BLD-Final | 2/25/2010 | 2/25/2010 | 2/25/2010 | P | PASS |
Mike Jordan
|
|
|
please call 1/2 hour before. thanks Jim Inspection requested from web by: James Larkin Phone #: ###-####
|
DOC - Permit Finaled | 2/25/2010 | 2/25/2010 | 2/25/2010 | P | PASS |
Mike Jordan
|
|
|
Certificate of occupancy issued.
|
Zoning Approval | 2/25/2010 | 2/25/2010 | 2/25/2010 | | DONE |
Sarah Schafer
|
|
|
|
BLD-Final | 2/24/2010 | 2/24/2010 | 2/24/2010 | P | NR |
Mike Jordan
|
|
|
Jim-please call at least 30 mins prior for access of him to meet ya there Phone #: ###-####. Needs zoning and elec. finals. Contacted Jim to let him know of final insp. still needed.
|
BLD-Wall cover | 2/4/2010 | 2/5/2010 | 2/5/2010 | A | NR |
Mike Jordan
|
|
|
House Wrap Phone #: ###-#### Internet Inspection Request from: James Larkin
|
BLD-Wall cover | 2/2/2010 | 2/2/2010 | 2/2/2010 | A | PART |
Mike Jordan
|
|
|
House Wrap Phone #: ###-#### Internet Inspection Request from: James Larkin. work in progress on installing exterior weather resistive barrier.
|
BLD-Energy code compliance | 1/27/2010 | 1/28/2010 | 1/28/2010 | P | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Internet Inspection Request from: James Larkin
|
BLD-Wall cover | 1/27/2010 | 1/27/2010 | 1/27/2010 | A | PART |
Tom Arcoraci
|
|
|
House wrap Phone #: ###-#### Internet Inspection Request from: James Larkin
|
BLD-Framing/Rough-in | 1/27/2010 | 1/27/2010 | 1/27/2010 | A | PASS |
Tom Arcoraci
|
|
|
House wrap Phone #: ###-#### Internet Inspection Request from: James Larkin
|
BLD-Framing/Rough-in | 1/18/2010 | 1/19/2010 | 1/19/2010 | A | PASS |
Mike Jordan
|
|
|
Fire Wall construction / Overbuild Areas Phone #: ###-#### Internet Inspection Request from: James Larkin. Base and face layers ok as well as overbuild. Also verified fire rated ply at lay down parapets.
|
BLD-Framing/Rough-in | 1/15/2010 | 1/15/2010 | 1/15/2010 | P | NR |
Mike Jordan
|
|
|
Firewall construction Phone #: ###-#### Internet Inspection Request from: James Larkin
|
BLD-Framing/Rough-in | 1/14/2010 | 1/14/2010 | 1/14/2010 | P | NR |
Mike Jordan
|
|
|
Firewall construction Phone #: ###-#### Internet Inspection Request from: James Larkin Will reschedule.
|
BLD-Framing/Rough-in | 1/5/2010 | 1/5/2010 | 1/5/2010 | P | NR |
Mike Jordan
|
|
|
Jim-Fire wall construction inspection please Phone #: ###-####
|
BLD-Framing/Rough-in | 12/30/2009 | 12/30/2009 | 12/30/2009 | P | PART |
Mike Jordan
|
|
|
Jim Phone #: ###-####. 2nd floor, face layer of 5/8 type x rock, both sides for 2hr. fire wall.
|
BLD-Framing/Rough-in | 12/23/2009 | 12/23/2009 | 12/23/2009 | P | PART |
Mike Jordan
|
|
|
Phone #: ###-#### Internet Inspection Request from: James Larkin. 2nd floor, 1st layer, both sides, 58type x rock for 2hr. fire wall.
|
BLD-Framing/Rough-in | 12/23/2009 | 12/23/2009 | 12/23/2009 | A | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### Internet Inspection Request from: James Larkin
|
BLD-Framing/Rough-in | 12/8/2009 | 12/8/2009 | 12/8/2009 | P | PASS |
Mike Jordan
|
|
|
Fire Wall construction Phone #: ###-#### Internet Inspection Request from: James LarkinFace layer of type x rock, 1st. floor both sides.
|
BLD-Framing/Rough-in | 12/6/2009 | 12/7/2009 | 12/7/2009 | P | PART |
Mike Jordan
|
|
|
Fire Wall. Should be ready any time after 11:00 Phone #: ###-#### Internet Inspection Request from: James Larkin. 1st. floor, 1st. layer both sides 5/8 type x rock for 2hr. firewall.
|
BLD-Framing/Rough-in | 12/4/2009 | 12/4/2009 | 12/4/2009 | P | NR |
Mike Jordan
|
|
|
Fire Wall Phone #: ###-#### Internet Inspection Request from: James Larkin
|
BLD-Foundation | 12/1/2009 | 12/1/2009 | 12/1/2009 | A | PART |
Mike Jordan
|
|
|
Phone #: ###-#### Internet Inspection Request from: James Larkin. wip on interior footings, to be placed with slab on grade.
|
BLD-Energy code compliance | 11/24/2009 | 11/24/2009 | 11/24/2009 | P | PASS |
Mike Jordan
|
|
|
Jim Phone #: ###-####. Rigid foam insulation on interior side of stemwall. ok.
|
BLD-Foundation | 11/20/2009 | 11/23/2009 | 11/23/2009 | A | PASS |
Mike Jordan
|
|
|
Bill Phone #: ###-####
|
BLD-Footing | 11/18/2009 | 11/19/2009 | 11/19/2009 | A | PASS |
Mike Jordan
|
|
|
bill Phone #: ###-####
|
BLD-Footing | 11/18/2009 | 11/18/2009 | 11/18/2009 | P | NR |
Mike Jordan
|
|
|
Jim Phone #: ###-####. rescheduled for 11-19-09.
|
Issue PAID IN FULL permit | | | 11/18/2009 | | DONE |
Tisha Gallop
|
|
|
|
Route to Impact Fee Review | 5/19/2009 | 5/22/2009 | 6/1/2009 | | PASS |
Cindy M. Gould
|
|
|
|
Inspection Record Card- Bld | | | 6/1/2009 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/1/2009 | | DONE |
|
|
|
|
Telephone call | | | 6/1/2009 | | DONE |
|
|
|
Called Jim and told him that permit is ready & fees due///6-1-09 @ 12:15pm BAS
|
Plan assigned to (CDM) | 5/26/2009 | 5/26/2009 | 5/29/2009 | | PASS |
Carl D Madsen
|
|
|
5/29/2009 15:50:40 CDM - activity updated through activity BLDA022 from case BLD09-00740.
|
Case Summary (BLD) | | | 5/29/2009 | | DONE |
|
|
|
|
1st review completed | | | 5/29/2009 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/29/2009 | | |
|
|
|
|
Routing - PLAN CHECK | | | 5/29/2009 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PUBLIC WORKS | 5/21/2009 | | 5/26/2009 | | PASS |
Beverly Hall
|
|
|
|
Routing - Design Review | 5/21/2009 | | 5/21/2009 | | PASS |
Andrea Tuning
|
|
|
|
Routing - PLANNING | 5/20/2009 | | 5/21/2009 | | PASS |
Sue Cummings
|
|
|
CUP07-150 CUP08-48
|
Routing - Addressing | 5/19/2009 | | 5/20/2009 | | PASS |
April Wing
|
|
|
|
Application received | | 5/19/2009 | 5/19/2009 | | DONE |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/19/2009 | | DONE |
Tisha Gallop
|
|
|
|