Permanent Occupancy | | | 6/6/2012 | | DONE |
|
|
|
|
First Notice | | 12/4/2009 | 12/30/2009 | | DONE |
|
|
|
|
Permanent Occupancy | | | 11/25/2009 | | DONE |
|
|
|
|
BLD-Final | 11/24/2009 | 11/24/2009 | 11/24/2009 | P | PASS |
Tom Arcoraci
|
|
|
request late pm, please call 45-30 min prior///Troy Blanton Phone #: ###-####
|
BLD-Final | 10/27/2009 | 10/28/2009 | 10/28/2009 | A | NR |
Tom Arcoraci
|
|
|
Troy Blanton ###-#### needs handrails completed
|
PubWorks Occupancy Approval | 10/28/2009 | 10/28/2009 | 10/28/2009 | | DONE |
Tiffany Lowery
|
|
|
|
FIRE-Final Inspection | 10/26/2009 | 10/27/2009 | 10/27/2009 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.
|
Zoning Approval | 10/12/2009 | 10/12/2009 | 10/12/2009 | | PASS |
Josh Wilson
|
|
|
|
BLD-Other | 9/30/2009 | 10/1/2009 | 10/1/2009 | A | PASS |
Tom Arcoraci
|
|
|
Troy Phone #: ###-#### grid maintained as built
|
BLD-Framing/Rough-in | 8/28/2009 | 8/31/2009 | 8/31/2009 | A | PART |
Jim Storey
|
|
|
TROY Phone #: ###-#### 450 c/n still pending papper work to recieve at next insp. header ok. sheer wall with staples ok if papper work is 8 and 8 oc/ lvl just fied on plan note as opsunal.
|
BLD-Framing/Rough-in | 8/25/2009 | 8/26/2009 | 8/26/2009 | P | PART |
Mike Jordan
|
|
|
Troy Phone #: ###-####. Interior wood framed walls. Need RFI from engineer for shearwall attachment in basement. Noted descrepency on plans and fasterners to be used not listed. Also needs detailfrom engineer justifing use os wood framed wall in leiu of LVL as shown on approved plans.
|
BLD-Footing | 7/30/2009 | 7/31/2009 | 7/31/2009 | P | PASS |
Jim Storey
|
|
|
troy Phone #: ###-#### - early afternoon please center bearing ft ok need si for 3000psi concrete pending.
|
Telephone call | | | 7/29/2009 | | DONE |
|
|
|
left vm for mike fairchild at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 7/29/2009 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 7/29/2009 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/28/2009 | | 7/28/2009 | | DONE |
Carl Westfall
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/28/2009 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/28/2009 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 7/27/2009 | | 7/28/2009 | | PASS |
Beverly Hall
|
|
|
Revised drainage plans submitted. Took to Bev.
|
Routing PW Drainage | 7/27/2009 | | 7/28/2009 | | PASS |
Brian Murphy
|
|
|
|
Plan assigned to (CJW) | 5/19/2009 | | 7/28/2009 | | PASS |
Carl Westfall
|
|
|
7/28/2009 13:26:32 CJW - activity updated through activity BLDA022 from case BLD09-00614.
|
Plan resubmittals received | | | 7/27/2009 | | DONE |
|
|
|
received 2 O& M plan,and 5 copies of sheet SW-100 taken to Carl W.
|
Routing - PLAN CHECK | 7/15/2009 | | 7/27/2009 | | PASS |
Carl Westfall
|
|
|
Drawings approved on July 22, 2009 after the resubmittal review.
|
Routing - PLANNING | 7/15/2009 | | 7/15/2009 | | PASS |
Josh Wilson
|
|
|
OK per DRH09-00127 and CUP09-00009. Parking agreement shall be submitted prior to sign off on occupancy.
|
Routing - PUBLIC WORKS | 7/10/2009 | | 7/15/2009 | | FAIL |
Connie Baumgartner
|
|
|
|
Routing PW Drainage | 7/10/2009 | | 7/14/2009 | | FAIL |
Brian Murphy
|
|
|
NEEDS REVISIONS TO PLAN AND O AND M TIMELINE. BRIAN MURPHY ###-####
|
Plan resubmittals received | | | 7/10/2009 | | |
Carl Westfall
|
|
|
Rec'd transmittal sheet, and two copies or sheet 2a- taken to Carl W
|
Routing - PLAN CHECK | 6/11/2009 | | 7/10/2009 | | FAIL |
Carl Westfall
|
|
|
Completed the IBC resubmittal review. 2 items were not resolved. Sent an E-mail to the architect and routed the drawing back to PW.
|
Plan resubmittals received | | | 7/7/2009 | | |
|
|
|
Received 1 letter of transmittal,2 structural reports,2 copies of sheets 1,2,7s3,s4,s1,m-100,s-101,s-103,p-100,p-101,p-102,p-103,e-100,e-101,e-102,e-103,e-104 and 3 copies of sheets 5 & 6
Also received 1 transmittal letter,2 copies of O & M manual & 2 copies of sheet SW-100 sent all resubmittals to Carl Westfall
|
Routing - FIRE | 6/5/2009 | 6/5/2009 | 6/11/2009 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
1st review completed | | | 6/11/2009 | | FAIL |
|
|
|
Failed Public Works, Planning, Plan Check
|
Route to Impact Fee Review | 6/5/2009 | 6/10/2009 | 6/8/2009 | | PASS |
Cindy M. Gould
|
|
|
Tenant improvements.
|
Routing - PLAN CHECK | 5/28/2009 | | 6/5/2009 | | FAIL |
Carl Westfall
|
|
|
The IBC plan review was started on June 1, 2009 and was finished on June 5, 2009. Revised drawings were required. See the plan review report.
|
Routing PW Drainage | 5/27/2009 | | 5/28/2009 | | FAIL |
Brian Murphy
|
|
|
NEED MONITORING WELL. SPEC C33 OR EQUAL SAND..BED LENG . SEPERATION DISTANCE . ECT. BRIAN MURPHY ###-####
|
Routing - PLAN CHECK | 5/20/2009 | | 5/27/2009 | | |
Carl Westfall
|
|
|
Taken out of Plan Review by Public Works for further review.
|
Routing - PUBLIC WORKS | 5/19/2009 | | 5/20/2009 | | FAIL |
Beverly Hall
|
|
|
Original review did not route to BM for parking lot - plans are failed.
|
Routing - Erosion and Sediment | | | 5/20/2009 | | PASS |
Steven Webb
|
|
|
ESC plan approved with attached conditions. ESC09-00259
|
Routing - PLANNING | 5/20/2009 | | 5/20/2009 | | FAIL |
Sue Cummings
|
|
|
Sue Cummings CUP09-00009. PASS- Needs to submit shared parking agreement and the landscaping needs to be completed prior to issuance of a C of O. Design Review Josh Wilson FAIL- DR application not yet approved.
|
Routing - Addressing | 5/19/2009 | | 5/19/2009 | | PASS |
April Wing
|
|
|
|
Pending Assignment by JCB | 5/19/2009 | | 5/19/2009 | | DONE |
Jason Blais
|
|
|
|
Intake Approval | | | 5/15/2009 | | PASS |
Dan Stuart
|
|
|
Visited with Cody Riddle 4/29/09 concerning intake of plans while Planning approval for associated new parking lot and landscaping is processing. He indicated there wouldn't be a problem. A letter provided by architect noting understanding that a permit will not be issued before Planning requirements are met. This is an occupancy use change and a CZC has been issued.
|
Intake Approval | | | 5/13/2009 | | FAIL |
Dan Stuart
|
|
|
|
Telephone call | | | 5/11/2009 | | DONE |
Dan Stuart
|
|
|
Mike Fairchild called to set up second Plan Intake T.I. for Boise Police Association Activities Building, 7311 Potomac, occupancy use change.
|
Intake Approval | | | 4/29/2009 | | FAIL |
Dan Stuart
|
|
|
|
Application received | | 4/29/2009 | | | |
|
|
|
|
Routing - Design Review | 5/20/2009 | | | | |
Josh Wilson
|
|
|
Josh Wilson DRH09-00127.
|