Permanent Occupancy UNPAID FEE | | | 6/22/2009 | | DONE |
|
|
|
|
BLD-Final | 6/9/2009 | 6/9/2009 | 6/9/2009 | P | PASS |
Jim Storey
|
|
|
signed card on site final ok
|
FIRE-Final Inspection | 6/5/2009 | 6/5/2009 | 6/5/2009 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
Temporary Occupancy | 5/7/2009 | 8/5/2009 | 5/7/2009 | | DONE |
Darla L Downs
|
|
|
|
BLD-Final | 4/28/2009 | 4/29/2009 | 4/29/2009 | P | PART |
Jim Storey
|
|
|
Nguyet Please 1/2 hr call before going out Phone #: ###-#### temp ok need ada bar behind tolite.
|
FIRE-Final Inspection | 4/28/2009 | 4/29/2009 | 4/29/2009 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given until the exit sign is repaired or removed, the sprinkler pendants that are too close together are addressed, the existing fire extinguisher is tagged with a current inspection tag and the dead bolt is removed from the rear exit door.
|
Plan assigned to (CDM) | 4/28/2009 | 4/28/2009 | 4/28/2009 | | PASS |
Carl D Madsen
|
|
|
4/28/2009 11:44:15 CDM - activity updated through activity BLDA022 from case BLD09-00596.
|
Routing - PLAN CHECK | 4/28/2009 | | 4/28/2009 | | PASS |
Carl D Madsen
|
|
|
|
Case Summary (BLD) | | | 4/28/2009 | | DONE |
|
|
|
|
1st review completed | | | 4/28/2009 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/28/2009 | | |
|
|
|
|
Print Occupancy Form | | | 4/28/2009 | | DONE |
|
|
|
|
Telephone call | | | 4/28/2009 | | DONE |
|
|
|
t/c w lilly at ###-#### - permit ready and fees paid
|
Permit Ready to Issue | | | 4/28/2009 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 4/28/2009 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/28/2009 | | DONE |
|
|
|
|
First Notice | | 6/22/2009 | | | |
|
|
|
|
Application received | | 4/28/2009 | | | |
|
|
|
|