BLD-Final | 9/25/2009 | 9/28/2009 | 9/28/2009 | P | PASS |
Mike Jordan
|
|
|
Please call 15 mins prior to inspection so he can make sure you have access--Jim Phone #: ###-####
|
DOC - Permit Finaled | 9/28/2009 | 9/28/2009 | 9/28/2009 | P | PASS |
Mike Jordan
|
|
|
Cert.of occ. issued.
|
BLD-Final | 9/25/2009 | 9/25/2009 | 9/25/2009 | P | DEFR |
Jim Storey
|
|
|
Please call 15 mins prior to inspection so he can make sure you have access--Jim Phone #: ###-#### need plm final rolled to pm monday no insp. performed.
|
Zoning Approval | 9/2/2009 | 9/2/2009 | 9/2/2009 | | DONE |
Matthew A Halitsky
|
|
|
|
BLD-Other | 8/13/2009 | 8/13/2009 | 8/13/2009 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 8/13/2009 at 6:09:36 AM. exterior weather resistive membrane.
|
BLD-Energy code compliance | 7/28/2009 | 7/28/2009 | 7/28/2009 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 7/28/2009 | 7/28/2009 | 7/28/2009 | P | PASS |
Mike Jordan
|
|
|
All issues resolved.
|
BLD-Energy code compliance | 7/28/2009 | 7/28/2009 | 7/28/2009 | A | CANC |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 7/28/2009 at 7:06:27 AM. MOved to pm.
|
BLD-Framing/Rough-in | 7/28/2009 | 7/28/2009 | 7/28/2009 | A | CANC |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 7/28/2009 at 7:05:35 AM. MOved to pm.
|
BLD-Framing/Rough-in | 7/27/2009 | 7/27/2009 | 7/27/2009 | P | FAIL |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 7/27/2009 at 8:13:16 AM. Strap top plates at plumbing penetrations and dryer vent. Complete lateral bracing on T08 trusses. Provide additional studs at 2 ply T07 truss at point load. ok to insul. c/n posted.
|
BLD-Framing/Rough-in | 7/23/2009 | 7/23/2009 | 7/23/2009 | A | CANC |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 7/23/2009 at 7:27:23 AM.
|
BLD-Framing/Rough-in | 7/17/2009 | 7/17/2009 | 7/17/2009 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 7/17/2009 at 10:59:06 AM.
|
BLD-Framing/Rough-in | 7/10/2009 | 7/10/2009 | 7/10/2009 | P | PASS |
Tom Arcoraci
|
|
|
Jim Phone #: ###-####
|
BLD-Framing/Rough-in | 7/8/2009 | 7/8/2009 | 7/8/2009 | P | NR |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 7/8/2009 at 7:23:55 AM.
|
BLD-Framing/Rough-in | 7/8/2009 | 7/8/2009 | 7/8/2009 | A | CANC |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 7/8/2009 at 7:23:41 AM.
|
BLD-Framing/Rough-in | 7/7/2009 | 7/7/2009 | 7/7/2009 | P | PART |
Mike Jordan
|
|
|
jim - firewall nailing Phone #: ###-####. 2nd layer of 5/8 type x rock, 1st. floor for 2hr. firewall.
|
BLD-Framing/Rough-in | 7/7/2009 | 7/7/2009 | 7/7/2009 | A | PART |
Mike Jordan
|
|
|
jim - firewall nailing Phone #: ###-####. 1st. layer of 5/8 type x rock for 2hr. firewall, 1st. floor.
|
BLD-Footing | 7/2/2009 | 7/2/2009 | 7/2/2009 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 7/2/2009 at 9:09:14 AM. Contact: ###-####. Interior footings ok.
|
BLD-Energy code compliance | 6/29/2009 | 6/29/2009 | 6/29/2009 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 6/29/2009 at 7:19:45 AM.
|
BLD-Foundation | 6/25/2009 | 6/25/2009 | 6/29/2009 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 6/25/2009 at 7:33:20 AM.
|
BLD-Footing | 6/25/2009 | 6/25/2009 | 6/25/2009 | A | PASS |
Mike Jordan
|
|
|
|
BLD-Footing | 6/25/2009 | 6/25/2009 | 6/25/2009 | P | CANC |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 6/25/2009 at 7:32:59 AM.
|
BLD-Footing | 6/23/2009 | 6/24/2009 | 6/24/2009 | P | NR |
Mike Jordan
|
|
|
Bill Phone #: ###-####
|
Issue PAID IN FULL permit | | | 6/23/2009 | | DONE |
|
|
|
|
Route to Impact Fee Review | 5/19/2009 | 5/22/2009 | 6/1/2009 | | PASS |
Cindy M. Gould
|
|
|
|
Inspection Record Card- Bld | | | 6/1/2009 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/1/2009 | | |
|
|
|
|
Telephone call | | | 6/1/2009 | | DONE |
|
|
|
Called Jim and told him that permit is ready & fees due///6-1-09 @ 12:15pm BAS
|
Routing - PLAN CHECK | 5/23/2009 | | 5/29/2009 | | PASS |
Carl D Madsen
|
|
|
|
Case Summary (BLD) | | | 5/29/2009 | | DONE |
|
|
|
|
1st review completed | | | 5/29/2009 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/29/2009 | | |
|
|
|
|
Routing - PUBLIC WORKS | | | 5/26/2009 | | PASS |
Beverly Hall
|
|
|
|
Routing - Design Review | 5/21/2009 | | 5/22/2009 | | PASS |
Andrea Tuning
|
|
|
|
Routing - PLANNING | 5/20/2009 | | 5/21/2009 | | PASS |
Sue Cummings
|
|
|
CUP07-150 CUP08-48
|
Routing - Addressing | 5/19/2009 | | 5/20/2009 | | PASS |
April Wing
|
|
|
|
Application received | | 5/19/2009 | 5/19/2009 | | DONE |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/19/2009 | | DONE |
Tisha Gallop
|
|
|
|