BLD-Final | 9/23/2009 | 9/23/2009 | 9/23/2009 | P | PASS |
Tom Arcoraci
|
|
|
ray Phone #: ###-####
|
DOC - Permit Finaled | 9/23/2009 | 9/23/2009 | 9/23/2009 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Framing/Rough-in | 7/22/2009 | 7/23/2009 | 7/23/2009 | P | PASS |
Tom Arcoraci
|
|
|
ray Phone #: ###-####
|
BLD-Foundation | 6/18/2009 | 6/19/2009 | 6/19/2009 | A | PASS |
Tom Arcoraci
|
|
|
Mike Phone #: ###-####
|
PubWorks Subgrade Approval | 6/16/2009 | 6/16/2009 | 6/16/2009 | | DONE |
Terry Records
|
|
|
Footing subgrade has been conditionally approved by the geotechnical engineer.The center of the south footing had a soft spot that must be overexcavated and replaced with additional concrete. For further clarification see the letter from the engineer attached to this case.
|
BLD-Footing | 6/11/2009 | 6/11/2009 | 6/12/2009 | P | CANC |
Tom Arcoraci
|
|
|
|
BLD-Footing | 6/10/2009 | 6/11/2009 | 6/11/2009 | A | NR |
Tom Arcoraci
|
|
|
Ray- after 10 please Phone #: ###-#### needs TR approval
|
Routing Walk-In (BLD) | 5/29/2009 | 5/29/2009 | 5/29/2009 | A | DONE |
Perry Paine
|
|
|
5/29/2009 12:45:11 PEP - activity updated through activity BLDA022 from case BLD09-00820.
|
Plan assigned to (PEP) | 5/29/2009 | 5/29/2009 | 5/29/2009 | | PASS |
Perry Paine
|
|
|
5/29/2009 12:45:11 PEP - activity updated through activity BLDA022 from case BLD09-00820.
|
Routing Walk-In (Erosion) | 5/28/2009 | 5/28/2009 | 5/29/2009 | P | PASS |
Steven Webb
|
|
|
ESC plan approved with attached conditions. ESC09-00296
|
Case Summary (BLD) | | | 5/29/2009 | | |
|
|
|
|
Inspection Record Card- Bld | | | 5/29/2009 | | |
|
|
|
|
1st review completed | | | 5/29/2009 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/29/2009 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 5/29/2009 | | DONE |
Tisha Gallop
|
|
|
|
Permit Ready to Issue | | | 5/29/2009 | | DONE |
Tisha Gallop
|
|
|
|
CHANGE STATUS TO (ISS) | | | 5/29/2009 | | DONE |
Tisha Gallop
|
|
|
|
Routing Walk-In (PW Hillside) | 5/28/2009 | 5/28/2009 | 5/28/2009 | P | PASS |
Joshua Johnson
|
|
|
Footing subgrade must be approved by the applicants's geotechnical engineer prior to calling for the footing inspection
|
Routing Walk-In (Zoning) | 5/28/2009 | 5/28/2009 | 5/28/2009 | P | PASS |
Colleen T Carroll
|
|
|
|
Application received | | 5/28/2009 | | | |
|
|
|
|