First Notice | | 11/6/2009 | 11/25/2009 | | DONE |
|
|
|
|
BLD-Final | 10/26/2009 | 10/26/2009 | 10/27/2009 | P | PASS |
Dave Hannah
|
|
|
Brian Phone #: ###-####
|
Permanent Occupancy | | | 10/27/2009 | | DONE |
|
|
|
|
BLD-Final | 10/22/2009 | 10/23/2009 | 10/24/2009 | A | FAIL |
Dave Hannah
|
|
|
Brian Phone #: ###-#### needs 60 min fire doors
|
BLD-Final | 10/21/2009 | 10/22/2009 | 10/22/2009 | P | CANC |
Dave Hannah
|
|
|
Brian Phone #: ###-####
|
FIRE-Final Inspection | 10/20/2009 | 10/21/2009 | 10/21/2009 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
|
FIRE-Final Inspection | 10/19/2009 | 10/20/2009 | 10/20/2009 | A | NR |
Forrest France
|
|
|
Need project related fire alarm permit final prior to building fire life safety approvals.
|
BLD-Conference | 9/18/2009 | 9/18/2009 | 9/21/2009 | P | PART |
Lee Rice
|
|
|
called troy on mechanical because someone in office noticed them working on the roof.
|
BLD-Framing/Rough-in | 9/3/2009 | 9/4/2009 | 9/4/2009 | A | PASS |
Dave Hannah
|
|
|
Brian Phone #: ###-####
|
Routing - PLAN CHECK | 7/22/2009 | | 7/22/2009 | | DONE |
Carl Westfall
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/22/2009 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/22/2009 | | DONE |
|
|
|
|
Telephone call | | | 7/22/2009 | | DONE |
|
|
|
left message w margie for bob smith at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 7/22/2009 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 7/22/2009 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (CJW) | 5/7/2009 | | 7/22/2009 | | PASS |
Carl Westfall
|
|
|
7/22/2009 09:19:09 CJW - activity updated through activity BLDA022 from case BLD09-00650.
|
Routing - PLANNING | 7/21/2009 | | 7/22/2009 | | PASS |
Sarah Schafer
|
|
|
Exterior improvements are very minor and not visible.
|
Routing - PLAN CHECK | 6/16/2009 | | 7/21/2009 | | PASS |
Carl Westfall
|
|
|
Completed the resubmittal review. Drawings approved.
|
Telephone call | | | 7/20/2009 | | DONE |
Tim Frost
|
|
|
Per Cameron at Shilo the pipe size reconnecting the grid will the same size (3") as existing not 2" as shown on the drawings.
|
Plan resubmittals received | | | 7/14/2009 | | |
Tisha Gallop
|
|
|
Received response from architect, two copies of response from engineer, supplemental structural calcs for the relocated HVAC units, supplemental structural calcs for new HVAC fraiming over and existing HVAC frame, supplemental structural calcs for the connection of the battery racks to the floor and reanalyze the 6th floor for the battery, plan sheet A-1; taken to Carl Westfall
|
Routing - FIRE | 6/10/2009 | | 6/16/2009 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
Routing - PLAN CHECK | 5/14/2009 | | 6/10/2009 | | FAIL |
Carl Westfall
|
|
|
Completed the resubmittal review. Sent an E-mail to the Architect asking for additional information.
|
Plan resubmittals received | | | 6/4/2009 | | |
|
|
|
received 1 response, 2 structural calcs, 2 flooded battery rack books and 2 copies of sheets A-1,A-2,A-3,M-2.0,M-4.1 taken to Carl W.
|
Route to Impact Fee Review | 5/12/2009 | 5/15/2009 | 5/15/2009 | | PASS |
Cindy M. Gould
|
|
|
Remodel of existing building. Tenant improvements.
|
Routing - FIRE | 5/12/2009 | 5/12/2009 | 5/14/2009 | | FAIL |
Scott Arellano
|
|
|
Faxed and emailed resubmittal items to architect.
|
1st review completed | | | 5/14/2009 | | FAIL |
|
|
|
Failed Plan Check, Fire
|
Plan resubmittals received | | | 5/12/2009 | | |
Tisha Gallop
|
|
|
received transmittal and two copies of Structural Calculations; taken to Carl Westfall
|
Routing - PLAN CHECK | 5/7/2009 | | 5/12/2009 | | FAIL |
Carl Westfall
|
|
|
The IBC plan review was started on May 8, 2009 and was finished on May 12, 2009. Revised drawings and additional structural analysis and design were required. See the plan review report. E-mailed a copy of the report to the architect and the applicant.
|
Plans ACCEPTED BY PLAN TECH | | | 5/7/2009 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/7/2009 | | DONE |
Tisha Gallop
|
|
|
|
Pending Assignment by JCB | 5/7/2009 | | 5/7/2009 | | DONE |
Jason Blais
|
|
|
|
Intake Approval | | | 5/6/2009 | | PASS |
|
|
|
|
Application received | | 5/6/2009 | | | |
|
|
|
|