Permanent Occupancy | | | 11/14/2013 | | DONE |
Barbara Stitt
|
|
|
|
Permanent Occupancy | | | 11/4/2013 | | DONE |
Tisha Gallop
|
|
|
Print new cert of occ with address correction. See scanned address form in documents. E-mailed to Linda Hines at Grace @ Englefiled Green
|
Case Summary (BLD) | | | 8/22/2012 | | |
|
|
|
|
FIRE-Final Inspection | 7/20/2010 | 7/21/2010 | 7/21/2010 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
Permanent Occupancy | | | 7/20/2010 | | DONE |
Jason Blais
|
|
|
|
Plan resubmittals received | | | 7/20/2010 | | DONE |
Jason Blais
|
|
|
Deferred submittal item on carport engineering received. Sent inspector out to verify carport structures are constructed in accordance with engineered design and calculations. Acceptable per inspection. Inspector previously verified footings during construction. New final Certificate of Value also submitted. Scope of permit will be changed regarding the carport structures. A new CO will be issued with changed scope of work.
|
First Notice | | 6/24/2010 | 7/16/2010 | | DONE |
|
|
|
|
Permanent Occupancy UNPAID FEE | | | 6/14/2010 | | DONE |
|
|
|
|
BLD-Conference | 6/11/2010 | 6/11/2010 | 6/11/2010 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Final | 6/11/2010 | 6/11/2010 | 6/11/2010 | P | PASS |
Tom Arcoraci
|
|
|
temp glass ok
|
Zoning Approval | 6/11/2010 | 6/11/2010 | 6/11/2010 | | PASS |
Andrea Tuning
|
|
|
The trash enlosures and the screening is now complete. Final occupancy may be issued at any time.
|
PubWorks Occupancy Approval | 6/7/2010 | 6/7/2010 | 6/7/2010 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Final | 6/1/2010 | 6/2/2010 | 6/2/2010 | A | PART |
Tom Arcoraci
|
|
|
harvey Phone #: ###-#### will use approved film for temp glass issues
|
Zoning Approval Temp | 6/2/2010 | 6/2/2010 | 6/2/2010 | | DONE |
Andrea Tuning
|
|
|
Staff has granted the applicant a 30 day temporary occupancy. Final occupancy was not granted due to the fact that the applicant has not completed the trash enclosures or the landscape screening of these enclosures. Once the trash enclosures and the screening is installed, staff will sign the permanent occupancy for the building.
|
Temporary Occupancy UNPAID FEE | | | 6/2/2010 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 6/2/2010 | | DONE |
|
|
|
|
BLD-Final | 5/28/2010 | 6/1/2010 | 6/1/2010 | P | NR |
Dave Hannah
|
|
|
Phone #: ###-####
|
FIRE-Final Inspection | 5/28/2010 | 6/1/2010 | 6/1/2010 | A | FAIL |
Troy Cobbley
|
|
|
Provide test report for the kitchen hood and the fire sprinkler permit needs to be finaled. Alarm permit finaled today. Occupant load signs for the assembly areas are temporary until the permanent ones are installed.
|
FIRE-Final Inspection | 5/27/2010 | 5/28/2010 | 5/28/2010 | A | FAIL |
Troy Cobbley
|
|
|
The only item for life safety that was inspected today were the exit signs and emergency lighting. One exit sign needs to be added as shown on the city approved plans. Herb is calling in for a re-inspection for Tuesday.
|
FIRE-Conference | 5/26/2010 | 5/27/2010 | 5/27/2010 | A | DONE |
Troy Cobbley
|
|
|
Trip test on smoke detectors--Matt Phone #: ###-####
|
FIRE-Final Inspection | 5/26/2010 | 5/26/2010 | 5/27/2010 | P | CANC |
Troy Cobbley
|
|
|
Wrong inspection type called in. Herb needed fire alarm inspection.
|
BLD-Conference | 5/24/2010 | 5/25/2010 | 5/25/2010 | P | PART |
Tom Arcoraci
|
|
|
|
BLD-Conference | 5/21/2010 | 5/24/2010 | 5/24/2010 | A | PASS |
Tom Arcoraci
|
|
|
|
BLD-Conference | 5/20/2010 | 5/21/2010 | 5/21/2010 | A | PASS |
Tom Arcoraci
|
|
|
|
BLD-Conference | 5/19/2010 | 5/20/2010 | 5/20/2010 | A | PART |
Mike Jordan
|
|
|
room in smoke compartment 4. needsz safety glazing.
|
BLD-Conference | 5/19/2010 | 5/19/2010 | 5/19/2010 | P | PART |
Tom Arcoraci
|
|
|
tempered glass required
|
BLD-Wall cover | 3/25/2010 | 3/26/2010 | 3/26/2010 | A | PASS |
Tom Arcoraci
|
|
|
|
BLD-Wall cover | 3/17/2010 | 3/24/2010 | 3/24/2010 | A | PASS |
Tom Arcoraci
|
|
|
|
BLD-Wall cover | 3/12/2010 | 3/17/2010 | 3/17/2010 | A | PASS |
Tom Arcoraci
|
|
|
|
FIRE-Conference | 3/12/2010 | 3/12/2010 | 3/12/2010 | P | DONE |
Troy Cobbley
|
|
|
Tom, building inspector, and I spoke to Herd about fire blocking and fire sprinkler requirements at the two fireplace locations and the columns. Also the the entire south third of the building has been covered with out the sprinkler piping having been inspected. I notified Herd of IFC requirements but stated that for this one specific happening I would not require the ceiling to be removed but the insulation would be required to be removed from over the piping for an inspection. The insulation will then need to be reinstalled for a secondary inspection. Any areas that I deam accessible will have the ceilings removed for sprinkler piping inspection. I notified Scott of the situation.
|
BLD-Framing/Rough-in | 3/12/2010 | 3/12/2010 | 3/12/2010 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Framing/Rough-in | 3/10/2010 | 3/11/2010 | 3/11/2010 | P | FAIL |
Tom Arcoraci
|
|
|
herb Phone #: ###-####
|
BLD-Wall cover | 3/10/2010 | 3/11/2010 | 3/11/2010 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Other | 2/25/2010 | 3/4/2010 | 3/4/2010 | A | PART |
Tom Arcoraci
|
|
|
work ij progress ok
|
BLD-Wall cover | 2/22/2010 | 2/25/2010 | 2/25/2010 | A | PASS |
Tom Arcoraci
|
|
|
|
BLD-Conference | 2/17/2010 | 2/24/2010 | 2/24/2010 | A | PASS |
Tom Arcoraci
|
|
|
|
BLD-Wall cover | 2/19/2010 | 2/22/2010 | 2/22/2010 | A | PART |
Tom Arcoraci
|
|
|
Herb Phone #: ###-#### wip
|
BLD-Conference | 2/10/2010 | 2/17/2010 | 2/17/2010 | A | PASS |
Tom Arcoraci
|
|
|
wip ok
|
BLD-Wall cover | 2/11/2010 | 2/12/2010 | 2/12/2010 | A | PASS |
Tom Arcoraci
|
|
|
Herb Phone #: ###-####
|
BLD-Other | 2/4/2010 | 2/10/2010 | 2/10/2010 | A | PASS |
Tom Arcoraci
|
|
|
|
BLD-Conference | 1/29/2010 | 2/3/2010 | 2/3/2010 | A | PASS |
Tom Arcoraci
|
|
|
|
BLD-Wall cover | 1/27/2010 | 1/29/2010 | 1/29/2010 | A | PART |
Tom Arcoraci
|
|
|
Herb Phone #: ###-#### wip ok
|
BLD-Framing/Rough-in | 1/22/2010 | 1/25/2010 | 1/25/2010 | A | PASS |
Tom Arcoraci
|
|
|
Curt-Cover inspection please Phone #: ###-####
|
FIRE-Conference | 1/20/2010 | 1/20/2010 | 1/20/2010 | P | DONE |
Troy Cobbley
|
|
|
The stop work order that had been previously posted for the fire alarm installation is being lifted due to the fire alarm plans being issued.
|
BLD-Wall cover | 1/20/2010 | 1/20/2010 | 1/20/2010 | A | FAIL |
Tom Arcoraci
|
|
|
fire stopping incomplete
|
BLD-Conference | 1/11/2010 | 1/19/2010 | 1/19/2010 | A | PASS |
Tom Arcoraci
|
|
|
wip ok
|
BLD-Framing/Rough-in | 1/8/2010 | 1/11/2010 | 1/11/2010 | P | PART |
Tom Arcoraci
|
|
|
Herb-Nailing inspection please Phone #: ###-#### wip ok
|
BLD-Other | 1/7/2010 | 1/7/2010 | 1/7/2010 | A | PASS |
Tom Arcoraci
|
|
|
discussed fire walls
|
BLD-Conference | 12/31/2009 | 1/6/2010 | 1/6/2010 | A | PASS |
Tom Arcoraci
|
|
|
|
Meeting | | | 1/6/2010 | | DONE |
|
|
|
Troy Cobbley issued a Stop work order due to fire alarm devices and wiring being installed without an approved permit. Work order is for further installation of fire alarm and installation of sheetrock that will cover wiring and/or backboxes. I gave the job superintendent permission to insulate the exterior walls.
|
BLD-Conference | 12/30/2009 | 12/31/2009 | 12/31/2009 | A | PASS |
Tom Arcoraci
|
|
|
|
BLD-Other | 12/23/2009 | 12/30/2009 | 12/30/2009 | A | PASS |
Tom Arcoraci
|
|
|
|
BLD-Wall cover | 12/17/2009 | 12/23/2009 | 12/23/2009 | A | PART |
Tom Arcoraci
|
|
|
wip ok
|
BLD-Conference | 12/17/2009 | 12/18/2009 | 12/18/2009 | P | PASS |
Tom Arcoraci
|
|
|
can lights ok
|
BLD-Other | 12/10/2009 | 12/17/2009 | 12/17/2009 | A | PASS |
Tom Arcoraci
|
|
|
wip ok
|
BLD-Wall cover | 12/4/2009 | 12/9/2009 | 12/10/2009 | P | PASS |
Tom Arcoraci
|
|
|
wip
|
BLD-Conference | 12/3/2009 | 12/4/2009 | 12/4/2009 | A | PASS |
Tom Arcoraci
|
|
|
wip ok discussed acces reach
|
BLD-Wall cover | 12/2/2009 | 12/3/2009 | 12/3/2009 | A | PASS |
Tom Arcoraci
|
|
|
wip
|
BLD-Wall cover | 12/1/2009 | 12/2/2009 | 12/2/2009 | A | PASS |
Tom Arcoraci
|
|
|
wip
|
BLD-Conference | 11/30/2009 | 12/1/2009 | 12/1/2009 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Wall cover | 11/19/2009 | 11/24/2009 | 11/24/2009 | A | PASS |
Tom Arcoraci
|
|
|
wip ok
|
BLD-Wall cover | 11/17/2009 | 11/24/2009 | 11/23/2009 | A | CANC |
Tom Arcoraci
|
|
|
|
BLD-Conference | 11/16/2009 | 11/17/2009 | 11/17/2009 | A | PASS |
Tom Arcoraci
|
|
|
|
BLD-Conference | 11/16/2009 | 11/16/2009 | 11/16/2009 | P | PART |
Tom Arcoraci
|
|
|
Herb Phone #: ###-####
|
BLD-Foundation | 9/30/2009 | 9/30/2009 | 9/30/2009 | A | PASS |
Tom Arcoraci
|
|
|
wip ok
|
BLD-Foundation | 9/29/2009 | 9/29/2009 | 9/29/2009 | P | PASS |
Tom Arcoraci
|
|
|
herb Phone #: ###-####
|
BLD-Footing | 9/24/2009 | 9/25/2009 | 9/25/2009 | P | PART |
Tom Arcoraci
|
|
|
wip ok
|
BLD-Footing | 9/23/2009 | 9/24/2009 | 9/24/2009 | A | PASS |
Tom Arcoraci
|
|
|
Herb-1:00 pouring so late am if possible please Phone #: ###-####
|
BLD-Footing | 9/21/2009 | 9/22/2009 | 9/22/2009 | P | PASS |
Tom Arcoraci
|
|
|
herb Phone #: ###-#### wip ok
|
Issue PAID IN FULL permit | | | 9/8/2009 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/26/2009 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/26/2009 | | DONE |
|
|
|
|
Telephone call | | | 8/26/2009 | | DONE |
|
|
|
called left message for Doug T. permit ready and fee given also need ACHD
|
Routing Off Site - STRUCTURAL | 8/20/2009 | | 8/25/2009 | | PASS |
Dan Stuart
|
|
|
Copy of engineering & architectural response e-mailed to Steve Call to review for his meeting with Mr. Cox & Mr. Tamura at 10 am on Monday 8/24/09.
8/25/09 -Inserted plan sheets A2.3, A2.4 & A4.2. Discussed on phone the use of the Simpson MSTC40 as a tension strap for the drag strut truss' indicated on plan Sheet A2.4 with Steve Call. Strap was approfed. Received copy of final structural engineering plan review report from Steve Call.
|
Routing - PLAN CHECK | 8/24/2009 | | 8/25/2009 | | PASS |
Dan Stuart
|
|
|
Inserted new resubmittal sheets into plans. Reviwed structural plan changes with Steve Call. No further resubmittals required.
|
Plan resubmittals received | | | 8/25/2009 | | |
Dan Stuart
|
|
|
Rec'd one copy of transmittal letter and three copies of sheets A2.3; A2.4; & A4.2- taken to Dan S
|
Telephone call | | | 8/25/2009 | | DONE |
|
|
|
Called Steve Call, Structural Engineer reviewing structural plans. Reviewed use of Simpson MSTC40 strap as tension drag strut for truss'. Okay.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/25/2009 | | PASS |
|
|
|
|
Plan assigned to (DRS) | 4/23/2009 | | 8/25/2009 | | PASS |
Dan Stuart
|
|
|
8/25/2009 16:15:47 DRS - activity updated through activity BLDA022 from case BLD09-00557.
|
Telephone call | | | 8/24/2009 | | DONE |
|
|
|
Call from Steve Call, engineer reviewing structural plans reporting on meeting with Mr. Cox & Mr. Tamura. I will be receiving a final report & resubmittals.
|
Telephone call | | | 8/24/2009 | | DONE |
|
|
|
Called Marla Carson to ask that she review her plan details for headers on Sheet A2.4, columns on A2.3 and the engineering calcs for the drag struts on sheet A4.2, Detail 6, to make sure same information called for in engineering design sheets is reflected on the plans.
|
Routing - Design Review | 8/24/2009 | | 8/24/2009 | | PASS |
Andrea Tuning
|
|
|
Staff has all of the items that are required. ANT
|
Routing - PLAN CHECK | 8/18/2009 | | 8/24/2009 | | FAIL |
Dan Stuart
|
|
|
Routed plans back to planning to have required sheets initialed by staff.
|
Routing Off Site - STRUCTURAL | 8/20/2009 | | 8/20/2009 | | FAIL |
Dan Stuart
|
|
|
Talked with Steve Call concerning engineering issues and his discussion with Mr. Cox. A meeting has been set up for 9/24/09 at 10 am in Mr. Calls office to review engineering items. I am e-mailing a copy of the plan review response I received to Steve Call to make sure we both had the same information.
We discussed a separate foundation permit possibility and it was determined additional design information was needed. Steve will call Mr. Cox to review foundation data in hope of have plan changes for foundation for Monday's meeting.
|
Telephone call | | | 8/20/2009 | | DONE |
|
|
|
Called Mr. Call to discuss remaining structural considerations to do with the foundation. Mr. Tamura had called to see if permits could be issued. Mr. Call said he had talked with Mr. Cox yesterday and that a meeting had been set up for Monday, 9/24/09, at 10 am at Mr. Call's office to review the structural items.
There are some foundation issues that need resloved before Mr. Call would okay the foundation design for permit. Mr. Call will call Mr. Cox and discuss the foundation issue to provide time for structural modification design data to be brought to the Monday meeting to see if the foundation can be approved.
|
Telephone call | | | 8/20/2009 | | DONE |
|
|
|
Dough Tamura, architect, called to discuss possibility of getting a building permit while the remaining structural concerns are addressed. I told him I would discuss the matter with Jason Blais and Mr. Call and get back with him. After discussion with Jason & Steve, I sent an e-mail to all parties concerned outlining the process for Mr. Tamura to obtain a seprate foundation permit.
|
Routing Off Site - STRUCTURAL | 8/18/2009 | | 8/19/2009 | | FAIL |
Dan Stuart
|
|
|
Called Steve Call to discuss plan resubmittals of 8/19/09 and to tell him I would be routing him plans to review. Steve said he had received a copy of the resubmittals from the architect directly. We discussed the drag strut detail, drag truss allighments, loads and strap design, diaphragm cord connections, etc. that had not bee adequately addressed for code compliance. Mr. Call would call Mr. Cox to discuss issues.
|
Telephone call | | | 8/19/2009 | | DONE |
|
|
|
Talked with steve Call concerning Mr. Cox structural engineering design resubmittals and details on plan resubmittals of 9/18/09. He had received a copy of the resubmittals direct from Doug Tamura at the same time copies were submitted to PDS plan review. We talked about the drag struct design, drag truss alighnment with walls, diaphragm cord connections, etc. remaining to be addressed to show code compliance. This resubmittal also failed. Mr. Call was going to call Mr. Cox to discuss the items.
|
Plan resubmittals received | | | 8/18/2009 | | |
Tisha Gallop
|
|
|
received transmittal, repsonse comments, and three copies of structural calculations, and sheets A0.2, A0.3, A2.0, A2.1, A2.2, A2.3, A2.4, A3.0, A4.1, A4.2, A4.3, A5.0, A5.1, A9.1, A9.2, A10.0, M1.1, M1.2, M5.2, P1.1, P1.2, E2.0, E3.0, E4,0, E5.0, E6.0, E7.0; inserted by arch. rep. and taken back to Dan Stuart
|
Routing - PLAN CHECK | 8/7/2009 | | 8/13/2009 | | FAIL |
Dan Stuart
|
|
|
Structural review and architectural details incomplete. Copy of engineering report & my plan review report e-mailed to Marla Carson & Doug Tamura.
|
Routing - PLAN CHECK | 8/6/2009 | | 8/13/2009 | | FAIL |
Dan Stuart
|
|
|
Resubmittals required.
|
Routing Off Site - STRUCTURAL | 7/29/2009 | | 8/11/2009 | | FAIL |
Dan Stuart
|
|
|
Engineering Calc changes and architectural plan submittals.
8/11/09 - List of engineering design data and details needing to be addressed e-mailed to Marla Carson and Doug Tamura.
|
Plan resubmittals requested | | | 8/7/2009 | | DONE |
|
|
|
E-mail to doug Tamura and Marla Carson.
|
Routing - Design Review | 8/6/2009 | | 8/6/2009 | | PASS |
Andrea Tuning
|
|
|
The plat has been recorded with a plat note allowing cross access, the fire department has released the non-build agreement and the site and landscape plans have been modified to provide 18 and 20 foor planter islands.
|
Route to Impact Fee Review | 7/31/2009 | 8/5/2009 | 8/4/2009 | | PASS |
Cindy M. Gould
|
|
|
|
Plan resubmittals received | | | 8/4/2009 | | |
Dan Stuart
|
|
|
Rec'd copies of the legal lot- given to Dan S
|
Routing - PLANNING Land Div | 8/4/2009 | | 8/4/2009 | | PASS |
Todd Tucker
|
|
|
Letter of Satisfaction from the Fire Department has been recorded.
|
Plan resubmittals received | | | 8/4/2009 | | DONE |
|
|
|
received 2 sets of sheets A1.0,A1.1 inserted by Marla with Doug Tarmura Arch and take back to Dan S.
|
Routing - PLAN CHECK | 7/31/2009 | | 8/4/2009 | | FAIL |
Dan Stuart
|
|
|
Routing plans back to Planning Land Div as requested by TRT.
|
Routing - FIRE | 7/28/2009 | 7/28/2009 | 7/31/2009 | | PASS |
Scott Arellano
|
|
|
Attached updated IFC comments to plans
|
FIRE DEPT. NON-BUILD | 11/2/2007 | 7/27/2009 | 7/29/2009 | | PASS |
Dan Stuart
|
|
|
Non-Building agreement recorded 11/2/07. 7/27/09 - Copy of non build provided by Planning Land Div with not that conditions of agreement are not satisfied as of this date.
7/29/09 - Copy of notorized SATISFACTION OF NON-BUILDING AGREEMENT provided.
|
Telephone call | | | 7/29/2009 | | DONE |
|
|
|
Call to Doug Tasmura - Will send copy of non-build agreement removal approval from Mark Senteno, two copies of recorded plat site plan with legend and property lines; then waiting for response from structural engineer, planning, plann-land div sign off and plan check. Hopefully by the end of next week - 8/7/09 to be ready.
|
Routing - PLAN CHECK | 7/20/2009 | | 7/29/2009 | | FAIL |
Dan Stuart
|
|
|
Routing to fire then Planning.
|
Routing - PLANNING Land Div | 7/27/2009 | | 7/27/2009 | | FAIL |
Todd Tucker
|
|
|
Non-build Agreement #107149467. Must get Satisfaction Memo.
|
Plan resubmittals received | | | 7/22/2009 | | |
Tisha Gallop
|
|
|
received memo and four copies of sheets A1.1, A1.2; inserted by arch. rep. and taken back to Dan Stuart
|
Routing - PLANNING | 7/20/2009 | | 7/20/2009 | | FAIL |
Andrea Tuning
|
|
|
The applicant will need a cross access acgreement, meet the conditions of the subdivision to remove the non-build agreement, and construct the landscape planters to be a minimum of 20-feet in length. ANT 7-20-09
Sue H & Andrea T
|
Routing - PUBLIC WORKS | 7/16/2009 | | 7/20/2009 | | PASS |
Beverly Hall
|
|
|
|
Routing PW Solid Waste | | | 7/17/2009 | | PASS |
Peter J. McCullough
|
|
|
|
Routing - PLANNING Land Div | 7/15/2009 | | 7/16/2009 | | FAIL |
Todd Tucker
|
|
|
Final Plat has still not been recorded. Subdivision Ordinance Section 9-20-08.A.2 states "No building permit for the construction of any new structure upon property within a proposed subdivison plat shall be issued until the subdivison plat has been recorded pursuant to the requirements of this Chapter."
|
Plan resubmittals received | | | 7/8/2009 | | DONE |
|
|
|
Routed to
|
Route to Impact Fee Review | 5/28/2009 | 6/2/2009 | 6/2/2009 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - FIRE | 5/28/2009 | 5/28/2009 | 6/1/2009 | | FAIL |
Scott Arellano
|
|
|
Faxed and emailed resubmittal items to architect.
|
1st review completed | | | 6/1/2009 | | FAIL |
|
|
|
Failed Public Works, Structural, Plumbing, Planning, Plan Check, Fire
|
Plan resubmittals requested | | | 5/28/2009 | | DONE |
|
|
|
Plan review list e-mailed to Doug Tamura.
|
Routing - PLAN CHECK | 5/8/2009 | | 5/28/2009 | | FAIL |
Dan Stuart
|
|
|
Resubmittals required. Copy of plan review to doug tamura. Plans to fire code analyst.
|
Telephone call | | | 5/14/2009 | | DONE |
|
|
|
Call from Marla Carson with request to allow project structural engineer, Harold Cox, contact our Contract structural engineer directly to discuss structural plan review. I will contact our structural engineer to see if this is ok by them.
|
Telephone call | | | 5/14/2009 | | DONE |
|
|
|
Talked with contracted Structural Engineer, Steve Call who said it would be okay to give his number to the architect and the engineer for direct correspondence.
|
Telephone call | | | 5/14/2009 | | DONE |
|
|
|
Called Marla Carson and left voice message that Harold cox could call Steve Call direct and left a phone number. Steve woul be available at his office on Friday 5/15/09.
|
Routing Off Site - STRUCTURAL | 4/24/2009 | | 5/11/2009 | | FAIL |
Dan Stuart
|
|
|
Called Action Couriers for pick up
5/11/09 - Received notification from Boise city Contract Structural Engineer that the structural review had failed. copy of report e-mailed to Marla Carson W/ Doug Tamura Architect to route to project engineer.
|
Routing - PLANNING | 5/6/2009 | | 5/8/2009 | | FAIL |
Darla L Downs
|
|
|
Cup07-126 Sue C. DRH07-451 Andrea T.
Needs cross access agreement between the lots. Sue
The applicant will need a cross access acgreement, meet the conditions of the subdivision to remove the non-build agreement, and construct the landscape planters to be a minimum of 20-feet in length. ANT
|
Routing - PLUMBING | 4/30/2009 | | 5/6/2009 | | PASS |
Bill VanDegrift
|
|
|
all interior rain water piping to be schedule 40. 2" min. waste below grade. Max. 120 deg. hot water to kitchen hand sinks. additional cross connection protection may be required.
|
Plan resubmittals received | | | 5/6/2009 | | DONE |
|
|
|
received 4 copies of sheet A1.2 taken to Dan S.
|
Routing PW Sewer Rating | 4/30/2009 | | 4/30/2009 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Solid Waste | 4/30/2009 | | 4/30/2009 | | FAIL |
Peter J. McCullough
|
|
|
Minimum 18' trash enclosure gate opening and gates must open 120 degrees minimum. Peter McCullough ###-####
|
Routing PW Street Lights | 4/29/2009 | | 4/30/2009 | | PASS |
Hank Alarcon
|
|
|
|
Routing PW Drainage | 4/30/2009 | | 4/30/2009 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Environmental | 4/30/2009 | | 4/30/2009 | | PASS |
Walt Baumgartner
|
|
|
OK in the WBSD, kitchen hooked to 1500 gal GI shown, standard design,
|
Routing - Erosion and Sediment | 4/30/2009 | | 4/30/2009 | | PASS |
Steven Webb
|
|
|
ESC plan approved with attached conditions. ESC09-00203
|
Routing - PUBLIC WORKS | 4/24/2009 | | 4/30/2009 | | FAIL |
Connie Baumgartner
|
|
|
|
Routing PW Drainage | 4/24/2009 | | 4/28/2009 | | FAIL |
Brian Murphy
|
|
|
monitoring well in bed BRIAN MURPHY ###-####
|
Routing - PLANNING Land Div | 4/24/2009 | | 4/24/2009 | | FAIL |
Todd Tucker
|
|
|
Do not issue permit until Englefield Green Sub. #3 has been recorded at the County Recorders Office.
|
Plans ACCEPTED BY PLAN TECH | | | 4/24/2009 | | DONE |
Darla L Downs
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 4/24/2009 | | DONE |
|
|
|
|
Pending Assignment by JCM | 4/23/2009 | | 4/23/2009 | | BLDA |
John Menard
|
|
|
4/23/2009 16:01:09 JCM - activity updated through activity BLDA168 from case BLD09-00557.
|
Application received | | 4/22/2009 | 4/22/2009 | | DONE |
Darla L Downs
|
|
|
|
Routing - PLAN CHECK | 6/1/2009 | | 7/15/2008 | | FAIL |
Dan Stuart
|
|
|
Resubmittals of 7/8/09 inserted into plans and re-routed plans to Planning Land Div., Planning, Public Works, Plan Check & Fire for second review.
|