkler n/a; fire alarm incl. in elec.//4/24/09 LEG
Telephone call  4/24/2009 DONE
DetailsTisha Gallop
called and left voice message for Erin at CM Co. of new fees calculated.
Case Summary (BLD)  4/16/2009 DONE
DetailsTim L. Woodard
Inspection Record Card- Bld  4/16/2009 DONE
Details
Telephone call  4/16/2009 DONE
Details
t/c w ed daniels at ###-#### - permit ready and fees given
Permit Ready to Issue  4/16/2009 DONE
Details
Plan assigned to (TLW)4/9/2009 4/15/2009 PASS
DetailsTim L. Woodard
4/15/2009 16:18:48 TLW - activity updated through activity BLDA022 from case BLD09-00467.
Routing - Erosion and Sediment4/15/2009 4/15/2009 PASS
DetailsTim L. Woodard
Waiver Letter approved. Applicant must comply with conditions attached to plans. TLW
PLANS/APPL TAKEN TO FRONT DESK  4/15/2009 DONE
Case Summary (BLD)  4/15/2009 PASS
DetailsTim L. Woodard
Routing - PLAN CHECK4/9/2009 4/14/2009 PASS
DetailsTim L. Woodard
Routing - Erosion and Sediment4/14/2009 4/14/2009 FAIL
DetailsTim L. Woodard
No ESC plan or Waiver Letter
Routing - FIRE  4/14/2009 PASS
Field Verify
1st review completed  4/14/2009 FAIL
DetailsTim L. Woodard
Failed ESC
Plans ACCEPTED BY PLAN TECH  4/9/2009 DONE
DetailsTisha Gallop
Recd Pcfee & Taken To Pln CK  4/9/2009 DONE
DetailsTisha Gallop
Application received 4/8/2009