Permit Information
Permit NumberBLD09-00515
StatusFinaled
Name PERKINS CONSTRUCTION
Site Address 200 E GOWEN RD
Project NamePERKINS OFFICE & STORAGE UNITS
Customer Number 
ePlanReviewNo
Description
Perkins Office & Self Storage Units - Office - Building #1 - To relocate an existing 2,585 sq. ft., one story, log building; and to remodel for a new business office. The remodel will include remodeling restrooms into two compliant accessible restrooms, to demo some interior partitions and reconfigure rooms in the southwest corner of the building and to add a new direct vent fireplace at the lobby area. This permit also includes related site improvements. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 12/8/201012/8/2010 DONE
Third Notice 11/8/201011/24/2010 DONE
faxed
Third Notice 10/12/201010/25/2010 DONE
faxed
Second Notice 10/4/201010/7/2010 DONE
First Notice 9/17/20109/24/2010 DONE
PubWorks Occupancy Approval9/7/20109/7/20109/7/2010 DONE
DetailsTiffany Lowery
Permanent Occupancy UNPAID FEE  9/7/2010 DONE
DetailsBarbara Stitt
BLD-Final9/1/20109/1/20109/1/2010PPASS
DetailsJim Storey
James-PLease call at least 30 mins prior to inspection for access Phone #: ###-####
Zoning Approval9/1/20109/1/20109/1/2010 PASS
DetailsJosh Wilson
BLD-Aging Inspection8/23/20108/23/20108/23/2010 PART
DetailsJim Storey
on temp / bond in place with p$z
BLD-Aging Inspection6/22/20106/22/20106/22/2010 PASS
DetailsJim Storey
BLD-Conference6/22/20106/22/20106/22/2010PPART
DetailsJim Storey
on temp / bond in place with p$z
BLD-Aging Inspection4/21/20104/21/20104/21/2010 PASS
DetailsJim Storey
BLD-Conference4/21/20104/21/20104/21/2010APASS
DetailsJim Storey
p&z bond posted
BLD-Conference2/19/20102/19/20102/19/2010PPASS
DetailsJim Storey
james Phone #: ###-####
BLD-Energy code compliance2/16/20102/17/20102/17/2010ACANC
DetailsJim Storey
james Phone #: ###-####
FIRE-Final Inspection1/7/20101/7/20101/7/2010PPART
DetailsForrest France
Office okayed per activity notes.
BLD-Final12/10/200912/11/200912/11/2009APASS
DetailsJim Storey
james Phone #: ###-#### TEMP OCC OK
FIRE-Final Inspection12/9/200912/10/200912/10/2009PPASS
DetailsForrest France
Fire life safety inspection passed for the relocated office building only.
BLD-Final12/9/200912/10/200912/10/2009PNR
DetailsJim Storey
james Phone #: ###-####
Zoning Approval Temp12/10/200912/10/200912/10/2009 PASS
DetailsJosh Wilson
Landscaping bond for $41,195.00 has been submitted
BLD-Conference12/2/200912/2/200912/2/2009PPASS
DetailsJim Storey
James please call before going out Phone #: ###-####
BLD-Framing/Rough-in10/16/200910/19/200910/19/2009APASS
DetailsJim Storey
Chuck Phone #: ###-####
BLD-Foundation8/28/20098/28/20098/28/2009PPART
DetailsJim Storey
John Perkins Phone #: ###-#### ok pending 2500psi design.
BLD-Foundation8/26/20098/27/20098/28/2009PFAIL
DetailsJim Storey
Joe Phone #: ###-#### Please call before going out plan called out #5 bar #4 installed in wall. provide re-engineering if not changed,
BLD-Footing8/19/20098/20/20098/20/2009PPASS
DetailsDave Hannah
Joe-around noon if you can please Phone #: ###-####
Plan resubmittals received  7/20/2009  
DetailsTisha Gallop
Received deferred resubmittal: four copy of Site Grading; taken to Brian Murphy
Issue PAID IN FULL permit  7/7/2009 DONE
DetailsAlexandra L. DeYoung
Permit Ready to Issue  6/24/2009 DONE
Telephone call  6/24/2009 DONE
DetailsBarbara Stitt
Called Dan Pritchard and faxed him a breakdown of fees for individual buildings and explained to him that we need ACHD information///6-24-09 @ 10:00am BAS
Routing - PLAN CHECK6/19/2009 6/22/2009 PASS
DetailsJohn Menard
PLANS/APPL TAKEN TO FRONT DESK  6/22/2009 DONE
DetailsJohn Menard
Print Occupancy Form  6/22/2009 DONE
Plan assigned to (JCM)4/16/2009 6/22/2009 PASS
DetailsJohn Menard
6/22/2009 11:19:28 JCM - activity updated through activity BLDA022 from case BLD09-00515.
Routing - PUBLIC WORKS6/12/2009 6/19/2009 PASS
DetailsBeverly Hall
Routing - PLUMBING6/19/2009 6/19/2009 PASS
DetailsBill VanDegrift
per plans and 2003 upc
Plan resubmittals received  6/18/2009  
received 5 copies of Site Grading inserted by Angela from Engineering & Waste Solutions. Plans taken back by Brian M.
Routing PW Street Lights6/18/2009 6/18/2009 PASS
DetailsHank Alarcon
Routing PW Drainage6/12/2009 6/18/2009 PASS
Details
Plan resubmittals received  6/16/2009  
DetailsAlexandra L. DeYoung
Rec'd two copies of sheets EN-1; A-2.1; A-3.2; M-1; M-2; M-3; M-4; M-5; two copies of eng. calcs and two copies of response letter- inserted by architect and taken back to Brian Murphy
Routing - PLAN CHECK6/12/2009 6/12/2009 FAIL
DetailsJohn Menard
Plan resubmittals received  6/12/2009  
DetailsAlexandra L. DeYoung
Rec'd 4 copies of sheet 3 and 1 copy of geo report for Brain- taken to John M
Routing - PUBLIC WORKS6/3/2009 6/12/2009 FAIL
DetailsConnie Baumgartner
Routing PW Drainage6/4/2009 6/11/2009 FAIL
DetailsBrian Murphy
need geoteh and revision
Routing - PLAN CHECK6/2/2009 6/3/2009  
DetailsJohn Menard
Routing - FIRE5/28/2009 6/2/2009 PASS
DetailsScott Arellano
No changes.
Plan resubmittals requested  5/28/2009 DONE
DetailsJohn Menard
E-mailed the architect a letter requesting additional revisions. JCM
Routing - PLAN CHECK5/11/2009 5/28/2009 FAIL
DetailsJohn Menard
Plan resubmittals received  5/26/2009  
DetailsTisha Gallop
Received trasmittals to structural and fire, three copies of revised structural calcs, and two copies of ESC narrative, Storm Drain Report, response comments from engineering company, plan sheets G-1, EN-1, 1, 2, 3, 4, L1.1, L1.2, SD-2, A-1.1, A-1.2, A-1.3, A-2.1, A-3.1, A-3.2, A-3.3, A-3.4, S1.1, S1.2, S1.3, S1.4, S1.5, S1.6, S2.1, S2.2, S2.3, M-1, M-2, M-3, M-4, M-5, E3.1, E3.2, four copies of sheet SD-1; inserted by LEG and taken back to John Menard
Route to Impact Fee Review5/6/20095/11/20095/15/2009 PASS
DetailsCindy M. Gould
Routing - FIRE5/6/20095/6/20095/11/2009 PASS
DetailsScott Arellano
Attached IFC comments to plans
1st review completed  5/11/2009 FAIL
Failed Public Works, Plumbing, Plan Check
Plan resubmittals requested  5/6/2009 DONE
DetailsJohn Menard
E-mailed the architect a copy of the structural and nonstructural plan reviews requesting revisions. JCM
Routing - PLAN CHECK5/4/2009 5/6/2009 FAIL
DetailsJohn Menard
Routing Off Site - STRUCTURAL4/17/2009 5/4/2009 PASS
DetailsJohn Menard
Routing - PLANNING5/1/2009 5/4/2009 PASS
DetailsJosh Wilson
DRH08-00400 Josh W.
Routing - PLUMBING4/30/2009 5/1/2009 FAIL
DetailsBill VanDegrift
see bld09-00516 for comments
Routing - Erosion and Sediment4/29/2009 4/30/2009 PASS
DetailsSteven Webb
ESC plan approved with attached conditions. ESC09-00181
Routing - PUBLIC WORKS4/17/2009 4/29/2009 FAIL
DetailsConnie Baumgartner
Failed by lighting and drainage.
Routing PW Solid Waste4/28/2009 4/29/2009 PASS
DetailsPeter J. McCullough
Gates to enclosure must open 120 degrees minimum.
Routing PW Street Lights4/27/2009 4/28/2009 FAIL
DetailsHank Alarcon
Called and faxed Shawn A. Meador of E2 Electrical Engineering on 04/28/2009 & advised him of changes required on drawing sheets E3.1 & E3.2
Routing PW Sewer Rating4/28/2009 4/28/2009 PASS
DetailsConnie Baumgartner
Routing PW Sewer Design4/24/2009 4/27/2009 PASS
DetailsJon R. Gunnerson
SEWER TAP PERMIT REQUIRED, contact public works prior to tap of pressure line.
Routing PW Drainage4/20/2009 4/24/2009 FAIL
DetailsBrian Murphy
NEEDS REVISIONS BRIAN MURPHY ###-####
Telephone call  4/17/2009 DONE
DetailsTisha Gallop
called Action Couriers for pick up
Routing - PLANNING Land Div4/17/2009 4/17/2009 PASS
DetailsDave Abo
Application received 4/16/20094/16/2009 DONE
DetailsBarbara Stitt
Plans ACCEPTED BY PLAN TECH  4/16/2009 DONE
DetailsTisha Gallop
Recd Pcfee & Taken To Pln CK  4/16/2009 DONE
DetailsTisha Gallop
Pending Assignment by JCM4/16/2009 4/16/2009 BLDA
DetailsJohn Menard
4/16/2009 16:10:48 JCM - activity updated through activity BLDA166 from case BLD09-00515.