BLD-Aging Inspection | 2/21/2011 | 2/21/2011 | 2/22/2011 | | PASS |
Jim Storey
|
|
|
|
DOC - Permit Expired | 2/22/2011 | 2/22/2011 | 2/22/2011 | P | PASS |
Jim Storey
|
|
|
|
BLD-Aging Inspection | 12/20/2010 | 12/20/2010 | 12/20/2010 | | PASS |
Jim Storey
|
|
|
|
BLD-Aging Inspection | 10/20/2010 | 10/20/2010 | 10/20/2010 | | PASS |
Jim Storey
|
|
|
|
BLD-Aging Inspection | 8/16/2010 | 8/16/2010 | 8/17/2010 | | PART |
Jim Storey
|
|
|
exp. 11/10 no work in progress.
|
CHANGE STATUS TO (ISS) | | | 5/14/2010 | | DONE |
Patricia Smith
|
|
|
|
Issue PAID IN FULL permit | | | 5/14/2010 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 5/4/2010 | | DONE |
|
|
|
ryan w cabal architects called and asked me to email the fees to him
|
Expiration Notice | 4/29/2010 | 5/20/2010 | 4/29/2010 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 1/27/2010 | | DONE |
|
|
|
Letter to Jenifer Gilliland requesting extension for tenant to pick up permit & plans allready reviewed indicates a reduction in scope of work is proposed. I e-mailed the architect of record and the tenant that plan resubmittals are required to show the actual scope of work and the materials proposed for use for this project. A new Lighting compliance Certificate and Fixture schedule is needed for the new lighting & controls for the project.
|
Telephone call | | | 1/27/2010 | | DONE |
|
|
|
t/c w john gillespie at ###-#### - let him know that the permit had been extended per his request - the new expiration date will be May 15, 2010 - he said he would pick up the plans before that date
|
CHANGE STATUS TO (RDY) | | | 1/27/2010 | | DONE |
|
|
|
|
Extend Review Timeline | | | 1/26/2010 | | DONE |
|
|
|
extended to May 15, 2010 per Rita
|
Telephone call | | | 8/13/2009 | | DONE |
|
|
|
Talked with James Cliff, Perkins Construction. Has not heard from architect or owner since he gave them his bid. He will follow up and get back to me. I am sending and inspector by the site to see if any work has begun of the building occupied without permits.
|
Print Occupancy Form | | | 8/13/2009 | | DONE |
|
|
|
|
Telephone call | | | 7/15/2009 | | DONE |
|
|
|
james cliff from perkins const. (###-####) called with an update - he is going to call the architect regarding the project value and will talk with dan stuart on friday
|
Telephone call | | | 7/14/2009 | | DONE |
|
|
|
t/c w john perkins at ###-#### - he is meeting w the owner tomorrow and will call me back - there are issues regarding the project amount - the architect submitted a CofV for $80,000 and Perkins Const. is saying the figure is closer to $181,000 at this time
|
Permit Ready to Issue | | | 7/14/2009 | | DONE |
Patricia Smith
|
|
|
|
Plan resubmittals received | | | 7/9/2009 | | |
Tisha Gallop
|
|
|
Received transmittal, two copies of applicaiton for Project Start Up for Special Inspetions and plan sheets a1.11, a2.11, a6.01; taken to Dan Stuart
|
Routing - PLAN CHECK | 7/6/2009 | | 7/9/2009 | | PASS |
Dan Stuart
|
|
|
Resubmittals received and inserted into plans. Plans to permit desk to issue.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/9/2009 | | PASS |
|
|
|
|
Print Occupancy Form | | | 7/9/2009 | | DONE |
|
|
|
|
Plan assigned to (DRS) | 5/22/2009 | | 7/9/2009 | | PASS |
Dan Stuart
|
|
|
7/9/2009 11:52:26 DRS - activity updated through activity BLDA022 from case BLD09-00761.
|
Routing - PLAN CHECK | 6/18/2009 | | 7/6/2009 | | FAIL |
Dan Stuart
|
|
|
Need further clarification on ventilation and completed Start Up For Special Inspection form. E-mail to architect.
|
Plan resubmittals requested | | | 7/6/2009 | | DONE |
|
|
|
E-mail to Ryan McCaene, architect concerning ventilation and a completed Special Inspection form.
|
Plan resubmittals received | | | 7/2/2009 | | |
Dan Stuart
|
|
|
Rec'd one transmittal letter, two copies of evaluation report, and two copies of sheets as1.11; a1.01; a1.11; a2.01; a2.11; a5.01; a6.01; a7.10; id1.10; a1.10; s1.20; E3.10; E3.20; and E4.20- taken to Dan S
|
Meeting | | | 6/30/2009 | | DONE |
|
|
|
Jason Blais, Building Official and myself, Dan Stuart, met with Ryan McCaene, Architect and John Rimbey, Electrical Engineer to review Energy Code Lighting Compliance Certificate and values used for watts and decorative lighting. Explanation of lighting design process and resubmittals with modifications to be provided.
|
Routing - FIRE | 6/16/2009 | | 6/18/2009 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
1st review completed | | | 6/18/2009 | | FAIL |
|
|
|
Failed Plan Check
|
Routing - MECHANICAL | 6/15/2009 | | 6/16/2009 | | PASS |
Troy James
|
|
|
Plans approved as noted on plans.
|
Plan resubmittals requested | | | 6/15/2009 | | DONE |
|
|
|
Copy of plan review e-mailed to architect for response resubmittals.
|
Plan Reviewer's activity | | | 6/15/2009 | | DONE |
|
|
|
Sent e-mail to Troy James that plans for the Beehive Salon were routed to him for review.
|
Routing - PLAN CHECK | 5/27/2009 | | 6/15/2009 | | FAIL |
Dan Stuart
|
|
|
Resubmittals are required. copy of plan review e-mailed to architect. Routing plans mechanical plan review (for portion of nail salon) and then to fire code analyst for review.
|
Routing - Design Review | 5/27/2009 | | 5/27/2009 | | PASS |
Andrea Tuning
|
|
|
Andrea Tuning DRH09-00094
|
Routing - Erosion and Sediment | 5/26/2009 | | 5/27/2009 | | PASS |
Steven Webb
|
|
|
ESC plan approved with attached conditions. ESC09-00279
|
Routing - PUBLIC WORKS | 5/22/2009 | | 5/26/2009 | | PASS |
Beverly Hall
|
|
|
|
Routing PW Sewer Rating | 5/26/2009 | | 5/26/2009 | | PASS |
Connie Baumgartner
|
|
|
|
Pending Assignment by JCB | 5/21/2009 | | 5/22/2009 | | DONE |
Jason Blais
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/21/2009 | | |
|
|
|
Ok to take in per Dan S. level 3
|
Recd Pcfee & Taken To Pln CK | | | 5/21/2009 | | |
|
|
|
|
Intake Approval | | | 5/20/2009 | | PASS |
Dan Stuart
|
|
|
|
Application received | | 5/20/2009 | | | |
|
|
|
|