Permit Information
Permit NumberBLD09-00615
StatusExpired
Name CAPITAL CITY DEVELOPMENT CORP
Site Address 245 S CAPITOL BLVD Unit: 180
Project NameGrove Hotel
Customer Number 
ePlanReviewNo
Description
**(ADVENTURE TOURS OF IDAHO)** Application for inspection to determine requirements for issuance of a Certificate of Occupancy for an existing 300 square foot Scooter rental occupancy. NO NEW WORK IS AUTHORIZED UNDER THIS PERMIT, EXCEPT THE PATIAL HIEGHT WALL ONTOP OF THE EXISTING COUNTER BECAUSE IT WAS LESS THAN 500 DOLLARS TO CONSTRUCT. This space was created under BLD97-01902. There is a letter attached to this permit that explains the restroom situation. There are no changes to occupancy or use under this permit. TLW
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Expired4/13/20104/13/20104/14/2010PPASS
DetailsDave Hannah
they have moved out of this site
BLD-Final4/13/20104/13/20104/14/2010PFAIL
DetailsDave Hannah
BLD-Final4/30/20095/1/20095/1/2009PPART
DetailsDave Hannah
John If possible please do this inspection around 1pm as he has a meeting with Mr Bieter at 3:30 Thanks Phone #: ###-#### ok for temp occ
FIRE-Final Inspection4/30/20095/1/20095/1/2009APART
DetailsTroy Cobbley
A temporary occupancy was given for the fire issues. See the city approved review notes for the corrections that are needed. That include providing the suite number, provide a fire extinguisher and repair or remove the exit sign.
Permit Ready to Issue  4/30/2009 DONE
DetailsDarla L Downs
CHANGE STATUS TO (ISS)  4/30/2009 DONE
DetailsDarla L Downs
Plan assigned to (TLW)4/29/2009 4/30/2009 PASS
DetailsTim L. Woodard
4/30/2009 16:16:24 TLW - activity updated through activity BLDA022 from case BLD09-00615.
Routing - PLAN CHECK4/30/2009 4/30/2009 PASS
DetailsTim L. Woodard
Approved per redline indicating non-combustable framing for partial hieght wall on top of existing conter. TLW
Routing - PUBLIC WORKS4/29/2009 4/30/2009 PASS
DetailsTim L. Woodard
Louise W. Signed off on attached Public Works review sheet. TLW
Routing PW Sewer Rating4/30/2009 4/30/2009 PASS
DetailsLouise Waldorf
1st review completed  4/30/2009 DONE
DetailsTim L. Woodard
PLANS/APPL TAKEN TO FRONT DESK  4/30/2009 DONE
DetailsTim L. Woodard
Case Summary (BLD)  4/30/2009 DONE
DetailsTim L. Woodard
Print Occupancy Form  4/30/2009 DONE
Issue PAID IN FULL permit  4/30/2009 DONE
Application received 4/29/2009