Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberBLD09-00818
StatusFinaled
Name PETROGLYPH ENERGY INC
Site Address 960 S BROADWAY AVE Unit: 500
Project NamePETROGLYPH ENERGY
Customer Number 
ePlanReviewNo
Description
(PETROGLYPH ENERGY) (SUITE 500) (10-8-09) A PLAN MODIFICATION IS APPROVED TO ELIMINATE THE SHOWER AND LOCKER ROOM FROM THE PROJECT, ENLARGE THE PROPOSED NEW RESTROOM, AND DOWNGRADE THE EXISTING 1-HR FIRE-RESISTANCE-RATED CORRIDOR TO A NON-RATED CORRIDOR. QUICK-RESPONSE SPRINKLERS ARE REQUIRED TO BE INSTALLED THROUGHOUT THE ENTIRE 5TH STORY IN LIEU OF MAINTAINING THE CORRIDOR AS A 1-HR FIRE-RESISTANCE-RATED CORRIDOR. THE FIRE SPRINKLER WORK IS COVERED BY PERMIT FIR09-00561. This building is required to be fully fire sprinklered. To create a 10,185 square foot office tenant space from a larger space located on the 5th story. Work is to include a toilet room accessible to the disabled, interior nonbearing walls, interior windows, interior doors, millwork, and finishes. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 as regulated by the Fire Department. If the existing automatic sprinklers within this tenant space are not quick-response, they are required to be replaced with quick-response automatic sprinklers. The adjacent tenant space is not allowed to be occupied under this permit. The tenant who intends to occupy the adjacent tenant space is required to get its own Certificate of Occupancy before occupying that space. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 2/9/20101/29/2010 DONE
Third Notice 1/18/20101/27/2010 DONE
faxed, mailed and called
Telephone call  1/27/2010 DONE
DetailsTisha Gallop
called and left message with Careen for Russ to call me back regarding final values.//Russ called me back said never saw other notices, I told him will fax and mail it right now.
Third Notice 1/3/20101/13/2010 DONE
faxed
Second Notice 12/3/200912/29/2009 DONE
First Notice 11/14/200911/24/2009 DONE
Additional plans submitted  11/4/2009 DONE
DetailsTisha Gallop
received letter from D & A glass company to Jim Storey regarding tempered glass; put in Jim Storey's box and e-mailed him that it is here.
Permanent Occupancy UNPAID FEE  11/4/2009 DONE
DetailsTisha Gallop
BLD-Final10/29/200910/30/200910/30/2009APASS
DetailsJim Storey
John Phone #: ###-#### perm final ok pending fire permit signed off for sprinkler head change out.
FIRE-Final Inspection10/28/200910/29/200910/29/2009PPASS
DetailsTroy Cobbley
Life safety passed.
BLD-Conference10/27/200910/27/200910/27/2009PDONE
DetailsForrest France
Regarding an existing fire smoke damper.
CHANGE STATUS TO (ISS)  10/12/2009 DONE
Case Summary (BLD)  10/9/2009 DONE
Permit Ready to Issue  10/9/2009 DONE
BLD-Framing/Rough-in10/7/200910/8/200910/8/2009APASS
DetailsJim Storey
john Phone #: ###-#### ok to cover ceilling ecept for at vav boxes to get plm insp.
Plan assigned to (CJW)10/7/200910/7/200910/8/2009 PASS
DetailsCarl Westfall
10/8/2009 16:29:00 CJW - activity updated through activity BLDA022 from case BLD09-00818.
Routing - PLAN CHECK10/7/2009 10/8/2009 PASS
DetailsCarl Westfall
Plan modification approved.
PLANS/APPL TAKEN TO FRONT DESK  10/8/2009 PASS
Plan Modification Accepted  10/7/2009 DONE
DetailsTisha Gallop
Plan modification accepted for Bld09-00818 (Petroglyph Energy, suite 500) to delete locker room, enlarge the ADA restroom and replace the existing storefront entrance (fire sprinkler heads at the common area of this floor has been replaced in order to downgrade the common area to non-rated under a separate fire sprinkler permit). Submitted on pages G-001, A-101, A-102, A-103, A-301, A-501, A-601; routed to Carl Westfall.
BLD-Framing/Rough-in9/25/20099/28/20099/28/2009APASS
DetailsJim Storey
John Phone #: ###-#### ceillings ok to cover.
BLD-Conference8/31/20099/1/20099/1/2009APASS
DetailsJim Storey
John Phone #: ###-####
BLD-Conference8/26/20098/26/20098/26/2009PPASS
DetailsJim Storey
John Phone #: ###-####
BLD-Framing/Rough-in8/6/20098/7/20098/7/2009PPART
DetailsJim Storey
john Phone #: ###-#### ok pending ele aprovals in conf. rm restaroom and loby soffit.
BLD-Framing/Rough-in7/16/20097/17/20097/17/2009APART
DetailsJim Storey
john Phone #: ###-#### revised plan to be submitted to carl w for change in ada shower area. walls ok to cover.
Issue PAID IN FULL permit  7/6/2009 DONE
DetailsTisha Gallop
Permit Ready to Issue  7/1/2009 DONE
Telephone call  7/1/2009 DONE
DetailsBarbara Stitt
Called and left voice message for Rob Thornton that permit is ready and fees due///7-1-09 @ 11am BAS
Plan assigned to (CJW)5/29/20096/1/20096/30/2009 PASS
DetailsCarl Westfall
6/30/2009 14:17:45 CJW - activity updated through activity BLDA022 from case BLD09-00818.
PLANS/APPL TAKEN TO FRONT DESK  6/30/2009 DONE
Print Occupancy Form  6/30/2009 DONE
Routing - PLAN CHECK6/17/2009 6/30/2009 PASS
DetailsCarl Westfall
Drawings approved after resubmittal review.
Plan resubmittals received  6/24/2009  
DetailsCarl Westfall
Rec'd response letter and spec info packets, and two copies of G-001; G-002; A-101; A-103; A-301; A-601; and A-602- taken to Carl W
Routing - FIRE6/15/20096/15/20096/17/2009 PASS
DetailsScott Arellano
Attached IFC comments to plans
1st review completed  6/17/2009 FAIL
Failed Plan Check
Route to Impact Fee Review6/15/20096/18/20096/15/2009 PASS
DetailsDonna Wolf
Tenant improvements - existing.
Routing - PLAN CHECK6/1/2009 6/15/2009 FAIL
DetailsCarl Westfall
The IBC plan review was started on June 10, 2009 and was finished on June 15, 2009 (4 work days). Revised drawings were required. See the plan review report.
Routing - PUBLIC WORKS5/29/2009 6/1/2009 PASS
DetailsBeverly Hall
Routing PW Sewer Rating6/1/2009 6/1/2009 PASS
DetailsConnie Baumgartner
Routing - Addressing5/29/2009 5/29/2009 PASS
DetailsApril Wing
Pending Assignment by JCB5/29/2009 5/29/2009 DONE
DetailsJason Blais
Intake Approval  5/28/2009 PASS
DetailsTim L. Woodard
Only thing missing from checklist was a water heater detail. Accepted plans without it, but informed applicant that may be required if "plumbing reviewer" requests it. TLW
Plans ACCEPTED BY PLAN TECH  5/28/2009 DONE
DetailsTisha Gallop
Recd Pcfee & Taken To Pln CK  5/28/2009 DONE
DetailsTisha Gallop
Application received 5/28/2009