Third Notice | | 11/1/2009 | 10/27/2009 | | DONE |
|
|
|
|
Third Notice | | 10/9/2009 | 10/22/2009 | | DONE |
|
|
|
faxed
|
Second Notice | | 9/27/2009 | 9/29/2009 | | DONE |
|
|
|
|
First Notice | | 9/11/2009 | 9/17/2009 | | DONE |
|
|
|
|
BLD-Final | 9/10/2009 | 9/11/2009 | 9/11/2009 | A | PASS |
Mike Jordan
|
|
|
Brett Phone #: ###-####. ok for perm occ.
|
Permanent Occupancy | | | 9/11/2009 | | DONE |
|
|
|
|
BLD-Final | 9/10/2009 | 9/10/2009 | 9/10/2009 | P | NR |
Mike Jordan
|
|
|
Darren Phone #: ###-####. Neds to remove the keyed lock on west exit door and provide transition at end of ramp at east exit door and get elec. temp.
|
FIRE-Final Inspection | 9/10/2009 | 9/10/2009 | 9/10/2009 | A | PART |
Troy Cobbley
|
|
|
Life safety passed.
|
Plan assigned to (SRZ) | 9/9/2009 | 9/9/2009 | 9/10/2009 | | PASS |
Sam Zahorka
|
|
|
9/10/2009 08:31:13 SRZ - activity updated through activity BLDA022 from case BLD09-00791.
|
CHANGE STATUS TO (ISS) | | | 9/10/2009 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 9/10/2009 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 9/10/2009 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 9/10/2009 | | 9/10/2009 | | PASS |
Sam Zahorka
|
|
|
Plan Modification reviewed.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/10/2009 | | DONE |
Sam Zahorka
|
|
|
|
Override - Parcel Holds | | | 9/10/2009 | | |
|
|
|
|
Routing - PLAN CHECK | 9/9/2009 | | 9/9/2009 | | PASS |
Sam Zahorka
|
|
|
|
Print Occupancy Form | | | 9/9/2009 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 9/9/2009 | | |
Sam Zahorka
|
|
|
Plan mod Rec'd- sheet A-1.2- Revise door location and fence enclosure as a result of a field change
|
FIRE-Final Inspection | 8/27/2009 | 8/28/2009 | 8/28/2009 | A | FAIL |
Troy Cobbley
|
|
|
All items are passed except the door needs infilled that leads to the next tenant space, the new door installed as well as the chain link fence or plans need to be resubmitted to Sam Zahorka showing changes for approval.
|
FIRE-Final Inspection | 8/27/2009 | 8/27/2009 | 8/27/2009 | P | FAIL |
Troy Cobbley
|
|
|
The contractor was unble to meet me to test the emergency lighting and exits signs. Door hardware needs to be installed on the east side new door as well as having the blinds that are installed over it removed. Emergency lighting will be required for this new corridor as well since it is marked as an exit path. The door the connects the two tenant spaces has not been infilled as shown on the city approved plans nor has the 6' chain link fence been built. Will meet with Darren in the morning for re-inspection.
|
CHANGE STATUS TO (ISS) | | | 8/21/2009 | | DONE |
|
|
|
|
(F) Reprint permit | | | 8/21/2009 | | DONE |
|
|
|
|
OVERRIDE | | | 7/30/2009 | | |
|
|
|
|
Plan assigned to (SRZ) | 7/30/2009 | 7/30/2009 | 7/30/2009 | | PASS |
Sam Zahorka
|
|
|
7/30/2009 11:15:18 SRZ - activity updated through activity BLDA022 from case BLD09-00791.
|
Routing - PLAN CHECK | 7/30/2009 | | 7/30/2009 | | PASS |
Sam Zahorka
|
|
|
Recieved plan modification and reviewed for code compliance. modified permit and issued to the front counter.
|
Plan Reviewer's activity | | | 7/30/2009 | | DONE |
Sam Zahorka
|
|
|
Recieved plan modification and reviewed for code compliance. modified permit and issued to the front counter.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/30/2009 | | DONE |
Sam Zahorka
|
|
|
|
Case Summary (BLD) | | | 7/30/2009 | | DONE |
Sam Zahorka
|
|
|
|
Telephone call | | | 7/30/2009 | | DONE |
|
|
|
t/c w dawna jenkins at ###-#### - permit (plan mod) ready and fees given
|
Plan Modification Accepted | | | 7/30/2009 | | |
Tisha Gallop
|
|
|
Plan Modification accepted for Bld09-00791 (iTrade Network) because new exterior door has been deleted - demo of 11' 7" of office wall to allow access to exterior door and sidewalk that already exist. Exit lighting and panic hardware will be installed at existing door; submitted on sheets SP-1, A-1; routed to Sam Zahorka
|
Zoning Approval | 7/15/2009 | 7/15/2009 | 7/15/2009 | | DONE |
Andrea Tuning
|
|
|
The applicant chose not to construct the exterior door that was proposed with CZC09-00090. Zoning will sign off on the improvement however building will require updated building plans be submitted to Sam Zahorka. The applicant has been notified.
|
BLD-Framing/Rough-in | 7/13/2009 | 7/14/2009 | 7/14/2009 | A | PASS |
Tom Arcoraci
|
|
|
Darren-ceiling inspection please Phone #: ###-####
|
BLD-Framing/Rough-in | 6/29/2009 | 6/30/2009 | 6/30/2009 | A | PASS |
Mike Jordan
|
|
|
darren Phone #: ###-####. Interior steel stud framed walls for neww hallway to rear exit and window infill. NO grid.
|
Issue PAID IN FULL permit | | | 6/8/2009 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/3/2009 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 6/3/2009 | | 6/3/2009 | | PASS |
Sam Zahorka
|
|
|
Plan Waiver accepted. Applicant must adhere to conditions attached to plans.
|
Telephone call | | | 6/3/2009 | | DONE |
|
|
|
left vm for cornell larson at ###-#### - permit ready and fees given - also need gc name, rce# and rp name
|
Permit Ready to Issue | | | 6/3/2009 | | DONE |
|
|
|
|
Plan assigned to (SRZ) | 5/27/2009 | 6/1/2009 | 6/2/2009 | | PASS |
Sam Zahorka
|
|
|
6/2/2009 16:04:32 SRZ - activity updated through activity BLDA022 from case BLD09-00791.
|
Routing - PLAN CHECK | 6/1/2009 | | 6/2/2009 | | PASS |
Sam Zahorka
|
|
|
|
Case Summary (BLD) | | | 6/2/2009 | | DONE |
Sam Zahorka
|
|
|
|
Routing - FIRE | | | 6/2/2009 | | PASS |
Sam Zahorka
|
|
|
Verify in field.
|
1st review completed | | | 6/2/2009 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLANNING | 6/2/2009 | | 6/2/2009 | | PASS |
Andrea Tuning
|
|
|
Andrea Tuning signed off on last sheet of Intake checklist per CZC09-00090.
|
Case Summary (BLD) | | | 6/2/2009 | | DONE |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/2/2009 | | DONE |
Sam Zahorka
|
|
|
|
Routing - Addressing | 5/26/2009 | | 5/27/2009 | | PASS |
April Wing
|
|
|
|
Routing - PUBLIC WORKS | 5/26/2009 | | 5/27/2009 | | PASS |
Beverly Hall
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/26/2009 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/26/2009 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Application received | | 5/26/2009 | | | |
|
|
|
|