Permanent Occupancy | | | 4/26/2012 | | DONE |
|
|
|
|
FIRE-Final Inspection | 7/6/2011 | 7/7/2011 | 7/7/2011 | A | PASS |
Forrest France
|
|
|
Fire life safety finaled.
|
BLD-Final | 7/7/2011 | 7/7/2011 | 7/7/2011 | A | PASS |
Jim Storey
|
|
|
|
BLD-Final | 7/6/2011 | 7/7/2011 | 7/7/2011 | A | PASS |
Jim Storey
|
|
|
andy Phone #: ###-####
|
DOC - Permit Finaled | 7/7/2011 | 7/7/2011 | 7/7/2011 | P | PASS |
Jim Storey
|
|
|
|
FIRE-Final Inspection | 7/5/2011 | 7/6/2011 | 7/6/2011 | P | PASS |
Forrest France
|
|
|
Fire life safety final okay at units 104 and 204.
|
FIRE-Final Inspection | 6/8/2011 | 6/9/2011 | 6/9/2011 | A | CANC |
Troy Cobbley
|
|
|
To be canceled per Andy Phone #: ###-####
|
BLD-Energy code compliance | 6/3/2011 | 6/6/2011 | 6/6/2011 | A | PASS |
Jim Storey
|
|
|
Andy Phone #: ###-####
|
FIRE-Sprinkler Rough-in | 6/3/2011 | 6/3/2011 | 6/3/2011 | P | PART |
Forrest France
|
|
|
New fire sprinkler work at units 104 and 204 approved for cover.
|
BLD-Framing/Rough-in | 6/2/2011 | 6/3/2011 | 6/3/2011 | A | PASS |
Jim Storey
|
|
|
Andy Phone #: ###-#### non-conbustable framing at fur down w/gyp atched to floor.
|
BLD-Aging Inspection | 4/11/2011 | 4/11/2011 | 4/11/2011 | | PEND |
Jim Storey
|
|
|
fire alarm sign off.
|
BLD-Aging Inspection | 2/7/2011 | 2/7/2011 | 2/8/2011 | | PASS |
Jim Storey
|
|
|
|
(F) Reprint permit | | | 1/3/2011 | | DONE |
Christina Prado
|
|
|
Changed GC reprint to show new GC
|
BLD-Aging Inspection | 12/6/2010 | 12/6/2010 | 12/8/2010 | | PASS |
Jim Storey
|
|
|
|
BLD-Aging Inspection | 10/4/2010 | 10/4/2010 | 10/5/2010 | | PASS |
Jim Storey
|
|
|
funding isues/ fire open
|
BLD-Aging Inspection | 8/2/2010 | 8/2/2010 | 8/2/2010 | | PASS |
Jim Storey
|
|
|
|
BLD-Aging Inspection | 5/31/2010 | 5/31/2010 | 6/1/2010 | | PASS |
Jim Storey
|
|
|
work will continue
|
BLD-Aging Inspection | 3/29/2010 | 3/29/2010 | 3/30/2010 | | PASS |
Jim Storey
|
|
|
work will continue
|
BLD-Aging Inspection | 1/27/2010 | 1/27/2010 | 1/27/2010 | | PASS |
Jim Storey
|
|
|
wip
|
FIRE-Sprinkler Rough-in | 11/25/2009 | 11/25/2009 | 11/27/2009 | P | PART |
Forrest France
|
|
|
Okayed overhead cover for fire sprinkler install-see green tag on site.
|
BLD-Aging Inspection | 10/27/2009 | 10/27/2009 | 10/28/2009 | | NR |
Jim Storey
|
|
|
|
BLD-Aging Inspection | 8/27/2009 | 8/27/2009 | 8/27/2009 | | NR |
Jim Storey
|
|
|
|
Issue PAID IN FULL permit | | | 5/27/2009 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 5/13/2009 | | DONE |
Tisha Gallop
|
|
|
Called Cathy Sewell and told her permit ready, fees and need ACHD
|
Override - Parcel Holds | | | 5/13/2009 | | |
|
|
|
|
Permit Ready to Issue | | | 5/13/2009 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (SRZ) | 4/16/2009 | 4/16/2009 | 5/12/2009 | | PASS |
Sam Zahorka
|
|
|
5/12/2009 09:20:56 TLW - activity updated through activity BLDA022 from case BLD09-00510.
|
Routing - Erosion and Sediment | 5/8/2009 | | 5/12/2009 | | PASS |
Steven Webb
|
|
|
Steve Webb signed off on waiver and plans. TLW
|
Routing - PLAN CHECK | 5/12/2009 | | 5/12/2009 | | PASS |
Sam Zahorka
|
|
|
Issued plans for Sam Z. TLW
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/12/2009 | | DONE |
Tim L. Woodard
|
|
|
|
Print Occupancy Form | | | 5/12/2009 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 5/7/2009 | | 5/8/2009 | | PEND |
Sam Zahorka
|
|
|
Pending others to pass. Routed to ESC.
|
Plan resubmittals received | | | 5/8/2009 | | |
Tisha Gallop
|
|
|
Receieved ESC appliation and waiver request letter; taken to Sam Z.
|
Routing - FIRE | 5/6/2009 | | 5/7/2009 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
Routing - PLAN CHECK | 4/23/2009 | | 5/6/2009 | | PEND |
Sam Zahorka
|
|
|
Pending others to pass. Routed to Fire
|
Plan resubmittals received | | | 4/30/2009 | | |
|
|
|
Received transmittal, plan review comments, response letter, copy of accessibility code (3 pgs.), plan review comments for fire, United Water flow sheet, and two copies of plan sheets G1.01, A2.21; taken to Sam Z.
|
Route to Impact Fee Review | 4/21/2009 | 4/24/2009 | 4/27/2009 | | PASS |
Cindy M. Gould
|
|
|
Fees applied to the addition on 1 unit < 800 sq ft
|
Routing - FIRE | 4/21/2009 | 4/21/2009 | 4/23/2009 | | FAIL |
Scott Arellano
|
|
|
Faxed and emailed resubmittal items to architect.
|
1st review completed | | | 4/23/2009 | | FAIL |
|
|
|
Failed ESC, Plan Check, Fire
|
Routing - Erosion and Sediment | 4/20/2009 | | 4/21/2009 | | FAIL |
Steven Webb
|
|
|
No ESC permit application, plan or plan waiver was included in the documents. ESC permit is required.
|
Routing - PUBLIC WORKS | 4/20/2009 | | 4/20/2009 | | PASS |
Beverly Hall
|
|
|
Suite 100 is 1st floor unit.
Suite 200 is 2nd floor unit.
|
Routing - PLUMBING | 4/17/2009 | | 4/20/2009 | | PASS |
Bill VanDegrift
|
|
|
|
Routing PW Sewer Rating | 4/20/2009 | | 4/20/2009 | | PASS |
Louise Waldorf
|
|
|
|
Routing - PLANNING | 4/17/2009 | | 4/17/2009 | | PASS |
Sarah Schafer
|
|
|
|
Routing - PLAN CHECK | 4/16/2009 | | 4/17/2009 | | FAIL |
Sam Zahorka
|
|
|
See Plan Review BLD09-00017.
|
Case Summary (BLD) | | | 4/17/2009 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/16/2009 | | |
Tisha Gallop
|
|
|
|
First Notice | | 5/6/2012 | | | |
|
|
|
|
Application received | | 4/16/2009 | | | |
Tisha Gallop
|
|
|
|