Third Notice | | 12/8/2010 | 12/8/2010 | | DONE |
|
|
|
|
Third Notice | | 11/8/2010 | 11/24/2010 | | DONE |
|
|
|
faxed
|
Third Notice | | 10/12/2010 | 10/25/2010 | | DONE |
|
|
|
faxed
|
Second Notice | | 10/4/2010 | 10/7/2010 | | DONE |
|
|
|
|
First Notice | | 9/17/2010 | 9/24/2010 | | DONE |
|
|
|
|
PubWorks Occupancy Approval | 9/7/2010 | 9/7/2010 | 9/7/2010 | | DONE |
Tiffany Lowery
|
|
|
|
Permanent Occupancy UNPAID FEE | | | 9/7/2010 | | DONE |
Barbara Stitt
|
|
|
|
BLD-Final | 9/1/2010 | 9/1/2010 | 9/1/2010 | P | PASS |
Jim Storey
|
|
|
James-PLease call at least 30 mins prior to inspection for access Phone #: ###-####
|
Zoning Approval | 9/1/2010 | 9/1/2010 | 9/1/2010 | | PASS |
Josh Wilson
|
|
|
|
BLD-Aging Inspection | 8/23/2010 | 8/23/2010 | 8/23/2010 | | PART |
Jim Storey
|
|
|
on temp / bond in place with p$z
|
BLD-Aging Inspection | 6/22/2010 | 6/22/2010 | 6/22/2010 | | PASS |
Jim Storey
|
|
|
|
BLD-Conference | 6/22/2010 | 6/22/2010 | 6/22/2010 | P | PART |
Jim Storey
|
|
|
on temp / bond in place with p$z
|
BLD-Aging Inspection | 4/21/2010 | 4/21/2010 | 4/21/2010 | | PASS |
Jim Storey
|
|
|
|
BLD-Conference | 4/21/2010 | 4/21/2010 | 4/21/2010 | A | PASS |
Jim Storey
|
|
|
p&z bond posted
|
BLD-Conference | 2/19/2010 | 2/19/2010 | 2/19/2010 | P | PASS |
Jim Storey
|
|
|
james Phone #: ###-####
|
BLD-Energy code compliance | 2/16/2010 | 2/17/2010 | 2/17/2010 | A | CANC |
Jim Storey
|
|
|
james Phone #: ###-####
|
FIRE-Final Inspection | 1/7/2010 | 1/7/2010 | 1/7/2010 | P | PART |
Forrest France
|
|
|
Office okayed per activity notes.
|
BLD-Final | 12/10/2009 | 12/11/2009 | 12/11/2009 | A | PASS |
Jim Storey
|
|
|
james Phone #: ###-#### TEMP OCC OK
|
FIRE-Final Inspection | 12/9/2009 | 12/10/2009 | 12/10/2009 | P | PASS |
Forrest France
|
|
|
Fire life safety inspection passed for the relocated office building only.
|
BLD-Final | 12/9/2009 | 12/10/2009 | 12/10/2009 | P | NR |
Jim Storey
|
|
|
james Phone #: ###-####
|
Zoning Approval Temp | 12/10/2009 | 12/10/2009 | 12/10/2009 | | PASS |
Josh Wilson
|
|
|
Landscaping bond for $41,195.00 has been submitted
|
BLD-Conference | 12/2/2009 | 12/2/2009 | 12/2/2009 | P | PASS |
Jim Storey
|
|
|
James please call before going out Phone #: ###-####
|
BLD-Framing/Rough-in | 10/16/2009 | 10/19/2009 | 10/19/2009 | A | PASS |
Jim Storey
|
|
|
Chuck Phone #: ###-####
|
BLD-Foundation | 8/28/2009 | 8/28/2009 | 8/28/2009 | P | PART |
Jim Storey
|
|
|
John Perkins Phone #: ###-#### ok pending 2500psi design.
|
BLD-Foundation | 8/26/2009 | 8/27/2009 | 8/28/2009 | P | FAIL |
Jim Storey
|
|
|
Joe Phone #: ###-#### Please call before going out plan called out #5 bar #4 installed in wall. provide re-engineering if not changed,
|
BLD-Footing | 8/19/2009 | 8/20/2009 | 8/20/2009 | P | PASS |
Dave Hannah
|
|
|
Joe-around noon if you can please Phone #: ###-####
|
Plan resubmittals received | | | 7/20/2009 | | |
Tisha Gallop
|
|
|
Received deferred resubmittal: four copy of Site Grading; taken to Brian Murphy
|
Issue PAID IN FULL permit | | | 7/7/2009 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Permit Ready to Issue | | | 6/24/2009 | | DONE |
|
|
|
|
Telephone call | | | 6/24/2009 | | DONE |
Barbara Stitt
|
|
|
Called Dan Pritchard and faxed him a breakdown of fees for individual buildings and explained to him that we need ACHD information///6-24-09 @ 10:00am BAS
|
Routing - PLAN CHECK | 6/19/2009 | | 6/22/2009 | | PASS |
John Menard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/22/2009 | | DONE |
John Menard
|
|
|
|
Print Occupancy Form | | | 6/22/2009 | | DONE |
|
|
|
|
Plan assigned to (JCM) | 4/16/2009 | | 6/22/2009 | | PASS |
John Menard
|
|
|
6/22/2009 11:19:28 JCM - activity updated through activity BLDA022 from case BLD09-00515.
|
Routing - PUBLIC WORKS | 6/12/2009 | | 6/19/2009 | | PASS |
Beverly Hall
|
|
|
|
Routing - PLUMBING | 6/19/2009 | | 6/19/2009 | | PASS |
Bill VanDegrift
|
|
|
per plans and 2003 upc
|
Plan resubmittals received | | | 6/18/2009 | | |
|
|
|
received 5 copies of Site Grading inserted by Angela from Engineering & Waste Solutions. Plans taken back by Brian M.
|
Routing PW Street Lights | 6/18/2009 | | 6/18/2009 | | PASS |
Hank Alarcon
|
|
|
|
Routing PW Drainage | 6/12/2009 | | 6/18/2009 | | PASS |
|
|
|
|
Plan resubmittals received | | | 6/16/2009 | | |
Alexandra L. DeYoung
|
|
|
Rec'd two copies of sheets EN-1; A-2.1; A-3.2; M-1; M-2; M-3; M-4; M-5; two copies of eng. calcs and two copies of response letter- inserted by architect and taken back to Brian Murphy
|
Routing - PLAN CHECK | 6/12/2009 | | 6/12/2009 | | FAIL |
John Menard
|
|
|
|
Plan resubmittals received | | | 6/12/2009 | | |
Alexandra L. DeYoung
|
|
|
Rec'd 4 copies of sheet 3 and 1 copy of geo report for Brain- taken to John M
|
Routing - PUBLIC WORKS | 6/3/2009 | | 6/12/2009 | | FAIL |
Connie Baumgartner
|
|
|
|
Routing PW Drainage | 6/4/2009 | | 6/11/2009 | | FAIL |
Brian Murphy
|
|
|
need geoteh and revision
|
Routing - PLAN CHECK | 6/2/2009 | | 6/3/2009 | | |
John Menard
|
|
|
|
Routing - FIRE | 5/28/2009 | | 6/2/2009 | | PASS |
Scott Arellano
|
|
|
No changes.
|
Plan resubmittals requested | | | 5/28/2009 | | DONE |
John Menard
|
|
|
E-mailed the architect a letter requesting additional revisions. JCM
|
Routing - PLAN CHECK | 5/11/2009 | | 5/28/2009 | | FAIL |
John Menard
|
|
|
|
Plan resubmittals received | | | 5/26/2009 | | |
Tisha Gallop
|
|
|
Received trasmittals to structural and fire, three copies of revised structural calcs, and two copies of ESC narrative, Storm Drain Report, response comments from engineering company, plan sheets G-1, EN-1, 1, 2, 3, 4, L1.1, L1.2, SD-2, A-1.1, A-1.2, A-1.3, A-2.1, A-3.1, A-3.2, A-3.3, A-3.4, S1.1, S1.2, S1.3, S1.4, S1.5, S1.6, S2.1, S2.2, S2.3, M-1, M-2, M-3, M-4, M-5, E3.1, E3.2, four copies of sheet SD-1; inserted by LEG and taken back to John Menard
|
Route to Impact Fee Review | 5/6/2009 | 5/11/2009 | 5/15/2009 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - FIRE | 5/6/2009 | 5/6/2009 | 5/11/2009 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
1st review completed | | | 5/11/2009 | | FAIL |
|
|
|
Failed Public Works, Plumbing, Plan Check
|
Plan resubmittals requested | | | 5/6/2009 | | DONE |
John Menard
|
|
|
E-mailed the architect a copy of the structural and nonstructural plan reviews requesting revisions. JCM
|
Routing - PLAN CHECK | 5/4/2009 | | 5/6/2009 | | FAIL |
John Menard
|
|
|
|
Routing Off Site - STRUCTURAL | 4/17/2009 | | 5/4/2009 | | PASS |
John Menard
|
|
|
|
Routing - PLANNING | 5/1/2009 | | 5/4/2009 | | PASS |
Josh Wilson
|
|
|
DRH08-00400 Josh W.
|
Routing - PLUMBING | 4/30/2009 | | 5/1/2009 | | FAIL |
Bill VanDegrift
|
|
|
see bld09-00516 for comments
|
Routing - Erosion and Sediment | 4/29/2009 | | 4/30/2009 | | PASS |
Steven Webb
|
|
|
ESC plan approved with attached conditions. ESC09-00181
|
Routing - PUBLIC WORKS | 4/17/2009 | | 4/29/2009 | | FAIL |
Connie Baumgartner
|
|
|
Failed by lighting and drainage.
|
Routing PW Solid Waste | 4/28/2009 | | 4/29/2009 | | PASS |
Peter J. McCullough
|
|
|
Gates to enclosure must open 120 degrees minimum.
|
Routing PW Street Lights | 4/27/2009 | | 4/28/2009 | | FAIL |
Hank Alarcon
|
|
|
Called and faxed Shawn A. Meador of E2 Electrical Engineering on 04/28/2009 & advised him of changes required on drawing sheets E3.1 & E3.2
|
Routing PW Sewer Rating | 4/28/2009 | | 4/28/2009 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Sewer Design | 4/24/2009 | | 4/27/2009 | | PASS |
Jon R. Gunnerson
|
|
|
SEWER TAP PERMIT REQUIRED, contact public works prior to tap of pressure line.
|
Routing PW Drainage | 4/20/2009 | | 4/24/2009 | | FAIL |
Brian Murphy
|
|
|
NEEDS REVISIONS BRIAN MURPHY ###-####
|
Telephone call | | | 4/17/2009 | | DONE |
Tisha Gallop
|
|
|
called Action Couriers for pick up
|
Routing - PLANNING Land Div | 4/17/2009 | | 4/17/2009 | | PASS |
Dave Abo
|
|
|
|
Application received | | 4/16/2009 | 4/16/2009 | | DONE |
Barbara Stitt
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/16/2009 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/16/2009 | | DONE |
Tisha Gallop
|
|
|
|
Pending Assignment by JCM | 4/16/2009 | | 4/16/2009 | | BLDA |
John Menard
|
|
|
4/16/2009 16:10:48 JCM - activity updated through activity BLDA166 from case BLD09-00515.
|