Permit NumberBLD09-00557
StatusFinaled
Name GRACE AT ENGLEFIELD GREEN LLC
Site Address 250 S ALLUMBAUGH WAY
Project NameGrace @ Englefield Green
Customer Number 
ePlanReviewNo
Description
(Grace @ Englefield Green - Assisted Living) Scope of work includes construction of a 66,772 sq. ft., single story, fully sprinklered, Type VA construction, divided by (4) 2-hour fire walls to create three buildings for allowable floor area compliance based on type of consturction (11, 857 sq. ft. / 43,167 sq. ft. / 11,698 sq. ft.); with 85 supervised residential units (34 one bedroom units @ 528 sq. ft.; 37 Studio Units @ 388 sq. ft.; 2 two bedroom units @ 816 sq. ft.; 2 two bedroom units @ 780 sq. ft. and 4 Friendship Units @ 366 sq. ft.); use of 2-hour fire walls and (4) 1-hour smoke barrier walls create (5) smoke compartments; 1-hour smoke partitions to create a smoke resistant corridor system; a kitchen, dining and socializing area; laundry, mechanical and common use support areas. There are four interior courts (3,536 sq. ft. / 2,911 sq. ft. / 4,492 sq. ft. / 3,536 sq. ft.) that exit back through the facility; installation of electrical, mechanical, plumbing, sprinkler and alarm systems; and all associated site work and landscaping, all per reviewed plans to include red-line review notes and all attached plan review conditions / comments as part of the reviewed plans. 7/20/10 Carport design and construction treated as deferred submittal. Engineered design submitted and verified for compliance in field. drs
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent Occupancy  11/14/2013 DONE
DetailsBarbara Stitt
Permanent Occupancy  11/4/2013 DONE
DetailsTisha Gallop
Print new cert of occ with address correction. See scanned address form in documents. E-mailed to Linda Hines at Grace @ Englefiled Green
Case Summary (BLD)  8/22/2012  
FIRE-Final Inspection7/20/20107/21/20107/21/2010APASS
DetailsTroy Cobbley
life safety passed
Permanent Occupancy  7/20/2010 DONE
DetailsJason Blais
Plan resubmittals received  7/20/2010 DONE
DetailsJason Blais
Deferred submittal item on carport engineering received. Sent inspector out to verify carport structures are constructed in accordance with engineered design and calculations. Acceptable per inspection. Inspector previously verified footings during construction. New final Certificate of Value also submitted. Scope of permit will be changed regarding the carport structures. A new CO will be issued with changed scope of work.
First Notice 6/24/20107/16/2010 DONE
Permanent Occupancy UNPAID FEE  6/14/2010 DONE
BLD-Conference6/11/20106/11/20106/11/2010PPASS
DetailsTom Arcoraci
BLD-Final6/11/20106/11/20106/11/2010PPASS
DetailsTom Arcoraci
temp glass ok
Zoning Approval6/11/20106/11/20106/11/2010 PASS
DetailsAndrea Tuning
The trash enlosures and the screening is now complete. Final occupancy may be issued at any time.
PubWorks Occupancy Approval6/7/20106/7/20106/7/2010 DONE
DetailsTiffany Lowery
BLD-Final6/1/20106/2/20106/2/2010APART
DetailsTom Arcoraci
harvey Phone #: ###-#### will use approved film for temp glass issues
Zoning Approval Temp6/2/20106/2/20106/2/2010 DONE
DetailsAndrea Tuning
Staff has granted the applicant a 30 day temporary occupancy. Final occupancy was not granted due to the fact that the applicant has not completed the trash enclosures or the landscape screening of these enclosures. Once the trash enclosures and the screening is installed, staff will sign the permanent occupancy for the building.
Temporary Occupancy UNPAID FEE  6/2/2010 DONE
Case Summary (BLD)  6/2/2010 DONE
BLD-Final5/28/20106/1/20106/1/2010PNR
DetailsDave Hannah
Phone #: ###-####
FIRE-Final Inspection5/28/20106/1/20106/1/2010AFAIL
DetailsTroy Cobbley
Provide test report for the kitchen hood and the fire sprinkler permit needs to be finaled. Alarm permit finaled today. Occupant load signs for the assembly areas are temporary until the permanent ones are installed.
FIRE-Final Inspection5/27/20105/28/20105/28/2010AFAIL
DetailsTroy Cobbley
The only item for life safety that was inspected today were the exit signs and emergency lighting. One exit sign needs to be added as shown on the city approved plans. Herb is calling in for a re-inspection for Tuesday.
FIRE-Conference5/26/20105/27/20105/27/2010ADONE
DetailsTroy Cobbley
Trip test on smoke detectors--Matt Phone #: ###-####
FIRE-Final Inspection5/26/20105/26/20105/27/2010PCANC
DetailsTroy Cobbley
Wrong inspection type called in. Herb needed fire alarm inspection.
BLD-Conference5/24/20105/25/20105/25/2010PPART
DetailsTom Arcoraci
BLD-Conference5/21/20105/24/20105/24/2010APASS
DetailsTom Arcoraci
BLD-Conference5/20/20105/21/20105/21/2010APASS
DetailsTom Arcoraci
BLD-Conference5/19/20105/20/20105/20/2010APART
DetailsMike Jordan
room in smoke compartment 4. needsz safety glazing.
BLD-Conference5/19/20105/19/20105/19/2010PPART
DetailsTom Arcoraci
tempered glass required
BLD-Wall cover3/25/20103/26/20103/26/2010APASS
DetailsTom Arcoraci
BLD-Wall cover3/17/20103/24/20103/24/2010APASS
DetailsTom Arcoraci
BLD-Wall cover3/12/20103/17/20103/17/2010APASS
DetailsTom Arcoraci
FIRE-Conference3/12/20103/12/20103/12/2010PDONE
DetailsTroy Cobbley
Tom, building inspector, and I spoke to Herd about fire blocking and fire sprinkler requirements at the two fireplace locations and the columns. Also the the entire south third of the building has been covered with out the sprinkler piping having been inspected. I notified Herd of IFC requirements but stated that for this one specific happening I would not require the ceiling to be removed but the insulation would be required to be removed from over the piping for an inspection. The insulation will then need to be reinstalled for a secondary inspection. Any areas that I deam accessible will have the ceilings removed for sprinkler piping inspection. I notified Scott of the situation.
BLD-Framing/Rough-in3/12/20103/12/20103/12/2010PPASS
DetailsTom Arcoraci
BLD-Framing/Rough-in3/10/20103/11/20103/11/2010PFAIL
DetailsTom Arcoraci
herb Phone #: ###-####
BLD-Wall cover3/10/20103/11/20103/11/2010PPASS
DetailsTom Arcoraci
BLD-Other2/25/20103/4/20103/4/2010APART
DetailsTom Arcoraci
work ij progress ok
BLD-Wall cover2/22/20102/25/20102/25/2010APASS
DetailsTom Arcoraci
BLD-Conference2/17/20102/24/20102/24/2010APASS
DetailsTom Arcoraci
BLD-Wall cover2/19/20102/22/20102/22/2010APART
DetailsTom Arcoraci
Herb Phone #: ###-#### wip
BLD-Conference2/10/20102/17/20102/17/2010APASS
DetailsTom Arcoraci
wip ok
BLD-Wall cover2/11/20102/12/20102/12/2010APASS
DetailsTom Arcoraci
Herb Phone #: ###-####
BLD-Other2/4/20102/10/20102/10/2010APASS
DetailsTom Arcoraci
BLD-Conference1/29/20102/3/20102/3/2010APASS
DetailsTom Arcoraci
BLD-Wall cover1/27/20101/29/20101/29/2010APART
DetailsTom Arcoraci
Herb Phone #: ###-#### wip ok
BLD-Framing/Rough-in1/22/20101/25/20101/25/2010APASS
DetailsTom Arcoraci
Curt-Cover inspection please Phone #: ###-####
FIRE-Conference1/20/20101/20/20101/20/2010PDONE
DetailsTroy Cobbley
The stop work order that had been previously posted for the fire alarm installation is being lifted due to the fire alarm plans being issued.
BLD-Wall cover1/20/20101/20/20101/20/2010AFAIL
DetailsTom Arcoraci
fire stopping incomplete
BLD-Conference1/11/20101/19/20101/19/2010APASS
DetailsTom Arcoraci
wip ok
BLD-Framing/Rough-in1/8/20101/11/20101/11/2010PPART
DetailsTom Arcoraci
Herb-Nailing inspection please Phone #: ###-#### wip ok
BLD-Other1/7/20101/7/20101/7/2010APASS
DetailsTom Arcoraci
discussed fire walls
BLD-Conference12/31/20091/6/20101/6/2010APASS
DetailsTom Arcoraci
Meeting  1/6/2010 DONE
Troy Cobbley issued a Stop work order due to fire alarm devices and wiring being installed without an approved permit. Work order is for further installation of fire alarm and installation of sheetrock that will cover wiring and/or backboxes. I gave the job superintendent permission to insulate the exterior walls.
BLD-Conference12/30/200912/31/200912/31/2009APASS
DetailsTom Arcoraci
BLD-Other12/23/200912/30/200912/30/2009APASS
DetailsTom Arcoraci
BLD-Wall cover12/17/200912/23/200912/23/2009APART
DetailsTom Arcoraci
wip ok
BLD-Conference12/17/200912/18/200912/18/2009PPASS
DetailsTom Arcoraci
can lights ok
BLD-Other12/10/200912/17/200912/17/2009APASS
DetailsTom Arcoraci
wip ok
BLD-Wall cover12/4/200912/9/200912/10/2009PPASS
DetailsTom Arcoraci
wip
BLD-Conference12/3/200912/4/200912/4/2009APASS
DetailsTom Arcoraci
wip ok discussed acces reach
BLD-Wall cover12/2/200912/3/200912/3/2009APASS
DetailsTom Arcoraci
wip
BLD-Wall cover12/1/200912/2/200912/2/2009APASS
DetailsTom Arcoraci
wip
BLD-Conference11/30/200912/1/200912/1/2009PPASS
DetailsTom Arcoraci
BLD-Wall cover11/19/200911/24/200911/24/2009APASS
DetailsTom Arcoraci
wip ok
BLD-Wall cover11/17/200911/24/200911/23/2009ACANC
DetailsTom Arcoraci
BLD-Conference11/16/200911/17/200911/17/2009APASS
DetailsTom Arcoraci
BLD-Conference11/16/200911/16/200911/16/2009PPART
DetailsTom Arcoraci
Herb Phone #: ###-####
BLD-Foundation9/30/20099/30/20099/30/2009APASS
DetailsTom Arcoraci
wip ok
BLD-Foundation9/29/20099/29/20099/29/2009PPASS
DetailsTom Arcoraci
herb Phone #: ###-####
BLD-Footing9/24/20099/25/20099/25/2009PPART
DetailsTom Arcoraci
wip ok
BLD-Footing9/23/20099/24/20099/24/2009APASS
DetailsTom Arcoraci
Herb-1:00 pouring so late am if possible please Phone #: ###-####
BLD-Footing9/21/20099/22/20099/22/2009PPASS
DetailsTom Arcoraci
herb Phone #: ###-#### wip ok
Issue PAID IN FULL permit  9/8/2009 DONE
Print Occupancy Form  8/26/2009 DONE
Permit Ready to Issue  8/26/2009 DONE
Telephone call  8/26/2009 DONE
called left message for Doug T. permit ready and fee given also need ACHD
Routing Off Site - STRUCTURAL8/20/2009 8/25/2009 PASS
DetailsDan Stuart
Copy of engineering & architectural response e-mailed to Steve Call to review for his meeting with Mr. Cox & Mr. Tamura at 10 am on Monday 8/24/09.
8/25/09 -Inserted plan sheets A2.3, A2.4 & A4.2. Discussed on phone the use of the Simpson MSTC40 as a tension strap for the drag strut truss' indicated on plan Sheet A2.4 with Steve Call. Strap was approfed. Received copy of final structural engineering plan review report from Steve Call.
Routing - PLAN CHECK8/24/2009 8/25/2009 PASS
DetailsDan Stuart
Inserted new resubmittal sheets into plans. Reviwed structural plan changes with Steve Call. No further resubmittals required.
Plan resubmittals received  8/25/2009  
DetailsDan Stuart
Rec'd one copy of transmittal letter and three copies of sheets A2.3; A2.4; & A4.2- taken to Dan S
Telephone call  8/25/2009 DONE
Called Steve Call, Structural Engineer reviewing structural plans. Reviewed use of Simpson MSTC40 strap as tension drag strut for truss'. Okay.
PLANS/APPL TAKEN TO FRONT DESK  8/25/2009 PASS
Plan assigned to (DRS)4/23/2009 8/25/2009 PASS
DetailsDan Stuart
8/25/2009 16:15:47 DRS - activity updated through activity BLDA022 from case BLD09-00557.
Telephone call  8/24/2009 DONE
Call from Steve Call, engineer reviewing structural plans reporting on meeting with Mr. Cox & Mr. Tamura. I will be receiving a final report & resubmittals.
Telephone call  8/24/2009 DONE
Called Marla Carson to ask that she review her plan details for headers on Sheet A2.4, columns on A2.3 and the engineering calcs for the drag struts on sheet A4.2, Detail 6, to make sure same information called for in engineering design sheets is reflected on the plans.
Routing - Design Review8/24/2009 8/24/2009 PASS
DetailsAndrea Tuning
Staff has all of the items that are required. ANT
Routing - PLAN CHECK8/18/2009 8/24/2009 FAIL
DetailsDan Stuart
Routed plans back to planning to have required sheets initialed by staff.
Routing Off Site - STRUCTURAL8/20/2009 8/20/2009 FAIL
DetailsDan Stuart
Talked with Steve Call concerning engineering issues and his discussion with Mr. Cox. A meeting has been set up for 9/24/09 at 10 am in Mr. Calls office to review engineering items. I am e-mailing a copy of the plan review response I received to Steve Call to make sure we both had the same information.
We discussed a separate foundation permit possibility and it was determined additional design information was needed. Steve will call Mr. Cox to review foundation data in hope of have plan changes for foundation for Monday's meeting.
Telephone call  8/20/2009 DONE
Called Mr. Call to discuss remaining structural considerations to do with the foundation. Mr. Tamura had called to see if permits could be issued. Mr. Call said he had talked with Mr. Cox yesterday and that a meeting had been set up for Monday, 9/24/09, at 10 am at Mr. Call's office to review the structural items.
There are some foundation issues that need resloved before Mr. Call would okay the foundation design for permit. Mr. Call will call Mr. Cox and discuss the foundation issue to provide time for structural modification design data to be brought to the Monday meeting to see if the foundation can be approved.
Telephone call  8/20/2009 DONE
Dough Tamura, architect, called to discuss possibility of getting a building permit while the remaining structural concerns are addressed. I told him I would discuss the matter with Jason Blais and Mr. Call and get back with him. After discussion with Jason & Steve, I sent an e-mail to all parties concerned outlining the process for Mr. Tamura to obtain a seprate foundation permit.
Routing Off Site - STRUCTURAL8/18/2009 8/19/2009 FAIL
DetailsDan Stuart
Called Steve Call to discuss plan resubmittals of 8/19/09 and to tell him I would be routing him plans to review. Steve said he had received a copy of the resubmittals from the architect directly. We discussed the drag strut detail, drag truss allighments, loads and strap design, diaphragm cord connections, etc. that had not bee adequately addressed for code compliance. Mr. Call would call Mr. Cox to discuss issues.
Telephone call  8/19/2009 DONE
Talked with steve Call concerning Mr. Cox structural engineering design resubmittals and details on plan resubmittals of 9/18/09. He had received a copy of the resubmittals direct from Doug Tamura at the same time copies were submitted to PDS plan review. We talked about the drag struct design, drag truss alighnment with walls, diaphragm cord connections, etc. remaining to be addressed to show code compliance. This resubmittal also failed. Mr. Call was going to call Mr. Cox to discuss the items.
Plan resubmittals received  8/18/2009  
DetailsTisha Gallop
received transmittal, repsonse comments, and three copies of structural calculations, and sheets A0.2, A0.3, A2.0, A2.1, A2.2, A2.3, A2.4, A3.0, A4.1, A4.2, A4.3, A5.0, A5.1, A9.1, A9.2, A10.0, M1.1, M1.2, M5.2, P1.1, P1.2, E2.0, E3.0, E4,0, E5.0, E6.0, E7.0; inserted by arch. rep. and taken back to Dan Stuart
Routing - PLAN CHECK8/7/2009 8/13/2009 FAIL
DetailsDan Stuart
Structural review and architectural details incomplete. Copy of engineering report & my plan review report e-mailed to Marla Carson & Doug Tamura.
Routing - PLAN CHECK8/6/2009 8/13/2009 FAIL
DetailsDan Stuart
Resubmittals required.
Routing Off Site - STRUCTURAL7/29/2009 8/11/2009 FAIL
DetailsDan Stuart
Engineering Calc changes and architectural plan submittals.
8/11/09 - List of engineering design data and details needing to be addressed e-mailed to Marla Carson and Doug Tamura.
Plan resubmittals requested  8/7/2009 DONE
E-mail to doug Tamura and Marla Carson.
Routing - Design Review8/6/2009 8/6/2009 PASS
DetailsAndrea Tuning
The plat has been recorded with a plat note allowing cross access, the fire department has released the non-build agreement and the site and landscape plans have been modified to provide 18 and 20 foor planter islands.
Route to Impact Fee Review7/31/20098/5/20098/4/2009 PASS
DetailsCindy M. Gould
Plan resubmittals received  8/4/2009  
DetailsDan Stuart
Rec'd copies of the legal lot- given to Dan S
Routing - PLANNING Land Div8/4/2009 8/4/2009 PASS
DetailsTodd Tucker
Letter of Satisfaction from the Fire Department has been recorded.
Plan resubmittals received  8/4/2009 DONE
received 2 sets of sheets A1.0,A1.1 inserted by Marla with Doug Tarmura Arch and take back to Dan S.
Routing - PLAN CHECK7/31/2009 8/4/2009 FAIL
DetailsDan Stuart
Routing plans back to Planning Land Div as requested by TRT.
Routing - FIRE7/28/20097/28/20097/31/2009 PASS
DetailsScott Arellano
Attached updated IFC comments to plans
FIRE DEPT. NON-BUILD11/2/20077/27/20097/29/2009 PASS
DetailsDan Stuart
Non-Building agreement recorded 11/2/07. 7/27/09 - Copy of non build provided by Planning Land Div with not that conditions of agreement are not satisfied as of this date.
7/29/09 - Copy of notorized SATISFACTION OF NON-BUILDING AGREEMENT provided.
Telephone call  7/29/2009 DONE
Call to Doug Tasmura - Will send copy of non-build agreement removal approval from Mark Senteno, two copies of recorded plat site plan with legend and property lines; then waiting for response from structural engineer, planning, plann-land div sign off and plan check. Hopefully by the end of next week - 8/7/09 to be ready.
Routing - PLAN CHECK7/20/2009 7/29/2009 FAIL
DetailsDan Stuart
Routing to fire then Planning.
Routing - PLANNING Land Div7/27/2009 7/27/2009 FAIL
DetailsTodd Tucker
Non-build Agreement #107149467. Must get Satisfaction Memo.
Plan resubmittals received  7/22/2009  
DetailsTisha Gallop
received memo and four copies of sheets A1.1, A1.2; inserted by arch. rep. and taken back to Dan Stuart
Routing - PLANNING7/20/2009 7/20/2009 FAIL
DetailsAndrea Tuning
The applicant will need a cross access acgreement, meet the conditions of the subdivision to remove the non-build agreement, and construct the landscape planters to be a minimum of 20-feet in length. ANT 7-20-09

Sue H & Andrea T
Routing - PUBLIC WORKS7/16/2009 7/20/2009 PASS
DetailsBeverly Hall
Routing PW Solid Waste  7/17/2009 PASS
DetailsPeter J. McCullough
Routing - PLANNING Land Div7/15/2009 7/16/2009 FAIL
DetailsTodd Tucker
Final Plat has still not been recorded. Subdivision Ordinance Section 9-20-08.A.2 states "No building permit for the construction of any new structure upon property within a proposed subdivison plat shall be issued until the subdivison plat has been recorded pursuant to the requirements of this Chapter."
Plan resubmittals received  7/8/2009 DONE
Routed to
Route to Impact Fee Review5/28/20096/2/20096/2/2009 PASS
DetailsCindy M. Gould
Routing - FIRE5/28/20095/28/20096/1/2009 FAIL
DetailsScott Arellano
Faxed and emailed resubmittal items to architect.
1st review completed  6/1/2009 FAIL
Failed Public Works, Structural, Plumbing, Planning, Plan Check, Fire
Plan resubmittals requested  5/28/2009 DONE
Plan review list e-mailed to Doug Tamura.
Routing - PLAN CHECK5/8/2009 5/28/2009 FAIL
DetailsDan Stuart
Resubmittals required. Copy of plan review to doug tamura. Plans to fire code analyst.
Telephone call  5/14/2009 DONE
Call from Marla Carson with request to allow project structural engineer, Harold Cox, contact our Contract structural engineer directly to discuss structural plan review. I will contact our structural engineer to see if this is ok by them.
Telephone call  5/14/2009 DONE
Talked with contracted Structural Engineer, Steve Call who said it would be okay to give his number to the architect and the engineer for direct correspondence.
Telephone call  5/14/2009 DONE
Called Marla Carson and left voice message that Harold cox could call Steve Call direct and left a phone number. Steve woul be available at his office on Friday 5/15/09.
Routing Off Site - STRUCTURAL4/24/2009 5/11/2009 FAIL
DetailsDan Stuart
Called Action Couriers for pick up
5/11/09 - Received notification from Boise city Contract Structural Engineer that the structural review had failed. copy of report e-mailed to Marla Carson W/ Doug Tamura Architect to route to project engineer.
Routing - PLANNING5/6/2009 5/8/2009 FAIL
DetailsDarla L Downs
Cup07-126 Sue C. DRH07-451 Andrea T.
Needs cross access agreement between the lots. Sue
The applicant will need a cross access acgreement, meet the conditions of the subdivision to remove the non-build agreement, and construct the landscape planters to be a minimum of 20-feet in length. ANT
Routing - PLUMBING4/30/2009 5/6/2009 PASS
DetailsBill VanDegrift
all interior rain water piping to be schedule 40. 2" min. waste below grade. Max. 120 deg. hot water to kitchen hand sinks. additional cross connection protection may be required.
Plan resubmittals received  5/6/2009 DONE
received 4 copies of sheet A1.2 taken to Dan S.
Routing PW Sewer Rating4/30/2009 4/30/2009 PASS
DetailsConnie Baumgartner
Routing PW Solid Waste4/30/2009 4/30/2009 FAIL
DetailsPeter J. McCullough
Minimum 18' trash enclosure gate opening and gates must open 120 degrees minimum. Peter McCullough ###-####
Routing PW Street Lights4/29/2009 4/30/2009 PASS
DetailsHank Alarcon
Routing PW Drainage4/30/2009 4/30/2009 PASS
DetailsBrian Murphy
Routing PW Environmental4/30/2009 4/30/2009 PASS
DetailsWalt Baumgartner
OK in the WBSD, kitchen hooked to 1500 gal GI shown, standard design,
Routing - Erosion and Sediment4/30/2009 4/30/2009 PASS
DetailsSteven Webb
ESC plan approved with attached conditions. ESC09-00203
Routing - PUBLIC WORKS4/24/2009 4/30/2009 FAIL
DetailsConnie Baumgartner
Routing PW Drainage4/24/2009 4/28/2009 FAIL
DetailsBrian Murphy
monitoring well in bed BRIAN MURPHY ###-####
Routing - PLANNING Land Div4/24/2009 4/24/2009 FAIL
DetailsTodd Tucker
Do not issue permit until Englefield Green Sub. #3 has been recorded at the County Recorders Office.
Plans ACCEPTED BY PLAN TECH  4/24/2009 DONE
DetailsDarla L Downs
Plan routing begun/NEW & ADDTN  4/24/2009 DONE
Pending Assignment by JCM4/23/2009 4/23/2009 BLDA
DetailsJohn Menard
4/23/2009 16:01:09 JCM - activity updated through activity BLDA168 from case BLD09-00557.
Application received 4/22/20094/22/2009 DONE
DetailsDarla L Downs
Routing - PLAN CHECK6/1/2009 7/15/2008 FAIL
DetailsDan Stuart
Resubmittals of 7/8/09 inserted into plans and re-routed plans to Planning Land Div., Planning, Public Works, Plan Check & Fire for second review.