Permanent Occupancy | | | 10/22/2009 | | DONE |
Tisha Gallop
|
|
|
|
BLD-Final | 10/7/2009 | 10/8/2009 | 10/9/2009 | P | PASS |
Dave Hannah
|
|
|
matt Phone #: ###-####
|
FIRE-Final Inspection | 10/7/2009 | 10/8/2009 | 10/8/2009 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 9/21/2009 | 9/22/2009 | 9/22/2009 | A | FAIL |
Forrest France
|
|
|
Need to remove the manual thumbturn at the main entry/exit door, remiander of fire life safety items okayed.
|
BLD-Aging Inspection | 9/21/2009 | 9/21/2009 | 9/22/2009 | | PEND |
Dave Hannah
|
|
|
|
Issue PAID IN FULL permit | | | 6/12/2009 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Plan assigned to (TLW) | 5/14/2009 | | 5/18/2009 | | PASS |
Tim L. Woodard
|
|
|
5/18/2009 13:40:48 TLW - activity updated through activity BLDA022 from case BLD09-00708.
|
Routing - PLAN CHECK | 5/14/2009 | | 5/18/2009 | | PASS |
Tim L. Woodard
|
|
|
Plans approved as submitted. TLW
|
1st review completed | | | 5/18/2009 | | DONE |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/18/2009 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 5/18/2009 | | DONE |
Tim L. Woodard
|
|
|
|
Permit Ready to Issue | | | 5/18/2009 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/18/2009 | | DONE |
|
|
|
|
CHANGE STATUS TO (FEE) | | | 5/18/2009 | | DONE |
|
|
|
|
Telephone call | | | 5/18/2009 | | DONE |
|
|
|
left vm for glenn walker at ###-#### - permit ready
|
Permit Ready to Issue | | | 5/18/2009 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/14/2009 | | DONE |
|
|
|
This permit was worked up for reduction of size only permit, No fees per Tim Woodard
|
Application received | | 5/14/2009 | | | |
|
|
|
|