Third Notice | | 2/9/2010 | 1/29/2010 | | DONE |
|
|
|
|
Third Notice | | 1/18/2010 | 1/27/2010 | | DONE |
|
|
|
faxed, mailed and called
|
Telephone call | | | 1/27/2010 | | DONE |
Tisha Gallop
|
|
|
called and left message with Careen for Russ to call me back regarding final values.//Russ called me back said never saw other notices, I told him will fax and mail it right now.
|
Third Notice | | 1/3/2010 | 1/13/2010 | | DONE |
|
|
|
faxed
|
Second Notice | | 12/3/2009 | 12/29/2009 | | DONE |
|
|
|
|
First Notice | | 11/14/2009 | 11/24/2009 | | DONE |
|
|
|
|
Additional plans submitted | | | 11/4/2009 | | DONE |
Tisha Gallop
|
|
|
received letter from D & A glass company to Jim Storey regarding tempered glass; put in Jim Storey's box and e-mailed him that it is here.
|
Permanent Occupancy UNPAID FEE | | | 11/4/2009 | | DONE |
Tisha Gallop
|
|
|
|
BLD-Final | 10/29/2009 | 10/30/2009 | 10/30/2009 | A | PASS |
Jim Storey
|
|
|
John Phone #: ###-#### perm final ok pending fire permit signed off for sprinkler head change out.
|
FIRE-Final Inspection | 10/28/2009 | 10/29/2009 | 10/29/2009 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
|
BLD-Conference | 10/27/2009 | 10/27/2009 | 10/27/2009 | P | DONE |
Forrest France
|
|
|
Regarding an existing fire smoke damper.
|
CHANGE STATUS TO (ISS) | | | 10/12/2009 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 10/9/2009 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/9/2009 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 10/7/2009 | 10/8/2009 | 10/8/2009 | A | PASS |
Jim Storey
|
|
|
john Phone #: ###-#### ok to cover ceilling ecept for at vav boxes to get plm insp.
|
Plan assigned to (CJW) | 10/7/2009 | 10/7/2009 | 10/8/2009 | | PASS |
Carl Westfall
|
|
|
10/8/2009 16:29:00 CJW - activity updated through activity BLDA022 from case BLD09-00818.
|
Routing - PLAN CHECK | 10/7/2009 | | 10/8/2009 | | PASS |
Carl Westfall
|
|
|
Plan modification approved.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/8/2009 | | PASS |
|
|
|
|
Plan Modification Accepted | | | 10/7/2009 | | DONE |
Tisha Gallop
|
|
|
Plan modification accepted for Bld09-00818 (Petroglyph Energy, suite 500) to delete locker room, enlarge the ADA restroom and replace the existing storefront entrance (fire sprinkler heads at the common area of this floor has been replaced in order to downgrade the common area to non-rated under a separate fire sprinkler permit). Submitted on pages G-001, A-101, A-102, A-103, A-301, A-501, A-601; routed to Carl Westfall.
|
BLD-Framing/Rough-in | 9/25/2009 | 9/28/2009 | 9/28/2009 | A | PASS |
Jim Storey
|
|
|
John Phone #: ###-#### ceillings ok to cover.
|
BLD-Conference | 8/31/2009 | 9/1/2009 | 9/1/2009 | A | PASS |
Jim Storey
|
|
|
John Phone #: ###-####
|
BLD-Conference | 8/26/2009 | 8/26/2009 | 8/26/2009 | P | PASS |
Jim Storey
|
|
|
John Phone #: ###-####
|
BLD-Framing/Rough-in | 8/6/2009 | 8/7/2009 | 8/7/2009 | P | PART |
Jim Storey
|
|
|
john Phone #: ###-#### ok pending ele aprovals in conf. rm restaroom and loby soffit.
|
BLD-Framing/Rough-in | 7/16/2009 | 7/17/2009 | 7/17/2009 | A | PART |
Jim Storey
|
|
|
john Phone #: ###-#### revised plan to be submitted to carl w for change in ada shower area. walls ok to cover.
|
Issue PAID IN FULL permit | | | 7/6/2009 | | DONE |
Tisha Gallop
|
|
|
|
Permit Ready to Issue | | | 7/1/2009 | | DONE |
|
|
|
|
Telephone call | | | 7/1/2009 | | DONE |
Barbara Stitt
|
|
|
Called and left voice message for Rob Thornton that permit is ready and fees due///7-1-09 @ 11am BAS
|
Plan assigned to (CJW) | 5/29/2009 | 6/1/2009 | 6/30/2009 | | PASS |
Carl Westfall
|
|
|
6/30/2009 14:17:45 CJW - activity updated through activity BLDA022 from case BLD09-00818.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/30/2009 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/30/2009 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/17/2009 | | 6/30/2009 | | PASS |
Carl Westfall
|
|
|
Drawings approved after resubmittal review.
|
Plan resubmittals received | | | 6/24/2009 | | |
Carl Westfall
|
|
|
Rec'd response letter and spec info packets, and two copies of G-001; G-002; A-101; A-103; A-301; A-601; and A-602- taken to Carl W
|
Routing - FIRE | 6/15/2009 | 6/15/2009 | 6/17/2009 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
1st review completed | | | 6/17/2009 | | FAIL |
|
|
|
Failed Plan Check
|
Route to Impact Fee Review | 6/15/2009 | 6/18/2009 | 6/15/2009 | | PASS |
Donna Wolf
|
|
|
Tenant improvements - existing.
|
Routing - PLAN CHECK | 6/1/2009 | | 6/15/2009 | | FAIL |
Carl Westfall
|
|
|
The IBC plan review was started on June 10, 2009 and was finished on June 15, 2009 (4 work days). Revised drawings were required. See the plan review report.
|
Routing - PUBLIC WORKS | 5/29/2009 | | 6/1/2009 | | PASS |
Beverly Hall
|
|
|
|
Routing PW Sewer Rating | 6/1/2009 | | 6/1/2009 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 5/29/2009 | | 5/29/2009 | | PASS |
April Wing
|
|
|
|
Pending Assignment by JCB | 5/29/2009 | | 5/29/2009 | | DONE |
Jason Blais
|
|
|
|
Intake Approval | | | 5/28/2009 | | PASS |
Tim L. Woodard
|
|
|
Only thing missing from checklist was a water heater detail. Accepted plans without it, but informed applicant that may be required if "plumbing reviewer" requests it. TLW
|
Plans ACCEPTED BY PLAN TECH | | | 5/28/2009 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/28/2009 | | DONE |
Tisha Gallop
|
|
|
|
Application received | | 5/28/2009 | | | |
|
|
|
|